Summary

PRFD201812533
Foundation
Finaled
BLOOMINGTON CENTRAL STATION LLC
Other
Not Required
Foundation portion of the project for the ramp and the building.
10/12/2018
11/19/2018
09/25/2021
03/29/2021

Locations

Permits

Permit Number: PRFD201812533

Foundation
Finaled
11/19/2018
09/25/2021

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Progress Inspection Passed w/ Conditions 11/27/2018 (10:00 - 12:00) 11/27/2018 (AM) 11/27/2018
Corrections:


Miscellaneous/Other
Comment Only
11/27/2018
Strip footing and pad footings north east corner job forman. Dave will send pics of completed forming all iron on site along with insulated blankets. Ground sand temp 18 degrees. Special inspector coming at 1 PM today to inspect prior to pour.

Progress Inspection Partial Pass 11/28/2018 (12:30 - 2:30) 11/28/2018 (PM) 11/28/2018
Corrections:


Miscellaneous/Other
Comment Only
11/28/2018
Rebar and footings.... Line Ra from grids r-5 to East of N17 Line Rb grids5.5 to N16 Line Eb to Ec at line R7 Footings are freshly dug and compacted, soil tested and frost blankets are being used. Approved for concrete placement.

Progress Inspection Partial Pass 11/29/2018 (12:30 - 2:30) 11/29/2018 (PM) 11/29/2018
Corrections:


Miscellaneous/Other
Comment Only
11/29/2018
Footing pads and rebar as per plan design at grid line Rb from line n16 to n13.5 Approved for concrete placement.

Progress Inspection Partial Pass 11/30/2018 (12:30 - 2:30) 11/30/2018 (PM) 11/30/2018
Corrections:


Miscellaneous/Other
Comment Only
11/30/2018
Line e-D and e-E... from lines s-19 to line s22.5. Rebar and footing approved for concrete placement.

Progress Inspection Not Ready 12/3/2018 (12:30 - 2:30) 12/3/2018 (PM) 12/03/2018
Corrections:


Miscellaneous/Other
Comment Only
12/03/2018
Footings canceled for today, will be inspected when ready and all rebar in place on 12/4/18.

Progress Inspection Partial Pass 12/4/2018 (12:30 - 2:30) 12/4/2018 (PM) 12/04/2018
Corrections:


Miscellaneous/Other
Comment Only
12/04/2018
Pad footings and rebar on line rA from N15 to N17... approved for concrete placement.

Progress Inspection Partial Pass 12/5/2018 (12:30 - 2:30) 12/5/2018 (PM) 12/05/2018
Corrections:


Miscellaneous/Other
Comment Only
12/05/2018
Line rA footing infills n15-n17

Progress Inspection Partial Pass 12/6/2018 (12:30 - 2:30) 12/6/2018 (PM) 12/06/2018
Corrections:


Miscellaneous/Other
Comment Only
12/06/2018
Pad footing at line rB, at line n12. Approved for concrete placement.

Progress Inspection Partial Pass 12/7/2018 (12:30 - 2:30) 12/7/2018 (PM) 12/07/2018
Corrections:


Miscellaneous/Other
Comment Only
12/07/2018
Walls between lines E-F and E-D. Strip footing on line rA between N15 & 16. Approved for concrete placement.

Progress Inspection Partial Pass 12/10/2018 (12:30 - 2:30) 12/10/2018 (PM) 12/10/2018
Corrections:


Miscellaneous/Other
Comment Only
12/10/2018
Footings /pads on line rA grid N13-14. Pad f11 at grid w-G line N10. Approved for concrete placement.

Progress Inspection Partial Pass 12/12/2018 (8:00 - 10:00) 12/12/2018 (AM) 12/12/2018
Corrections:


Miscellaneous/Other
Comment Only
12/12/2018
Line N10 grids W-G to W-H ... 3 pads and footing. Line W-E between lines N10 to N13 .., pad and strip footing. Approved for concrete placement.

Progress Inspection Partial Pass 12/13/2018 (12:30 - 2:30) 12/13/2018 (PM) 12/13/2018
Corrections:


Miscellaneous/Other
Comment Only
12/13/2018
Porch footings on N16 & 15. Pad footings on S13,14,15,16,17. Approved for concrete placement.

