Permit Application Status

PREL202509100


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PREL202509100
Electrical
Finaled
MOAC MALL HOLDINGS LLC
Alteration/Repair/Replace
ELECTRICAL TENANT BUILDOUT & FEES HAAGEN DAZ
07/29/2025
07/30/2025
05/03/2026
11/04/2025

Locations

Permits

Permit Number: PREL202509100

Electrical
Finaled
07/30/2025
05/03/2026

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Electrical Rough-in Inspection Passed 8/18/2025 (12:30 - 2:30) 8/18/2025 (PM) 08/18/2025
Corrections:


Miscellaneous/Other
Comment Only
08/18/2025
Ceiling inspection for Haagen Daz. New LED recessed lighting. - Ok Check disconnect for LED storefront sign on final. Check Available fault current on final.

Electrical Final Inspection Partial Pass 10/29/2025 (8:00 - 10:00) 10/29/2025 (AM) 10/29/2025
Corrections:


Miscellaneous/Other
Comment Only
10/29/2025
Hagen Daz final Water heater still needs to be wired. Breaker within sight will qualify as disconnect Signs still need to be installed Look at translucent menu boards

Electrical Final Inspection Passed 11/4/2025 (12:30 - 2:30) 11/4/2025 (PM) 11/04/2025
Corrections:


Miscellaneous/Other
Comment Only
11/04/2025
Water heater wired signs installed Menu boards were plug in