Summary

PRFD201701925
Foundation
Finaled
PHD PROPERTIES LLC
New
Not Required
Not Required
Excavation, utilities, footings/foundation, pre-cast
03/29/2017
04/24/2017
12/30/2018
07/03/2018

Locations

Permits

Permit Number: PRFD201701925

Foundation
Finaled
04/24/2017
12/30/2018

Permit Number: PRFD201701925

Utility
VOID

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Progress Inspection Partial Pass 5/9/2017 (8:00 - 10:00) 5/9/2017 05/09/2017
pre-construction meeting
Corrections:


Miscellaneous/Other
Comment Only
05/09/2017
Onsite inspection with job sup. Went over inspections and plans. Dirt work in process, footings to be about a week out yet.

Footing Inspection Partial Pass 5/22/2017 (12:30 - 2:30) 05/23/2017
Corrections:


Miscellaneous/Other
Comment Only
05/23/2017
Strip footing from grids A-D and 1-5 on north side. All is highlighted on plans. Rebar in footing as per plan, and the hook dowels are not in place, but are pending engineer approval to wet set. Will recheck at inspection set on 5/24.

Footing Inspection Partial Pass 05/24/2017
Corrections:


Miscellaneous/Other
Comment Only
05/24/2017
Hook dowels in place at the footing sections that were inspected on 5/23/17 (phase 1).

Footing Inspection Partial Pass 6/5/2017 (12:30 - 2:30) 6/5/2017 06/05/2017
Corrections:


Miscellaneous/Other
Comment Only
06/05/2017
Strip footings and 2 piers from grid "A" to "D" approx. line 9&8 . This is labeled as phase II of footings on the plans. Approved for concrete placement.

Footing Inspection Partial Pass 6/20/2017 (12:30 - 2:30) 6/20/2017 06/20/2017
Corrections:


Miscellaneous/Other
Comment Only
06/20/2017
Progress only, no inspection needed

Footing Inspection Partial Pass 6/21/2017 (12:30 - 2:30) 6/21/2017 06/21/2017
Corrections:


Miscellaneous/Other
Comment Only
06/21/2017
3rd and last section of perimeter footings and elevator pit slab rebar, as per plans. Approved for concrete placement.

Footing Inspection Partial Pass 6/26/2017 (10:00 - 12:00) 6/26/2017 06/26/2017
Corrections:


Miscellaneous/Other
Comment Only
06/26/2017
Elevator pit rebar for poured walls....approved. Contractor is wet sticking the the bars for CMU.

Footing Inspection Partial Pass 7/12/2017 (12:30 - 2:30) 7/12/2017 07/12/2017
Corrections:


Miscellaneous/Other
Comment Only
07/12/2017
5 pads along line "B" at interior. 4 pads along line "C" on interior... approved for concrete. Water proofing, R10 foam insulation and draintile system viewed on perimeter of bldg. approved for backfill.

Footing Inspection Partial Pass 8/11/2017 (12:30 - 2:30) 8/11/2017 08/11/2017
Corrections:


Miscellaneous/Other
Comment Only
08/11/2017
Footings for stoop and trash room approved.

Building Final Inspection Passed 07/03/2018
Corrections:


Miscellaneous/Other
Comment Only
07/03/2018
All foundation work was completed, pool foundation already inspected. See Building permit 201700986