Progress Inspection Partial Pass 12/14/2018 (12:30 - 2:30) 12/14/2018 (PM) 12/14/2018
Corrections:


Miscellaneous/Other
Comment Only
12/14/2018
Rebar and footings on grid line r-C from lines s-13 to s-24 / grid e-E lines s-23 to s-24. Approved for concrete placement.

Progress Inspection Not Ready 12/17/2018 (12:30 - 2:30) 12/17/2018 (PM) 12/17/2018
Corrections:


Miscellaneous/Other
Comment Only
12/17/2018
Inspection canceled, reset for 11/18/18 inspection.

Progress Inspection Partial Pass 12/18/2018 (8:00 - 10:00) 12/18/2018 (AM) 12/18/2018
Corrections:


Miscellaneous/Other
Comment Only
12/18/2018
Line s-A pads at lines s19 to s23. West elevator pit area pads and footings. Approved for concrete placement.

Progress Inspection Partial Pass 12/18/2018 (12:30 - 2:30) 12/18/2018 (PM) 12/18/2018
Corrections:


Miscellaneous/Other
Comment Only
12/18/2018
5 pad footings on line s-B. Poured walls on line r-A at N15 & 16. Approved for concrete placement.

Progress Inspection Partial Pass 12/19/2018 (12:30 - 2:30) 12/19/2018 (PM) 12/19/2018
Corrections:


Miscellaneous/Other
Comment Only
12/19/2018
Stem wall at n-10 and line w-G Infill wall footings around west elevator for footing to pad connections. Approved for concrete placement.

Progress Inspection Partial Pass 12/20/2018 (12:30 - 2:30) 12/20/2018 (PM) 12/20/2018
Corrections:


Miscellaneous/Other
Comment Only
12/20/2018
Poured walls at west elevator footing area and 2 columns. Approved for concrete placement.

Progress Inspection Not Ready 12/21/2018 (10:00 - 12:00) 12/21/2018 (AM) 12/21/2018
Corrections:


Miscellaneous/Other
Comment Only
12/21/2018
Progress: Site cleanup and stripping of forms from poured walls. No footings or walls for today. Happy holidays!

Progress Inspection Partial Pass 12/26/2018 (12:30 - 2:30) 12/26/2018 (PM) 12/26/2018
Corrections:


Miscellaneous/Other
Comment Only
12/26/2018
2 pad footings f7b and strip footing on grid line N21 lines e-C, & e-D. 2 f7A pads on N20 lines e-C & e-D. Piers on line sA of garage footing. Approved for concrete placement.

Progress Inspection Not Ready 12/27/2018 (12:30 - 2:30) 12/27/2018 (PM) 12/27/2018
Corrections:


Miscellaneous/Other
Comment Only
12/27/2018
Inspection was canceled for today.

Progress Inspection Partial Pass 12/28/2018 (12:30 - 2:30) 12/28/2018 (PM) 12/28/2018
Corrections:


Miscellaneous/Other
Comment Only
12/28/2018
Rebar, footing/pads online n-8 grids w-G to w-M Footings/ pads on approximately line e-E grids s24-s26.5 Approved for concrete placement.

Progress Inspection Partial Pass 12/31/2018 (8:00 - 10:00) 12/31/2018 (AM) 12/31/2018
Corrections:


Miscellaneous/Other
Comment Only
12/31/2018
Poured wall on line e-E /s-26. 7 piers between s24-26 between e-D to e-E. Approved for concrete placement.

Progress Inspection Partial Pass 1/2/2019 (12:30 - 2:30) 1/2/2019 (PM) 01/02/2019
Corrections:


Miscellaneous/Other
Comment Only
01/02/2019
Piers on line n-7, wall at line w-G from N7 to n9, footings and pads/ rebar at line w-M grids s7 to s10. Ok for concrete placement.

Progress Inspection Partial Pass 1/3/2019 (12:30 - 2:30) 1/3/2019 (PM) 01/03/2019
Corrections:


Miscellaneous/Other
Comment Only
01/03/2019
Piers at line w-M grids s7 & s9. Wall at line s10 see plan sheet s2.1sw Approved for concrete placement.

Progress Inspection Partial Pass 1/4/2019 (12:30 - 2:30) 1/4/2019 (PM) 01/04/2019
Corrections:


Miscellaneous/Other
Comment Only
01/04/2019
Pads, footings, rebar from lines w-P to w-R between grids s4 to s9. Pad footing f33A at line s7 Approved for concrete placement.

