PREL202415669
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Lighting Inspection | Pending | |||
| Electrical Final Inspection | Pending | |||
| Electrical Rough-in Inspection | Partial Pass | 12/10/2024 (Afternoon) | 12/10/2024 (PM) | 12/10/2024 |
| underground inspection | ||||
|
Corrections:
Miscellaneous/Other
Comment Only
12/10/2024
Partial underground
|
||||
| Electrical Rough-in Inspection | Partial Pass | 12/11/2024 (AM) | 12/11/2024 | |
|
Corrections:
Miscellaneous/Other
Comment Only
12/11/2024
Partial underground
|
||||
| Electrical Rough-in Inspection | Failed | 1/13/2025 (Afternoon) | 1/13/2025 (PM) | 01/13/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
01/13/2025
Not ready
|
||||
| Electrical Rough-in Inspection | Partial Pass | 1/14/2025 (Morning) | 1/14/2025 (AM) | 01/14/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
01/14/2025
Garage underground ri
|
||||
| Electrical Rough-in Inspection | Partial Pass | 5/20/2025 (8:00 - 10:00) | 5/20/2025 (AM) | 05/20/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
05/20/2025
Half 5th floor RI OK
|
||||
| Electrical Rough-in Inspection | Partial Pass | 5/22/2025 (8:00 - 10:00) | 5/22/2025 (AM) | 05/22/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
05/22/2025
More 5th floor RI OK
5th floor not fully finished RI
|
||||
| Electrical Rough-in Inspection | Partial Pass | 6/5/2025 (10:00 - 12:00) | 6/5/2025 (AM) | 06/05/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
06/05/2025
2nd half 5th floor RI OK
1 fitness room, storage rooms, elevator room OK
|
||||
| Electrical Rough-in Inspection | Partial Pass | 6/12/2025 (8:00 - 10:00) | 6/12/2025 (AM) | 06/12/2025 |
| Electrical Rough-in Inspection | Partial Pass | 6/18/2025 (8:00 - 10:00) | 6/18/2025 (AM) | 06/18/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
06/18/2025
East wing 4th floor RI - OK
|
||||
| Electrical Rough-in Inspection | Partial Pass | 6/23/2025 (2:30 - 3:30) | 6/23/2025 (PM) | 06/23/2025 |
| Electrical Rough-in Inspection | Partial Pass | 6/26/2025 (8:00 - 10:00) | 6/26/2025 (AM) | 06/26/2025 |
| Electrical Rough-in Inspection | Partial Pass | 7/3/2025 (12:30 - 2:30) | 7/3/2025 (PM) | 07/03/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
07/03/2025
West side 4th floor RI - OK
|
||||
| Electrical Rough-in Inspection | Partial Pass | 7/16/2025 (12:30 - 2:30) | 7/16/2025 (PM) | 07/16/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
07/16/2025
RI for half of 3rd floor - OK
Underground for service - OK
|
||||
| Electrical Rough-in Inspection | Partial Pass | 7/30/2025 (12:30 - 2:30) | 7/30/2025 (PM) | 07/30/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
07/30/2025
RI for the west side of 3rd floor ok. Still waiting for service equipment.
|
||||
| Underground Electrical Inspection | Partial Pass | 8/4/2025 (2:30 - 3:30) | 8/4/2025 (PM) | 08/04/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
08/04/2025
Underground for parking lot lights - OK
|
||||
| Underground Electrical Inspection | Not Ready | 8/5/2025 (2:30 - 3:30) | 8/5/2025 (PM) | 08/05/2025 |
| CANCELED | ||||
| Electrical Rough-in Inspection | Partial Pass | 8/6/2025 (12:30 - 2:30) | 8/6/2025 (PM) | 08/06/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
08/06/2025
Underground finished for parking lot. -OK AC max
Half of 2nd floor RI -OK
|
||||
| Underground Electrical Inspection | Passed | 8/7/2025 (8:00 - 10:00) | 8/7/2025 (AM) | 08/07/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
08/07/2025
Underground for parking lights, dedicated #8 equipment ground to each circuit
|
||||
| Progress Inspection | Passed | 8/7/2025 (8:00 - 10:00) | 8/7/2025 (AM) | 08/07/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
08/07/2025
New service for Ever apartments.
Water main bond checked - OK
Three 1000amp boards, one 800 amp, and one 600 amp.
All panel boards are bonded and have a point of connection to ground.
