PREL202502112
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Electrical Rough-in Inspection | Passed | 3/11/2025 (Morning) | 3/11/2025 (AM) | 03/11/2025 |
Corrections:
Miscellaneous/Other
Outstanding
03/11/2025
Contractor said he would do ceiling inspection at the final inspection
|
||||
Electrical Rough-in Inspection | Passed | 8/13/2025 (8:00 - 10:00) | 8/13/2025 (AM) | 08/13/2025 |
Corrections:
Miscellaneous/Other
Outstanding
08/13/2025
Floor outlet RI -OK
|
||||
Electrical Rough-in Inspection | Passed | 8/19/2025 (12:30 - 2:30) | 8/19/2025 (PM) | 08/19/2025 |
Electrical Final Inspection | Passed | 8/19/2025 (12:30 - 2:30) | 8/19/2025 (PM) | 08/19/2025 |