Progress Inspection Partial Pass 1/7/2019 (12:30 - 2:30) 1/7/2019 (PM) 01/07/2019
Corrections:


Miscellaneous/Other
Comment Only
01/07/2019
2 Piers on f33 footing pad. Piers and walls on line s4 to s9 grids wP to wQ. Wall footing from grids s9 to s11 Pad footings on line s10 / wQ and wP. Pad footings on line s11 / wQ, wP, and wN Approved for concrete placement.

Progress Inspection Partial Pass 1/8/2019 (12:30 - 2:30) 1/8/2019 (PM) 01/08/2019
Corrections:


Miscellaneous/Other
Comment Only
01/08/2019
Rebar and footing pads on s11 grids sD & wK. Rebar /Footings / pads on line s12 from wQ to sD . Rebar/ footings/ pads and piers on line wQ from s11 to s12.

Progress Inspection Not Ready 1/9/2019 (12:30 - 2:30) 1/9/2019 (PM) 01/09/2019
Corrections:


Miscellaneous/Other
Comment Only
01/09/2019
Inspection canceled

Progress Inspection Partial Pass 1/10/2019 (12:30 - 2:30) 1/10/2019 (PM) 01/10/2019
Corrections:


Miscellaneous/Other
Comment Only
01/10/2019
Footing pads, footings, rebar.. Line S16to line SE. Line S16 to s19 Line sE from s13 to s19 piers on line s12. Wall off line s11 Pad on line s18 and s-c Approved for concrete placement.

Progress Inspection Partial Pass 1/11/2019 (12:30 - 2:30) 1/11/2019 (PM) 01/11/2019
Corrections:


Miscellaneous/Other
Comment Only
01/11/2019
Footings/pads on s27 at grids eN and eO. Walls and piers on line sE from s16 to s18. Piers on line s23 from eO to sE. Pier on line eG / s26. Approved for concrete placement.

Footing Inspection Partial Pass 1/14/2019 (Morning) 1/14/2019 (AM) 01/14/2019
Corrections:


Miscellaneous/Other
Comment Only
01/14/2019
Pads and wall footings at lines s18 & s19 from line sJ to sF. Wf6a wall footing north of line s-H. Pad and wall footing on line s-20 to north of line s-H. Piers on lines s-J & s-I. See plan page S2.1SE.

Progress Inspection Not Ready 1/14/2019 (12:30 - 2:30) 1/14/2019 (PM) 01/14/2019
Inspection scheduled per Jon Aaron - No need for additional inspection on 1/15/19. vcarlson 01/11/2019 3:51 PM
Corrections:


Miscellaneous/Other
Comment Only
01/14/2019
Footings still in progress for the morning scheduled inspection, will stop back later for completion of footings.

Footing Inspection Partial Pass 1/16/2019 (12:30 - 2:30) 1/16/2019 (PM) 01/16/2019
Corrections:


Miscellaneous/Other
Comment Only
01/16/2019
Line s23 from eO to sD. Piers on s20 / sF to sA. Piers on sD / 21-23. Wall east of s20 line / sD to sA. Pad footing on line eG and s26. Approved for concrete placement.

Footing Inspection Partial Pass 1/17/2019 (12:30 - 2:30) 1/17/2019 (PM) 01/17/2019
Corrections:


Miscellaneous/Other
Comment Only
01/17/2019
Footings,pads, rebar.... Line EO /s25-27 Lines s25&26 from EO to EM Piers on s23 Pad on EL / s25 Approved for concrete placement

Footing Inspection Partial Pass 1/18/2019 (12:30 - 2:30) 1/18/2019 (PM) 01/18/2019
Corrections:


Miscellaneous/Other
Comment Only
01/18/2019
Rebar, footings, pads.... Line s25 & 26 lines EK to EG. Elevator walls s24 linen EH / SD Piers s25 & 27 Walls s26 lines EN & Em Lines27 EM to EI. Approved for concrete placement

Footing Inspection Partial Pass 1/22/2019 (12:30 - 2:30) 1/22/2019 (PM) 01/22/2019
Corrections:


Miscellaneous/Other
Comment Only
01/22/2019
Line s2 / WR to WP and WN to WM. 2 columns on line s1 / wO & wM Approved for concrete placement.

