PREL202506549
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Lighting Inspection | Pending | |||
| Electrical Final Inspection | Not Ready | 7/15/2025 (10:00 - 12:00) | 7/15/2025 (AM) | 07/15/2025 |
|
Corrections:
Miscellaneous/Other
Carried Forward
07/15/2025
The reason this is not ready is that I need someone with a ladder and to show me what work was completed
|
||||
| Electrical Final Inspection | Passed | 8/4/2025 (10:00 - 12:00) | 8/4/2025 (AM) | 08/04/2025 |
|
Corrections:
Miscellaneous/Other
Outstanding
07/15/2025
The reason this is not ready is that I need someone with a ladder and to show me what work was completed
|
||||