PREL202501396
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Progress Inspection | Pending | |||
Electrical Rough-in Inspection | Partial Pass | 3/27/2025 (7:00 - 8:00) | 3/27/2025 (AM) | 03/27/2025 |
Corrections:
Miscellaneous/Other
Comment Only
03/27/2025
Wall ri
|
||||
Electrical Rough-in Inspection | Partial Pass | 3/31/2025 (Morning) | 3/31/2025 (AM) | 03/31/2025 |
Corrections:
Miscellaneous/Other
Comment Only
03/31/2025
Meeting in site
|
||||
Electrical Rough-in Inspection | Partial Pass | 4/16/2025 (8:00 - 10:00) | 4/16/2025 (AM) | 04/16/2025 |
Corrections:
Miscellaneous/Other
Comment Only
04/16/2025
Hard lid ceiling ri
|
||||
Electrical Rough-in Inspection | Failed | 5/16/2025 (12:30 - 2:30) | 5/16/2025 (PM) | 05/16/2025 |
Corrections:
Miscellaneous/Other
Comment Only
05/16/2025
Ceilings not ready - open boxes, whips hanging with wire nuts, pinched wire out of box
|
||||
Electrical Rough-in Inspection | Passed | 5/19/2025 (8:00 - 10:00) | 5/19/2025 (AM) | 05/19/2025 |
Corrections:
Miscellaneous/Other
Comment Only
05/19/2025
Ceiling ri
|
||||
Above Ceiling Inspection | Passed | 5/21/2025 (8:00 - 10:00) | 5/21/2025 (AM) | 05/21/2025 |
Corrections:
Miscellaneous/Other
Comment Only
05/21/2025
Ceiling ri
|
||||
Electrical Rough-in Inspection | Partial Pass | 7/17/2025 (8:00 - 10:00) | 7/17/2025 (AM) | 07/17/2025 |
Corrections:
Miscellaneous/Other
Comment Only
07/17/2025
Meeting on site
|
||||
Progress Inspection | Failed | 7/18/2025 (12:30 - 2:30) | 7/18/2025 (PM) | 07/18/2025 |
Corrections:
Miscellaneous/Other
Comment Only
07/18/2025
Could not verify any listing marks for bathroom stall door lights that came from Germany per NEC 410.6
|
||||
Electrical Final Inspection | Passed | 7/30/2025 (10:00 - 12:00) | 7/30/2025 (AM) | 07/30/2025 |