Footing Inspection Partial Pass 1/23/2019 (12:30 - 2:30) 1/23/2019 (PM) 01/23/2019
Corrections:


Miscellaneous/Other
Comment Only
01/23/2019
Plans s2.1sw Pad footings on line s1... WF6A & F7A Lines s3-s4 and lines WR to WP. Pad at s5 & WO. Step footing and Piers ons2. Pad at s3 & WM with section of strip footing. Soil corrections verified by AET. Frost blankets onsite and being used throughout the placement of concrete.

Footing Inspection Partial Pass 1/24/2019 (12:30 - 2:30) 1/24/2019 (PM) 01/24/2019
Corrections:


Miscellaneous/Other
Comment Only
01/24/2019
Walls at line S1/WR Walls at line s3&4/ wP to wR Pier at line s1/wQ Pier at line s3wM Pier at lines w2 & 3 / wO & wP Frost blankets onsite . Approved for concrete placement

Footing Inspection Not Ready 1/25/2019 (12:30 - 2:30) 1/25/2019 (PM) 01/25/2019
Corrections:


Miscellaneous/Other
Comment Only
01/25/2019
Inspection canceled

Footing Inspection Partial Pass 1/28/2019 (12:30 - 2:30) 1/28/2019 (PM) 01/28/2019
Corrections:


Miscellaneous/Other
Comment Only
01/28/2019
Plans page s2.1se. Footings, pads, rebar... SE corner section, lines s26 to s29 from lines sD to eE. Frost blankets being used for all footings and tented and heated section along line s29 to protect and heat footing and exposed water main. Approved for concrete placement.

Footing Inspection Not Ready 1/29/2019 (12:30 - 2:30) 1/29/2019 (PM) 01/29/2019
Corrections:


Miscellaneous/Other
Comment Only
01/29/2019
Inspection canceled due to Extreme cold weather, no footings or walls ready for concrete.

Footing Inspection Not Ready 1/30/2019 (12:30 - 2:30) 1/30/2019 (PM) 01/30/2019
Corrections:


Miscellaneous/Other
Comment Only
01/30/2019
Due to extreme cold weather, no footings, walls, rebar, are being placed at this time. Inspection has been canceled by contractor.

Footing Inspection Not Ready 1/31/2019 (12:30 - 2:30) 1/31/2019 (PM) 01/31/2019
Corrections:


Miscellaneous/Other
Comment Only
01/31/2019
No work ready for inspection due to extreme cold temps. Inspection canceled.

Footing Inspection Partial Pass 2/1/2019 (12:30 - 2:30) 2/1/2019 (PM) 02/01/2019
Corrections:


Miscellaneous/Other
Comment Only
02/01/2019
Piers and wall in SE corner, lines s26 to s29 / lines sD to eE. Chair two columns for concrete coverage in forms. Approved for concrete placement.

Footing Inspection Partial Pass 02/02/2019
Corrections:


Miscellaneous/Other
Comment Only
02/02/2019
Rebar, footings and pads on line w-A grids n4 to n14.5. Temps are about 27 and above. degrees at time of concrete placement, blankets are on hand for coverage. Approved for concrete placement.

Footing Inspection Partial Pass 2/4/2019 (12:30 - 2:30) 2/4/2019 (PM) 02/04/2019
Corrections:


Miscellaneous/Other
Comment Only
02/04/2019
F8A footing pad at line w-F/ N1. Piers in line wA, between grids N4 to N14. Approved for concrete placement.

Footing Inspection Partial Pass 2/5/2019 (12:30 - 2:30) 2/5/2019 (PM) 02/05/2019
Corrections:


Miscellaneous/Other
Comment Only
02/05/2019
Outer perimeter NW corner , see page s2.1NW. From lines w-F to w-A and connecting to footing pad at line N4. Approved for concrete placement

Footing Inspection Not Ready 2/6/2019 (12:30 - 2:30) 2/6/2019 (PM) 02/06/2019
Corrections:


Miscellaneous/Other
Comment Only
02/06/2019
Inspection canceled

Footing Inspection Partial Pass 2/11/2019 (12:30 - 2:30) 2/11/2019 (PM) 02/11/2019
Corrections:


Miscellaneous/Other
Comment Only
02/11/2019
Piers on line N1. Poured wall at lines wF to wE on line wE to line N9. (2)F32A pads wB to wD/ lines N2&N3.

