Permit Application Status

PREL202415669


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PREL202415669
Electrical
Permit(s) Issued
BLOOMINGTON EVER COMMERCIAL LLC
Other
Complete electrical systems for 208-unit apt bldg; including wiring for temperature control and fire alarm.
11/27/2024
12/06/2024
09/08/2026

Locations

Permits

Permit Number: PREL202415669

Electrical
Issued
12/06/2024
09/08/2026

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Lighting Inspection Pending
Electrical Final Inspection Pending
Electrical Rough-in Inspection Partial Pass 12/10/2024 (Afternoon) 12/10/2024 (PM) 12/10/2024
underground inspection
Corrections:


Miscellaneous/Other
Comment Only
12/10/2024
Partial underground

Electrical Rough-in Inspection Partial Pass 12/11/2024 (AM) 12/11/2024
Corrections:


Miscellaneous/Other
Comment Only
12/11/2024
Partial underground

Electrical Rough-in Inspection Failed 1/13/2025 (Afternoon) 1/13/2025 (PM) 01/13/2025
Corrections:


Miscellaneous/Other
Comment Only
01/13/2025
Not ready

Electrical Rough-in Inspection Partial Pass 1/14/2025 (Morning) 1/14/2025 (AM) 01/14/2025
Corrections:


Miscellaneous/Other
Comment Only
01/14/2025
Garage underground ri

Electrical Rough-in Inspection Partial Pass 5/20/2025 (8:00 - 10:00) 5/20/2025 (AM) 05/20/2025
Corrections:


Miscellaneous/Other
Comment Only
05/20/2025
Half 5th floor RI OK

Electrical Rough-in Inspection Partial Pass 5/22/2025 (8:00 - 10:00) 5/22/2025 (AM) 05/22/2025
Corrections:


Miscellaneous/Other
Comment Only
05/22/2025
More 5th floor RI OK 5th floor not fully finished RI

Electrical Rough-in Inspection Partial Pass 6/5/2025 (10:00 - 12:00) 6/5/2025 (AM) 06/05/2025
Corrections:


Miscellaneous/Other
Comment Only
06/05/2025
2nd half 5th floor RI OK 1 fitness room, storage rooms, elevator room OK

Electrical Rough-in Inspection Partial Pass 6/12/2025 (8:00 - 10:00) 6/12/2025 (AM) 06/12/2025
Electrical Rough-in Inspection Partial Pass 6/18/2025 (8:00 - 10:00) 6/18/2025 (AM) 06/18/2025
Corrections:


Miscellaneous/Other
Comment Only
06/18/2025
East wing 4th floor RI - OK

Electrical Rough-in Inspection Partial Pass 6/23/2025 (2:30 - 3:30) 6/23/2025 (PM) 06/23/2025
Electrical Rough-in Inspection Partial Pass 6/26/2025 (8:00 - 10:00) 6/26/2025 (AM) 06/26/2025
Electrical Rough-in Inspection Partial Pass 7/3/2025 (12:30 - 2:30) 7/3/2025 (PM) 07/03/2025
Corrections:


Miscellaneous/Other
Comment Only
07/03/2025
West side 4th floor RI - OK

Electrical Rough-in Inspection Partial Pass 7/16/2025 (12:30 - 2:30) 7/16/2025 (PM) 07/16/2025
Corrections:


Miscellaneous/Other
Comment Only
07/16/2025
RI for half of 3rd floor - OK Underground for service - OK

Electrical Rough-in Inspection Partial Pass 7/30/2025 (12:30 - 2:30) 7/30/2025 (PM) 07/30/2025
Corrections:


Miscellaneous/Other
Comment Only
07/30/2025
RI for the west side of 3rd floor ok. Still waiting for service equipment.

Underground Electrical Inspection Partial Pass 8/4/2025 (2:30 - 3:30) 8/4/2025 (PM) 08/04/2025
Corrections:


Miscellaneous/Other
Comment Only
08/04/2025
Underground for parking lot lights - OK

Underground Electrical Inspection Not Ready 8/5/2025 (2:30 - 3:30) 8/5/2025 (PM) 08/05/2025
CANCELED
Electrical Rough-in Inspection Partial Pass 8/6/2025 (12:30 - 2:30) 8/6/2025 (PM) 08/06/2025
Corrections:


Miscellaneous/Other
Comment Only
08/06/2025
Underground finished for parking lot. -OK AC max Half of 2nd floor RI -OK

Underground Electrical Inspection Passed 8/7/2025 (8:00 - 10:00) 8/7/2025 (AM) 08/07/2025
Corrections:


Miscellaneous/Other
Comment Only
08/07/2025
Underground for parking lights, dedicated #8 equipment ground to each circuit

Progress Inspection Passed 8/7/2025 (8:00 - 10:00) 8/7/2025 (AM) 08/07/2025
Corrections:


