Permit Application Status

PRFD201813925


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRFD201813925
Foundation
Finaled
DARK HORSE HOSPITALITY LLC
Other
Not Required
Footing and foundation for a new hotel.
11/06/2018
01/03/2020
04/24/2024

Locations

Permits

Permit Number: PRFD201813925

Foundation
Finaled
01/03/2020
04/24/2024

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Footing Inspection Not Ready 3/6/2020 (8:00 - 10:00) 3/6/2020 (AM) 03/06/2020
Corrections:


Miscellaneous/Other
Comment Only
03/06/2020
First run of footings at SE corner perimeter in place. Rebar in footings approved, column bar and wall dowels need to be placed. Set up inspection for viewing remains rebar prior to concrete placement.

Footing Inspection Partial Pass 3/9/2020 (8:00 - 10:00) 3/9/2020 (AM) 03/09/2020
Corrections:


Miscellaneous/Other
Comment Only
03/09/2020
Line 23 from AB to X. Grid X from line 20 to 23. Line 20 from grid X to V Grid V from line 19 to 20 Line 19 from V to T Line 15 from T to R Grid R from Lines 14 to 15 Line 14 from R to P Grid P from lines 12 to 14 including line 12 from P to Q

Footing Inspection Partial Pass 3/12/2020 (8:00 - 10:00) 3/12/2020 (AM) 03/12/2020
Corrections:


Miscellaneous/Other
Comment Only
03/12/2020
Footings on line 11 from grids D to R Footings on grid J lines 11 to 20 Approved for concrete placement

Footing Inspection Partial Pass 03/16/2020
Corrections:


Miscellaneous/Other
Comment Only
03/16/2020
Wall footing at grid V , lines 15 to 19.4. Footing at grid V , lines 15 to 19.4 Approved for concrete placement

Footing Inspection Partial Pass 3/18/2020 (12:30 - 2:30) 3/18/2020 (PM) 03/18/2020
Corrections:


Miscellaneous/Other
Comment Only
03/18/2020
Wall pour at line 23, grids AC to X. Grid X from lines 20 to 23. Approved for concrete placement

Footing Inspection Partial Pass 3/20/2020 (8:00 - 10:00) 3/20/2020 (AM) 03/20/2020
Corrections:


Miscellaneous/Other
Comment Only
03/20/2020
5 columns for today’s inspection and concrete pour. Line 20 at grid X and V. Line 19 at grid V Line 19 at grid T Line 20.5 at grid U.5 Approved for concrete placement

Footing Inspection Partial Pass 3/24/2020 (12:30 - 2:30) 3/24/2020 (PM) 03/24/2020
Corrections:


Miscellaneous/Other
Comment Only
03/24/2020
Walls on line V footing from grid 15-19 Walls on line 19 footing. Walls on line 14 footing Walls on line 15 footing grids grids V to T

Footing Inspection Partial Pass 3/27/2020 (10:00 - 12:00) 3/27/2020 (AM) 03/27/2020
Corrections:


Miscellaneous/Other
Comment Only
03/27/2020
Walls on line 20, grids X to V Walls on line 19, grids T to V Wall on grid T, lines 15 to 19 Wall on line 15, grids T to R Wall on grid R, lines, 14-15 Contractor to chair mats that are burning against forms... verbal to contractor. Approved for concrete placement

Footing Inspection Partial Pass 3/31/2020 (12:30 - 2:30) 3/31/2020 (PM) 03/31/2020
Corrections:


Miscellaneous/Other
Comment Only
03/31/2020
Elevator pit at grids K-N, lines21-22.2 Column at line 19 and grid M Columns at grid L, lines 16 and 17.5 Wall at line 12, grids F.8-H Wall on grid H, lines12- 20 includes the jog at line 15 Approved for concrete placement

Footing Inspection Partial Pass 4/2/2020 (8:00 - 10:00) 4/2/2020 (AM) 04/02/2020
Corrections:


Miscellaneous/Other
Comment Only
04/02/2020
Viewed the rebar in elevator walls at elevator pad footing... approved for concrete placement.

