PREL202508254
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Electrical Final Inspection | Pending | |||
Electrical Rough-in Inspection | Pending | |||
Electrical Rough-in Inspection | Failed | 7/18/2025 (10:00 - 12:00) | 7/18/2025 (AM) | 07/18/2025 |
Corrections:
Miscellaneous/Other
Comment Only
07/18/2025
Called electrician to meet on site when I got down to first floor B wing nobody was there he called and will reschedule
|
||||
Electrical Rough-in Inspection | Partial Pass | 7/28/2025 (10:00 - 12:00) | 7/28/2025 (AM) | 07/28/2025 |
Corrections:
Miscellaneous/Other
Comment Only
07/28/2025
Called for underground inspection floor is poured before any inspections
|