| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Electrical Rough-in Inspection | Partial Pass | 9/16/2025 (3:30 - 4:00) | 9/16/2025 (PM) | 09/16/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/16/2025
Walls for MOA SAMSUNG. - OK There will also be floor conduit and boxes for device tables throughout the room.
Still need a ceiling inspection.
|
||||
| Electrical Rough-in Inspection | Passed | 9/26/2025 (10:00 - 12:00) | 9/26/2025 (AM) | 09/26/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/26/2025
Ceiling inspection for MOA Samsung ok. LED recessed lighting is ok and supported. RI for fire alarm ok. Sign power and disconnect means are present. Will be hard lid. Temp power will be accessible after install for removal.
|
||||
| Electrical Final Inspection | Passed | 10/16/2025 (10:00 - 12:00) | 10/16/2025 (AM) | 10/16/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
10/16/2025
Samsung MOA final OK
All lights are listed as well as the storefront signs.
Panels have all labels and calculations
Receptacles and device tables are code compliant.
|
||||