Footing Inspection Partial Pass 2/12/2019 (12:30 - 2:30) 2/12/2019 (PM) 02/12/2019
Corrections:


Miscellaneous/Other
Comment Only
02/12/2019
Footing WF6A slightly east of line N2 from wD to wF. Strip footing infill at line wF. F5A pad wL and s1. Approved for concrete placement.

Footing Inspection Partial Pass 2/13/2019 (12:30 - 2:30) 2/13/2019 (PM) 02/13/2019
Corrections:


Miscellaneous/Other
Comment Only
02/13/2019
Pier on line wL & s1 Wall on line N2 All remaining piers in NW corner from line N1 to N4 Approved for concrete placement.

Footing Inspection Not Ready 3/18/2019 (12:30 - 2:30) 3/18/2019 (PM) 03/18/2019
Corrections:


Miscellaneous/Other
Comment Only
03/18/2019
Footings canceled due to soil corrections needed.

Progress Inspection Partial Pass 03/18/2019
Corrections:


Miscellaneous/Other
Comment Only
03/18/2019
Viewed progress of the joint sealing of parking ramp precast panels. Ultra block blocking backer installed in joints and covered with the caulking spec,d for this application, both inside and outside of ramp.

Footing Inspection Not Ready 3/19/2019 (12:30 - 2:30) 3/19/2019 (PM) 03/19/2019
Corrections:


Miscellaneous/Other
Comment Only
03/19/2019
Inspection canceled, still digging footings and doing soil corrections.

Footing Inspection Partial Pass 3/20/2019 (12:30 - 2:30) 3/20/2019 (PM) 03/20/2019
Corrections:


Miscellaneous/Other
Comment Only
03/20/2019
Footings on line w-A from lines n16 to n20. 2pad footings online n20 grids W-c and E-A Approved for concrete placement

Footing Inspection Partial Pass 3/21/2019 (12:30 - 2:30) 3/21/2019 (PM) 03/21/2019
Corrections:


Miscellaneous/Other
Comment Only
03/21/2019
Footings on line w-A from lines N20 to N23. Elevator footing t line N21 between w-D and e-A Approved for concrete placement

Footing Inspection Partial Pass 3/22/2019 (12:30 - 2:30) 3/22/2019 (PM) 03/22/2019
Corrections:


Miscellaneous/Other
Comment Only
03/22/2019
Piers along line w-A. Walls at elevator pad. Line n23 footing. Line w-A from n23 to n24 including the revised corner pad footing . Approved for concrete placement

Footing Inspection Partial Pass 3/25/2019 (12:30 - 2:30) 3/25/2019 (PM) 03/25/2019
Corrections:


Miscellaneous/Other
Comment Only
03/25/2019
Poured wall at line n23 /wA to wD Footing at line n24, lines wA to wD 2piers at line n21 to n22, lines wC and wD F6A pad at line n21 /eA Approved for concrete placement.

Footing Inspection Partial Pass 3/26/2019 (12:30 - 2:30) 3/26/2019 (PM) 03/26/2019
Corrections:


Miscellaneous/Other
Comment Only
03/26/2019
Line n24 from grids W-D to e-B Line e-B from n24 to n21 Piers on this pour sections approved Approved for concrete placement

Footing Inspection Partial Pass 3/27/2019 (12:30 - 2:30) 04/30/2019
Corrections:


Miscellaneous/Other
Comment Only
04/30/2019
Viewed rebar installation at the parking ramp drive in ramp... installed as per plan. Approved for concrete placement.

Progress Inspection Partial Pass 04/30/2019
Corrections:


Miscellaneous/Other
Comment Only
04/30/2019
Viewed one side of the SW 3 hour wall... 2nd and 3d layer for the one side only approved per UL design.

Progress Inspection Partial Pass 06/28/2019
Corrections:


Miscellaneous/Other
Comment Only
06/28/2019
Out 1st layer of gypsum at 4th floor stair shaft at SW building....approved. 2nd layer at elevator shaft ....approved.

Building Final Inspection Passed 03/29/2021
Corrections:


Miscellaneous/Other
Comment Only
03/29/2021
Work has been completed, see permit for building buildout.