Footing Inspection Partial Pass 4/7/2020 (10:00 - 12:00) 4/7/2020 (AM) 04/07/2020
Corrections:


Miscellaneous/Other
Comment Only
04/07/2020
Wall rebar inspected at: line 12, grids E to H Line F.4 grids 11 to 12 Line 11, gridsE to Q Grid Q, lines 9-11 Approved for concrete placement

Footing Inspection Partial Pass 4/8/2020 (10:00 - 12:00) 4/8/2020 (AM) 04/08/2020
Corrections:


Miscellaneous/Other
Comment Only
04/08/2020
Footings at lines 1 to 6, grids H to P. Approved for concrete placement

Footing Inspection Partial Pass 4/9/2020 (10:00 - 12:00) 4/9/2020 (AM) 04/09/2020
Corrections:


Miscellaneous/Other
Comment Only
04/09/2020
Walls at lines 12-14 grids P and Q ... Approved for concrete placement

Footing Inspection Partial Pass 4/10/2020 (10:00 - 12:00) 4/10/2020 (AM) 04/10/2020
Corrections:


Miscellaneous/Other
Comment Only
04/10/2020
Footings on line 28, grids AC to X Footing on grid AC , lines 23 to 28 These are perimeter footings for this pour, the stoop on line 28 will be done at a later date. Approved for concrete placement

Footing Inspection Partial Pass 4/14/2020 (10:00 - 12:00) 4/14/2020 (AM) 04/14/2020
Corrections:


Miscellaneous/Other
Comment Only
04/14/2020
Perimeter footing...grid J from lines 21-24 and line 24, grid J to N. 2 interior pad footings grid M at lines 12 and 14 Perimeter footing and elevator pit... lines 1 to 5 ar grids A, C, and D. Approved for concrete placement

Footing Inspection Partial Pass 4/15/2020 (10:00 - 12:00) 4/15/2020 (AM) 04/15/2020
Corrections:


Miscellaneous/Other
Comment Only
04/15/2020
Column pad footings at grid R, at lines 16, 17.5,19 and line 21, grid U Wall at line 28, grids AA to X Approved for concrete placement

Footing Inspection Partial Pass 4/16/2020 (10:00 - 12:00) 4/16/2020 (AM) 04/16/2020
Corrections:


Miscellaneous/Other
Comment Only
04/16/2020
Columns at lines 16,17.5, grid R . Line 20.5 grid U.5 & line 23 grid W. Wall from grid AC to X at line 28 Approved for concrete placement

Footing Inspection Partial Pass 4/20/2020 (10:00 - 12:00) 4/20/2020 (PM) 04/20/2020
Corrections:


Miscellaneous/Other
Comment Only
04/20/2020
Wall on line 20.5 to 24, grid J ant line 24 grids J to N Column footing pads... line 19 and grid Q, and line 24 grid U.5 Wall footing and column pad on line 24, grids N to U.5 Wall footings from grids AA to Z including footing on line 24.

Footing Inspection Partial Pass 4/21/2020 (10:00 - 12:00) 4/21/2020 (PM) 04/21/2020
Contractor called and cancelled footing inspection for today, Friday, 4/17/2020. jsmidt 04/17/2020 8:51 AM
Corrections:


Miscellaneous/Other
Comment Only
04/21/2020
Wall and 3 columns are being placed with concrete today. Wall was inspected at yesterday’s inspection and approved, the columns are to the pads from yesterday’s inspection and the columns are also approved for concrete placement.

