PREL202507439
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Electrical Rough-in Inspection | Pending | |||
Corrections:
Miscellaneous/Other
Outstanding
07/10/2025
Waiting for NRTL listing of the tools
|
||||
Electrical Final Inspection | Pending | |||
Corrections:
Miscellaneous/Other
Outstanding
07/10/2025
Waiting for NRTL listing of the tools
|
||||
Electrical Rough-in Inspection | Partial Pass | 7/10/2025 (8:00 - 10:00) | 7/10/2025 (AM) | 07/10/2025 |
Corrections:
Miscellaneous/Other
Carried Forward
07/10/2025
Waiting for NRTL listing of the tools
|
||||
Electrical Final Inspection | Partial Pass | 7/10/2025 (8:00 - 10:00) | 7/10/2025 (AM) | 07/10/2025 |
Corrections:
Miscellaneous/Other
Carried Forward
07/10/2025
Waiting for NRTL listing of the tools
|