Miscellaneous/Other
Comment Only
08/07/2025
New service for Ever apartments. Water main bond checked - OK Three 1000amp boards, one 800 amp, and one 600 amp. All panel boards are bonded and have a point of connection to ground. I will contact Xcel

Electrical Rough-in Inspection Partial Pass 8/18/2025 (8:00 - 10:00) 8/18/2025 (AM) 08/18/2025
Corrections:


Miscellaneous/Other
Comment Only
08/18/2025
West side 2nd floor RI OK

Electrical Rough-in Inspection Partial Pass 8/20/2025 (8:00 - 10:00) 8/20/2025 (AM) 08/20/2025
Corrections:


Miscellaneous/Other
Comment Only
08/20/2025
RI for East half of 1st floor - OK Looked at bonding for spa pool - OK

Electrical Rough-in Inspection Partial Pass 8/27/2025 (8:00 - 10:00) 8/27/2025 (AM) 08/27/2025
Corrections:


Miscellaneous/Other
Comment Only
08/27/2025
2nd half of 1st floor including common areas, bathrooms, and fitness room. - OK RI for units are complete. A few more RIs left.

Electrical Rough-in Inspection Partial Pass 10/6/2025 (8:00 - 10:00) 10/6/2025 (AM) 10/06/2025
Corrections:


Miscellaneous/Other
Comment Only
10/06/2025
New terminations for service equipment and tap boxes OK

Electrical Rough-in Inspection Passed 12/16/2025 (2:30 - 3:30) 12/16/2025 (PM) 12/16/2025
Corrections:


Miscellaneous/Other
Comment Only
12/16/2025
12/16 - Started final inspections for units on 5th floor. Rooftop units have also been inspected. OK

Progress Inspection Partial Pass 12/30/2025 (2:30 - 3:30) 12/30/2025 (PM) 12/30/2025
Corrections:


Miscellaneous/Other
Comment Only
12/30/2025
12/30 - Final Inspection for 5th floor OK Still to do on 5th: two hallway bathrooms, fitness room drinking fountain receptacle, light above elevator. All rooms OK.

Electrical Final Inspection Partial Pass 1/5/2026 (2:30 - 3:30) 1/5/2026 (PM) 01/05/2026
Corrections:


Miscellaneous/Other
Comment Only
01/05/2026
1/5/26 - Final for 4th floor West side units OK.

Electrical Final Inspection Partial Pass 1/6/2026 (2:30 - 3:30) 1/6/2026 (PM) 01/06/2026
Corrections:


Miscellaneous/Other
Comment Only
01/06/2026
1/6/26 - Final inspections for 4th floor East wing OK.

Electrical Final Inspection Partial Pass 1/12/2026 (2:30 - 3:30) 1/12/2026 (PM) 01/12/2026
Corrections:


Miscellaneous/Other
Comment Only
01/12/2026
1/12/26 - Final inspections for West side 3rd floor OK.

Electrical Final Inspection Partial Pass 1/14/2026 (2:30 - 3:30) 1/14/2026 (PM) 01/14/2026
Corrections:


Miscellaneous/Other
Comment Only
01/14/2026
1/14/26 - other half of 3rd floor OK

Electrical Final Inspection Partial Pass 2/3/2026 (8:00 - 10:00) 2/3/2026 (AM) 02/03/2026
Corrections:


Miscellaneous/Other
Comment Only
02/03/2026
2/3/26 - final for half of 2nd floor OK

Electrical Final Inspection Partial Pass 2/4/2026 (8:00 - 10:00) 2/4/2026 (AM) 02/04/2026
Corrections:


Miscellaneous/Other
Comment Only
02/04/2026
2/4/26- finals for 2nd floor OK

Electrical Final Inspection Partial Pass 3/3/2026 (Morning) 3/3/2026 (AM) 03/03/2026
Corrections:


Miscellaneous/Other
Comment Only
03/03/2026
3/3/26 - final for 1st half of 1st floor units OK

Electrical Final Inspection Partial Pass 3/4/2026 (8:00 - 10:00) 3/4/2026 (AM) 03/04/2026
Corrections:


Miscellaneous/Other
Comment Only
03/04/2026
3/4/26 - Final for other half of 1st floor and the common areas OK. 1st floor complete. Remaining areas include Pool and garage.

Electrical Final Inspection Partial Pass 3/11/2026 (2:30 - 3:30) 3/11/2026 (PM) 03/11/2026
Corrections:


Miscellaneous/Other
Comment Only
03/11/2026
3/11/26 - 1st half of garage OK.

Electrical Final Inspection Partial Pass 3/12/2026 (8:00 - 10:00) 3/12/2026 (AM) 03/12/2026
Corrections:


Miscellaneous/Other
Comment Only
03/12/2026
3/12/26 - garage final. OK waiting on pool equipment. TCO OK