Footing Inspection Partial Pass 4/23/2020 (10:00 - 12:00) 4/23/2020 (AM) 04/23/2020
Corrections:


Miscellaneous/Other
Comment Only
04/23/2020
Stair Walls on grids AA and Z and at line 24... Approved for concrete placement

Footing Inspection Partial Pass 4/24/2020 (10:00 - 12:00) 4/24/2020 (AM) 04/24/2020
Corrections:


Miscellaneous/Other
Comment Only
04/24/2020
Work is still ongoing, and rebar is still being set at footings. Will recheck on Mondays inspection.

Footing Inspection Partial Pass 4/27/2020 (8:00 - 10:00) 04/29/2020
Corrections:


Miscellaneous/Other
Comment Only
04/29/2020
Footing at grids T to W , line 28 and monument sign footing at grid V. Pad footing off grid U and line 24 Approved for concrete placement

Progress Inspection Partial Pass 5/6/2020 (12:30 - 2:30) 5/6/2020 (PM) 05/06/2020
Corrections:


Miscellaneous/Other
Comment Only
05/06/2020
Progress inspection, work is ongoing. Consulted with contractor about next inspections and work progress.

Footing Inspection Partial Pass 5/7/2020 (10:00 - 12:00) 5/7/2020 (AM) 05/07/2020
Corrections:


Miscellaneous/Other
Comment Only
05/07/2020
Exterior walls from lines1to 6 , at grids A to P. Approved for concrete placement.

Footing Inspection Partial Pass 5/12/2020 (10:00 - 12:00) 5/12/2020 (AM) 05/12/2020
Corrections:


Miscellaneous/Other
Comment Only
05/12/2020
Infill footing sections between lines 6 to 8 grids C to Q as highlighted on the job site prints. Walls already formed approved for concrete placement. Sign base wall at south of building approved.

Progress Inspection Partial Pass 5/26/2020 (10:00 - 12:00) 5/26/2020 (AM) 05/26/2020
Corrections:


Miscellaneous/Other
Comment Only
05/26/2020
Poured walls we’re already inspected and approved for concrete placement. Viewed podium deck rebar and stud rail placement...approved for concrete placement taking place on 5/27/20.

Progress Inspection Partial Pass 5/29/2020 (8:00 - 10:00) 5/29/2020 (AM) 05/29/2020
Corrections:


Miscellaneous/Other
Comment Only
05/29/2020
Rebar for added sump pit approved per RFI design change. Ok to place concrete

Progress Inspection Partial Pass 6/2/2020 (10:00 - 12:00) 6/2/2020 (AM) 06/01/2020
Corrections:


Miscellaneous/Other
Comment Only
06/01/2020
Line 5, grids J-P Line 7, grids J-P Lines 4&5, grids H-D Grid J & H, lines 2-2.4 Approved for concrete placement

Progress Inspection Partial Pass 6/8/2020 (10:00 - 12:00) 06/02/2020
Corrections:


Miscellaneous/Other
Comment Only
06/02/2020
Went over next phase of construction with contractor, footing pour scheduled for today was canceled due to the heat. Will inspect the next set of poured walls and /or footings at next inspection.

Progress Inspection Partial Pass 6/3/2020 (10:00 - 12:00) 6/3/2020 (AM) 06/03/2020
Corrections:


Miscellaneous/Other
Comment Only
06/03/2020
Foundation walls at interior footings, and walls around the added sump... approved for concrete placement

Progress Inspection Partial Pass 6/4/2020 (10:00 - 12:00) 6/4/2020 (AM) 06/04/2020
Corrections:


Miscellaneous/Other
Comment Only
06/04/2020
Stoop walls at added footing were poured today, no other footings or walls ready for inspection.

Progress Inspection Partial Pass 6/8/2020 (10:00 - 12:00) 6/8/2020 (AM) 06/08/2020
Corrections:


Miscellaneous/Other
Comment Only
06/08/2020
Outside perimeter footing about grid C, from lines 15-32. Footing at line 32 to grids A-N ... approved for concrete placement

Progress Inspection Partial Pass 6/11/2020 (10:00 - 12:00) 6/11/2020 (AM) 06/11/2020
Corrections:


Miscellaneous/Other
Comment Only
06/11/2020
Footing connections already placed footing on line 32. All of footing outside line 32, ( no grid lines shown on plans). Connecting footing to already placed footings on grids C & E, including the footing jogs. Approved for concrete placement.

