PREL202501478
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Electrical Final Inspection | Pending | |||
| Electrical Rough-in Inspection | Partial Pass | 2/26/2025 (Morning) | 2/26/2025 (AM) | 02/26/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
02/26/2025
Partial wall ri
|
||||
| Electrical Rough-in Inspection | Partial Pass | 3/5/2025 (10:00 - 12:00) | 3/5/2025 (AM) | 03/05/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
03/05/2025
Partial ri
|
||||
| Electrical Rough-in Inspection | Partial Pass | 3/12/2025 (10:00 - 12:00) | 3/12/2025 (AM) | 03/12/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
03/12/2025
Partial wall ri
|
||||
| Electrical Rough-in Inspection | Partial Pass | 10/29/2025 (10:00 - 12:00) | 10/29/2025 (AM) | 10/29/2025 |
| Electrical Rough-in Inspection | Passed | 12/12/2025 | ||
|
Corrections:
Miscellaneous/Other
Comment Only
12/12/2025
Ceilings on first and second floor hallways ri
|
||||