PREL202501516
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Electrical Final Inspection | Pending | |||
|
Corrections:
Miscellaneous/Other
Outstanding
03/04/2026
9-30-25 partial pass of limited access areas.
Electrician still has some boxes to blank off and a couple of emerg/exit signs to install. Most of the lights in these areas are installed
|
||||
|
Miscellaneous/Other
Outstanding
03/04/2026
Area C:
KO plug and cover in Referee Room
Upper Area C:
Water Cooler GFCI needed
Attach 4 square box in Floor hockey area
Area D:
Blank off 208 volt receptacles-upper level
Need lock for Parking lot lighting panel(exposed live wires inside) -
Upper level
Area E:
Zamboni room-Garage Door Opener needs disconnect
Roller Door needs disconnect
Exterior light 4 square blank
Area E Bobcat room-Garage Door Opener needs a disconnect
Area E Zamboni repair room: Garage Door Opener needs disconnect
Area E tool room: Need KO plug on transformer
Zamboni Room #1-missing 4 square blank
Zamboni Room #2-Need disconnects for Garage door opener, roller door and heater
Mech Room in Area B- heater needs disconnect
Area E, 40-3 room--panel clearance still needs to be addressed
|
||||
| Electrical Rough-in Inspection | Partial Pass | 4/7/2025 (Morning) | 4/7/2025 (AM) | 04/07/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
04/07/2025
Partial underground
|
||||
| Electrical Rough-in Inspection | Partial Pass | 5/5/2025 (12:30 - 2:30) | 5/5/2025 (PM) | 05/05/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
05/05/2025
Underground ri
|
||||
| Electrical Rough-in Inspection | Partial Pass | 5/12/2025 | 5/12/2025 (AM) | 05/12/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
05/12/2025
Meeting on site
|
||||
| Electrical Rough-in Inspection | Partial Pass | 5/19/2025 | 5/19/2025 (PM) | 05/19/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
05/19/2025
Meeting on site
|
||||
| Electrical Rough-in Inspection | Partial Pass | 5/23/2025 | 5/23/2025 (AM) | 05/23/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
05/23/2025
Walk through
|
||||
| Electrical Rough-in Inspection | Partial Pass | 6/20/2025 (12:30 - 2:30) | 6/20/2025 (PM) | 06/20/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
06/20/2025
Walkthrough
|
||||
| Electrical Rough-in Inspection | Partial Pass | 6/26/2025 (8:00 - 10:00) | 6/26/2025 (AM) | 06/26/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
06/26/2025
Meeting on site
|
||||
| Electrical Rough-in Inspection | Partial Pass | 7/17/2025 (8:00 - 10:00) | 7/17/2025 (AM) | 07/17/2025 |
|
Corrections:
Miscellaneous/Other
Carried Forward
07/17/2025
Stud wall RI in the following areas ok:
A
B mezzanine
C and D mezzanine.
|
||||
| Electrical Rough-in Inspection | Partial Pass | 07/24/2025 | ||
|
Corrections:
Miscellaneous/Other
Carried Forward
07/24/2025
Stud wall RI in the following areas ok:
A
B mezzanine
C and D mezzanine.
|
||||
|
Miscellaneous/Other
Comment Only
07/24/2025
7-24-25
UG for parking lot poles
|
||||
| Electrical Rough-in Inspection | Partial Pass | 8/5/2025 (10:00 - 12:00) | 8/5/2025 (AM) | 08/05/2025 |
|
Corrections:
Miscellaneous/Other
Carried Forward
08/05/2025
Stud wall RI in the following areas ok:
A
B mezzanine
C and D mezzanine.
|
||||
|
Miscellaneous/Other
Comment Only
08/05/2025
8-5-25 Switchgear and CT cab only
From Main breakers in switchgear to sub panels not done
|
||||
| Electrical Rough-in Inspection | Partial Pass | 9/24/2025 (2:30 - 3:30) | 9/24/2025 (PM) | 09/24/2025 |
|
Corrections:
Miscellaneous/Other
Carried Forward
09/24/2025
Stud wall RI in the following areas ok:
A
B mezzanine
C and D mezzanine.
|
||||
|
Miscellaneous/Other
Carried Forward
09/24/2025
Above ceiling- Hallway A and Hallway D and the bathrooms adjacent to these hallways
|
||||
| Electrical Final Inspection | Partial Pass | 9/30/2025 (12:30 - 2:30) | 9/30/2025 (PM) | 09/30/2025 |
|
Corrections:
Miscellaneous/Other
Carried Forward
09/30/2025
9-30-25 partial pass of limited access areas.
Electrician still has some boxes to blank off and a couple of emerg/exit signs to install. Most of the lights in these areas are installed
|
||||
| Electrical Rough-in Inspection | Partial Pass | 10/30/2025 (10:00 - 12:00) | 10/30/2025 (AM) | 10/30/2025 |
|
Corrections:
Miscellaneous/Other
Carried Forward
10/30/2025
Stud wall RI in the following areas ok:
A
B mezzanine
C and D mezzanine.
|
||||
|
Miscellaneous/Other
Carried Forward
10/30/2025
Above ceiling- Hallway A and Hallway D and the bathrooms adjacent to these hallways
|
||||
|
Miscellaneous/Other
Comment Only
10/30/2025
10-30-2025
Ceilings-ok
Up area B mez
concessions
offices
|
||||
| Electrical Final Inspection | Partial Pass | 2/26/2026 (Morning) | 2/26/2026 (AM) | 02/26/2026 |
|
Corrections:
Miscellaneous/Other
Carried Forward
10/30/2025
9-30-25 partial pass of limited access areas.
Electrician still has some boxes to blank off and a couple of emerg/exit signs to install. Most of the lights in these areas are installed
|
||||
|
Miscellaneous/Other
Comment Only
10/30/2025
|
||||
|
Miscellaneous/Other
Outstanding
02/26/2026
2-26-2026 partial
Area A
Electrical room A- missing some breaker blanks
Red breaker locks for 2 FA panels missing
Area D
Clearance to Electrical panel behind roof access stairs needs to be evaluated.
Area B
Girls Locker room sign(Jaguars)needs to be powered without an extension cord
Water coolers need GFCI protection
Also need updated panel schedules
|
||||
| Electrical Final Inspection | Partial Pass | 3/3/2026 (12:30 - 2:30) | 3/3/2026 (PM) | 03/04/2026 |
|
Corrections:
Miscellaneous/Other
Carried Forward
03/04/2026
9-30-25 partial pass of limited access areas.
Electrician still has some boxes to blank off and a couple of emerg/exit signs to install. Most of the lights in these areas are installed
|
||||
|
Miscellaneous/Other
Carried Forward
03/04/2026
Area C:
KO plug and cover in Referee Room
Upper Area C:
Water Cooler GFCI needed
Attach 4 square box in Floor hockey area
Area D:
Blank off 208 volt receptacles-upper level
Need lock for Parking lot lighting panel(exposed live wires inside) -
Upper level
Area E:
Zamboni room-Garage Door Opener needs disconnect
Roller Door needs disconnect
Exterior light 4 square blank
Area E Bobcat room-Garage Door Opener needs a disconnect
Area E Zamboni repair room: Garage Door Opener needs disconnect
Area E tool room: Need KO plug on transformer
Zamboni Room #1-missing 4 square blank
Zamboni Room #2-Need disconnects for Garage door opener, roller door and heater
Mech Room in Area B- heater needs disconnect
Area E, 40-3 room--panel clearance still needs to be addressed
|
||||