PRFD201701925
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Progress Inspection | Partial Pass | 5/9/2017 (8:00 - 10:00) | 5/9/2017 | 05/09/2017 |
pre-construction meeting | ||||
Corrections:
Miscellaneous/Other
Comment Only
05/09/2017
Onsite inspection with job sup. Went over inspections and plans. Dirt work in process, footings to be about a week out yet.
|
||||
Footing Inspection | Partial Pass | 5/22/2017 (12:30 - 2:30) | 05/23/2017 | |
Corrections:
Miscellaneous/Other
Comment Only
05/23/2017
Strip footing from grids A-D and 1-5 on north side. All is highlighted on plans. Rebar in footing as per plan, and the hook dowels are not in place, but are pending engineer approval to wet set. Will recheck at inspection set on 5/24.
|
||||
Footing Inspection | Partial Pass | 05/24/2017 | ||
Corrections:
Miscellaneous/Other
Comment Only
05/24/2017
Hook dowels in place at the footing sections that were inspected on 5/23/17 (phase 1).
|
||||
Footing Inspection | Partial Pass | 6/5/2017 (12:30 - 2:30) | 6/5/2017 | 06/05/2017 |
Corrections:
Miscellaneous/Other
Comment Only
06/05/2017
Strip footings and 2 piers from grid "A" to "D" approx. line 9&8 . This is labeled as phase II of footings on the plans. Approved for concrete placement.
|
||||
Footing Inspection | Partial Pass | 6/20/2017 (12:30 - 2:30) | 6/20/2017 | 06/20/2017 |
Corrections:
Miscellaneous/Other
Comment Only
06/20/2017
Progress only, no inspection needed
|
||||
Footing Inspection | Partial Pass | 6/21/2017 (12:30 - 2:30) | 6/21/2017 | 06/21/2017 |
Corrections:
Miscellaneous/Other
Comment Only
06/21/2017
3rd and last section of perimeter footings and elevator pit slab rebar, as per plans. Approved for concrete placement.
|
||||
Footing Inspection | Partial Pass | 6/26/2017 (10:00 - 12:00) | 6/26/2017 | 06/26/2017 |
Corrections:
Miscellaneous/Other
Comment Only
06/26/2017
Elevator pit rebar for poured walls....approved.
Contractor is wet sticking the the bars for CMU.
|
||||
Footing Inspection | Partial Pass | 7/12/2017 (12:30 - 2:30) | 7/12/2017 | 07/12/2017 |
Corrections:
Miscellaneous/Other
Comment Only
07/12/2017
5 pads along line "B" at interior. 4 pads along line "C" on interior... approved for concrete.
Water proofing, R10 foam insulation and draintile system viewed on perimeter of bldg. approved for backfill.
|
||||
Footing Inspection | Partial Pass | 8/11/2017 (12:30 - 2:30) | 8/11/2017 | 08/11/2017 |
Corrections:
Miscellaneous/Other
Comment Only
08/11/2017
Footings for stoop and trash room approved.
|
||||
Building Final Inspection | Passed | 07/03/2018 | ||
Corrections:
Miscellaneous/Other
Comment Only
07/03/2018
All foundation work was completed, pool foundation already inspected. See Building permit 201700986
|