PREL202504715
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Electrical Final Inspection | Passed | 6/17/2025 (10:00 - 12:00) | 6/17/2025 (AM) | 06/17/2025 |
Corrections:
Miscellaneous/Other
Comment Only
06/17/2025
1 MW generator install -OK
5 new ATS installed and grounded - OK
|