Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Progress Inspection | Pending | |||
Footing Inspection | Not Ready | 8/28/2018 (10:00 - 12:00) | 8/28/2018 | 08/28/2018 |
Corrections:
Miscellaneous/Other
Comment Only
08/28/2018
Contractor working on soil compaction to make the density ratings in order to start forming footings. No footings ready for inspection at this time.
|
||||
Footing Inspection | Partial Pass | 8/31/2018 (8:00 - 10:00) | 8/31/2018 | 08/31/2018 |
Corrections:
Miscellaneous/Other
Comment Only
08/31/2018
Strip footings and pads on west side... approved for concrete placement.
|
||||
Footing Inspection | Partial Pass | 9/5/2018 (2:30 - 3:30) | 9/5/2018 | 09/05/2018 |
Corrections:
Miscellaneous/Other
Comment Only
09/05/2018
Rebar, Footings / pads on the south perimeter grid line approved for concrete placement. Inbeds are being placed at time of inspection.
|
||||
Footing Inspection | Partial Pass | 9/7/2018 (12:30 - 2:30) | 9/7/2018 | 09/07/2018 |
Corrections:
Miscellaneous/Other
Comment Only
09/07/2018
Footings , pads, and rebar, at grids 15-16 and up to line “D” approved for concrete placement.
|
||||
Footing Inspection | Partial Pass | 9/10/2018 (12:30 - 2:30) | 9/10/2018 | 09/10/2018 |
Corrections:
Miscellaneous/Other
Comment Only
09/10/2018
4 - f6.5x13 pad footings on line C , grids 8-11. Approved for concrete.
|
||||
Footing Inspection | Partial Pass | 09/11/2018 | ||
Corrections:
Miscellaneous/Other
Comment Only
09/11/2018
Footings and rebar line 4, grids B.3, D, & F. Approved for concrete placement.
|
||||
Footing Inspection | Partial Pass | 9/12/2018 (12:30 - 2:30) | 9/12/2018 | 09/12/2018 |
Corrections:
Miscellaneous/Other
Comment Only
09/12/2018
Pad footings... 3- f6.5x13.0 pads at line C betweengrids 12-14.
2- f7.0 pads at lines 8 & 9.
Pads on grid 3 from lines F-M, 1-f8.0, 1- f7.5, & 6- f6 pads. All approved for concrete placement.
|
||||
Footing Inspection | Partial Pass | 9/13/2018 (10:00 - 12:00) | 9/13/2018 | 09/13/2018 |
Corrections:
Miscellaneous/Other
Outstanding
09/13/2018
Footings and pads on lines 1 & 2 from N - P. Approved for concrete placement.
|
||||
Footing Inspection | Partial Pass | 9/17/2018 (10:00 - 12:00) | 9/17/2018 | 09/17/2018 |
Corrections:
Miscellaneous/Other
Comment Only
09/17/2018
Line 12 - 16 grids “F -“G.7” footing/ pads and rebar... approved for concrete placement.
|
||||
Footing Inspection | Partial Pass | 9/18/2018 (12:30 - 2:30) | 9/18/2018 | 09/18/2018 |
Corrections:
Miscellaneous/Other
Comment Only
09/18/2018
Pad footings grids H - N lines 4.3 & 4.2
Approved for concrete placement
|
||||
Footing Inspection | Partial Pass | 09/21/2018 | ||
Corrections:
Miscellaneous/Other
Comment Only
09/21/2018
Footing/pads ... elevator. Grids 5-6 lines C-E.
Approved for concrete placement.
|
||||
Footing Inspection | Partial Pass | 9/25/2018 (8:00 - 10:00) | 9/25/2018 | 09/25/2018 |
Corrections:
Miscellaneous/Other
Comment Only
09/25/2018
Footings and pads grids J- 6.9 and remaining line F.
Approved for concrete placement.
|
||||
Footing Inspection | Partial Pass | 9/26/2018 (2:30 - 3:30) | 9/26/2018 | 09/25/2018 |
Corrections:
Miscellaneous/Other
Comment Only
09/25/2018
Columns at lines C,D,E,F from grids 5.5-7 approved for concrete placement.
|
||||
Footing Inspection | Partial Pass | 09/27/2018 | ||
Corrections:
Miscellaneous/Other
Comment Only
09/27/2018
Footings and pads on lines “O” & “P” from grids 2.9 - 6.9. Grid line 6.9 from “K” -“P” footings and pads. All approved for concrete placement.
|
||||
Footing Inspection | Partial Pass | 10/5/2018 (8:00 - 10:00) | 10/5/2018 | 10/05/2018 |
Corrections:
Miscellaneous/Other
Comment Only
10/05/2018
4 footing pads for the entry overhang. Approved for concrete placement.
|
||||
Footing Inspection | Passed | 12/05/2018 | ||
Corrections:
Miscellaneous/Other
Comment Only
12/05/2018
Underslab poly for stairwells and last section of north end of building, approved. See permit 201711598 for all other remaining inspections.
|
||||
Building Final Inspection | Passed | 12/05/2018 | ||
Corrections:
Miscellaneous/Other
Comment Only
12/05/2018
Final for foundation approved . See permit for the building buildout for remaining inspections.
|
||||
Progress Inspection | Partial Pass | 03/27/2019 | ||
Corrections:
Miscellaneous/Other
Comment Only
03/27/2019
Construction meeting about exiting signage and locations for placement. Also went over Knox box locations, and building address locations of placement.
|