PREL202508254
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Electrical Rough-in Inspection | Failed | 7/18/2025 (10:00 - 12:00) | 7/18/2025 (AM) | 07/18/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
07/18/2025
Called electrician to meet on site when I got down to first floor B wing nobody was there he called and will reschedule
|
||||
| Electrical Rough-in Inspection | Partial Pass | 7/28/2025 (10:00 - 12:00) | 7/28/2025 (AM) | 07/28/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
07/28/2025
Called for underground inspection floor is poured before any inspections
|
||||
| Electrical Rough-in Inspection | Passed | 10/30/2025 (12:30 - 2:30) | 10/30/2025 (PM) | 10/30/2025 |
| Electrical Final Inspection | Passed | 10/30/2025 (12:30 - 2:30) | 10/31/2025 (PM) | 10/30/2025 |