Permit Application Status

PRFD201805372


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRFD201805372
Foundation
Finaled
MSP BLOOMINGTON LLC
New
Not Required
Foundation for new Whirlyball facility - this is a phased project, applying for Grading, Foundation, Structural and Builidng permits all separately.
06/04/2018
08/07/2018
02/03/2019

Locations

Permits

Permit Number: PRFD201805372

Foundation
Finaled
08/07/2018
02/03/2019

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Footing Inspection Partial Pass 8/27/2018 (12:30 - 2:30) 8/27/2018 08/27/2018
Corrections:


Miscellaneous/Other
Comment Only
08/27/2018
Perimeter footings... North side, west side, and south side up to grid line ā€œDā€. Approved for concrete placement.

Footing Inspection Partial Pass 8/29/2018 (12:30 - 2:30) 8/29/2018 08/29/2018
Corrections:


Miscellaneous/Other
Comment Only
08/29/2018
2- f-9 pads, 1-f/6 pad, the remaining strip footings on south side perimeter, and 3/4 of the perimeter footings on east side. Elevator pad is being lined with membrane, rebar is as per plan. The drain being used is a side wall drain and will be installed with the wall sections. Approx 1/4 of east perimeter footing that ties to the north perimeter footing is remaining to be set with the next pour.

Footing Inspection Passed 8/30/2018 (12:30 - 2:30) 8/30/2018 08/30/2018
Moved 08/28/2018 inspection to 08/30/2018 per contractor - rained out. Emailed Jon and called. ajacobson 08/28/2018 8:29 AM
Corrections:


Miscellaneous/Other
Comment Only
08/30/2018
Remaining strip footing on east side, and the last four pad footings. Pier by elevator pad and 2 stem walls on north footing .... all approved for concrete.

Progress Inspection Partial Pass 9/26/2018 (12:30 - 2:30) 9/26/2018 09/26/2018
Corrections:


Miscellaneous/Other
Comment Only
09/26/2018
Rebar in place for the masonry walls of elevator . Approved.

Building Final Inspection Passed 7/23/2019 9/30/2019 (PM) 07/23/2019
07/23/2019: Finalled on 7/23/19 per Jon Aaron. dheile 09/30/2019 12:36 PM
Corrections:


Miscellaneous/Other
Comment Only
07/23/2019
This portion of the work is completed, see permit 201810629 for remaining inspections with this new build.