PREL202503041
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Electrical Rough-in Inspection | Partial Pass | 7/3/2025 (10:00 - 12:00) | 7/3/2025 (AM) | 07/03/2025 |
Corrections:
Miscellaneous/Other
Comment Only
07/03/2025
Underground for track, press box, and concessions pull boxes. High voltage and control circuits separated. - OK
Next visit for more underground on lights and power for scoreboard.
|
||||
Electrical Rough-in Inspection | Partial Pass | 7/9/2025 (12:30 - 2:30) | 7/9/2025 (PM) | 07/09/2025 |
Corrections:
Miscellaneous/Other
Comment Only
07/09/2025
Inspection for underground for new service going in. New 480v panel. New transformer. New 120/240 panel from transformer. Fed from main gear in school that is fused.
New service bonded to rebar grid encased in concrete pad.
|
||||
Electrical Rough-in Inspection | Partial Pass | 7/17/2025 (10:00 - 12:00) | 7/17/2025 (AM) | 07/17/2025 |
Corrections:
Miscellaneous/Other
Comment Only
07/17/2025
Concession Stands ceiling RI - 5 lights 0-10v dimming. 1 Heater. -OK
|
||||
Electrical Final Inspection | Partial Pass | 8/21/2025 (2:30 - 3:30) | 8/21/2025 (PM) | 08/21/2025 |
Corrections:
Miscellaneous/Other
Comment Only
08/21/2025
Partial Final for Kennedy field.
Lights have been wired and are UL compliant. Each pole has its own concrete encased-electrode. - OK
Press box is wired with 100 amp sub panel. All receptacles are gfci protected.
Concession stand is 95% complete and waiting on water main bonding.
Scoreboard is temp wired as new one will not be arriving until October.
|
||||
Electrical Final Inspection | Partial Pass | 9/18/2025 (12:30 - 2:30) | 9/18/2025 (PM) | 09/18/2025 |
Corrections:
Miscellaneous/Other
Comment Only
09/18/2025
Concession stand final OK
Leaving permit open for scoreboard sign coming next month
|
||||
Electrical Final Inspection | Passed | 10/6/2025 (10:00 - 12:00) | 10/6/2025 (AM) | 10/06/2025 |
Corrections:
Miscellaneous/Other
Comment Only
10/06/2025
Scoreboard for Kennedy high school OK. Properly grounded to beam and ground rod. Transformer is grounded and has disconnect means. Service receptacle installed. This concludes the job
|