PREL202503467
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Electrical Rough-in Inspection | Failed | 4/14/2025 (10:00 - 12:00) | 4/14/2025 (AM) | 04/14/2025 |
Corrections:
Miscellaneous/Other
Comment Only
04/14/2025
Bidet has a heater per general contractor which needs a dedicated 20 amp circuit
|
||||
Electrical Rough-in Inspection | Passed | 4/15/2025 (12:30 - 2:30) | 4/15/2025 (PM) | 04/15/2025 |
Corrections:
Miscellaneous/Other
Comment Only
04/15/2025
Master bathroom ri
Bidet circuit added
|
||||
Electrical Final Inspection | Passed | 6/4/2025 (12:30 - 2:30) | 6/4/2025 (PM) | 06/04/2025 |