I will contact Xcel
|
||||
| Electrical Rough-in Inspection | Partial Pass | 8/18/2025 (8:00 - 10:00) | 8/18/2025 (AM) | 08/18/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
08/18/2025
West side 2nd floor RI OK
|
||||
| Electrical Rough-in Inspection | Partial Pass | 8/20/2025 (8:00 - 10:00) | 8/20/2025 (AM) | 08/20/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
08/20/2025
RI for East half of 1st floor - OK
Looked at bonding for spa pool - OK
|
||||
| Electrical Rough-in Inspection | Partial Pass | 8/27/2025 (8:00 - 10:00) | 8/27/2025 (AM) | 08/27/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
08/27/2025
2nd half of 1st floor including common areas, bathrooms, and fitness room. - OK
RI for units are complete.
A few more RIs left.
|
||||
| Electrical Rough-in Inspection | Partial Pass | 10/6/2025 (8:00 - 10:00) | 10/6/2025 (AM) | 10/06/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
10/06/2025
New terminations for service equipment and tap boxes OK
|
||||
| Electrical Rough-in Inspection | Passed | 12/16/2025 (2:30 - 3:30) | 12/16/2025 (PM) | 12/16/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
12/16/2025
12/16 - Started final inspections for units on 5th floor. Rooftop units have also been inspected. OK
|
||||
| Progress Inspection | Partial Pass | 12/30/2025 (2:30 - 3:30) | 12/30/2025 (PM) | 12/30/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
12/30/2025
12/30 - Final Inspection for 5th floor OK
Still to do on 5th: two hallway bathrooms, fitness room drinking fountain receptacle, light above elevator.
All rooms OK.
|
||||
| Electrical Final Inspection | Partial Pass | 1/5/2026 (2:30 - 3:30) | 1/5/2026 (PM) | 01/05/2026 |
|
Corrections:
Miscellaneous/Other
Comment Only
01/05/2026
1/5/26 - Final for 4th floor West side units OK.
|
||||
| Electrical Final Inspection | Partial Pass | 1/6/2026 (2:30 - 3:30) | 1/6/2026 (PM) | 01/06/2026 |
|
Corrections:
Miscellaneous/Other
Comment Only
01/06/2026
1/6/26 - Final inspections for 4th floor East wing OK.
|
||||
| Electrical Final Inspection | Partial Pass | 1/12/2026 (2:30 - 3:30) | 1/12/2026 (PM) | 01/12/2026 |
|
Corrections:
Miscellaneous/Other
Comment Only
01/12/2026
1/12/26 - Final inspections for West side 3rd floor OK.
|
||||
| Electrical Final Inspection | Partial Pass | 1/14/2026 (2:30 - 3:30) | 1/14/2026 (PM) | 01/14/2026 |
|
Corrections:
Miscellaneous/Other
Comment Only
01/14/2026
1/14/26 - other half of 3rd floor OK
|
||||
| Electrical Final Inspection | Partial Pass | 2/3/2026 (8:00 - 10:00) | 2/3/2026 (AM) | 02/03/2026 |
|
Corrections:
Miscellaneous/Other
Comment Only
02/03/2026
2/3/26 - final for half of 2nd floor OK
|
||||
| Electrical Final Inspection | Partial Pass | 2/4/2026 (8:00 - 10:00) | 2/4/2026 (AM) | 02/04/2026 |
|
Corrections:
Miscellaneous/Other
Comment Only
02/04/2026
2/4/26- finals for 2nd floor OK
|
||||
| Electrical Final Inspection | Partial Pass | 3/3/2026 (Morning) | 3/3/2026 (AM) | 03/03/2026 |
|
Corrections:
Miscellaneous/Other
Comment Only
03/03/2026
3/3/26 - final for 1st half of 1st floor units OK
|
||||
| Electrical Final Inspection | Partial Pass | 3/4/2026 (8:00 - 10:00) | 3/4/2026 (AM) | 03/04/2026 |
|
Corrections:
Miscellaneous/Other
Comment Only
03/04/2026
3/4/26 - Final for other half of 1st floor and the common areas OK.
1st floor complete.
Remaining areas include Pool and garage.
|
||||
| Electrical Final Inspection | Partial Pass | 3/11/2026 (2:30 - 3:30) | 3/11/2026 (PM) | 03/11/2026 |
|
Corrections:
Miscellaneous/Other
Comment Only
03/11/2026
3/11/26 - 1st half of garage OK.
|
||||
| Electrical Final Inspection | Partial Pass | 3/12/2026 (8:00 - 10:00) | 3/12/2026 (AM) | 03/12/2026 |
|
Corrections:
Miscellaneous/Other
Comment Only
03/12/2026
3/12/26 - garage final. OK waiting on pool equipment. TCO OK
|
||||