Progress Inspection Partial Pass 6/16/2020 (10:00 - 12:00) 6/16/2020 (AM) 06/16/2020
Corrections:


Miscellaneous/Other
Comment Only
06/16/2020
West Perimeter poured walls, approximately lines 19-32... approved for concrete placement

Progress Inspection Partial Pass 6/22/2020 (10:00 - 12:00) 6/22/2020 (AM) 06/22/2020
Corrections:


Miscellaneous/Other
Comment Only
06/22/2020
Poured walls on grid “ A “ and line 32... approved for concrete placement.

Progress Inspection Partial Pass 6/24/2020 (12:30 - 2:30) 6/24/2020 (PM) 06/24/2020
Corrections:


Miscellaneous/Other
Comment Only
06/24/2020
Rebar for walls at south end of building footings is approved per design. Clearances will be checked for concrete placement at next inspection.

Footing Inspection Partial Pass 6/25/2020 (12:30 - 2:30) 6/25/2020 (PM) 06/25/2020
Corrections:


Miscellaneous/Other
Comment Only
06/25/2020
Clearance for rebar at walls on south end approved. Rebar for Footing tie in to the walls at lines 7&8... approved. Approved for concrete placement

Footing Inspection Partial Pass 6/25/2020 (2:30 - 3:30) 6/25/2020 (PM) 06/25/2020
Corrections:


Miscellaneous/Other
Comment Only
06/25/2020
See notes from earlier inspection today

Progress Inspection Partial Pass 07/20/2020
Corrections:


Miscellaneous/Other
Comment Only
07/20/2020
Underslab poly with wire mesh reinforcement for the basement slab in the hotel... approved for concrete placement.

Progress Inspection Partial Pass 08/05/2020
Corrections:


Miscellaneous/Other
Comment Only
08/05/2020
Stopped by job site to check on activity and work. Tie in Footings and footings for building overhang yet to be completed. Talked with the general contractor to set up inspections when they are ready to do the last footings.

Progress Inspection Partial Pass 8/10/2020 (10:00 - 12:00) 8/10/2020 (AM) 08/10/2020
Corrections:


Miscellaneous/Other
Comment Only
08/10/2020
Met with framer Forman and general contractor to go over the inspections, and what we look for during the building phase. Contractor to have the most current set of plans onsite with inspections. Other information as per the Mechanical connectors and anchor bolts, are called for use and have been changed from the first set of plans. Information and details per architect and design and use, will be needed for the framing inspection process. Have information onsite for inspection with framing.

Progress Inspection Partial Pass 8/10/2020 (10:00 - 12:00) 8/10/2020 (AM) 08/10/2020
Corrections:


Miscellaneous/Other
Comment Only
08/10/2020
Viewed underslab poly, and wire mesh reinforcement in the slab on grade locations both of podium deck slab. Chairs are to be installed prior to concrete placement and will be onsite before concrete is scheduled to be placed.

Progress Inspection Partial Pass 8/11/2020 (12:30 - 2:30) 8/11/2020 (PM) 08/11/2020
Corrections:


Miscellaneous/Other
Comment Only
08/11/2020
Underslab poly and reinforcing wire mats at sla on grade north of podium deck. Chairs to be installed at mesh hen they arrive on 8/12. Approved for concrete placement when chairs are installed, special inspection will verify.

Progress Inspection Partial Pass 10/9/2020 (7:00 - 8:00) 10/9/2020 (AM) 10/09/2020
Corrections:


Miscellaneous/Other
Comment Only
10/09/2020
Underslab poly for slab on grade at south portion of building...approved for concrete placement

Progress Inspection Partial Pass 8/4/2021 (10:00 - 12:00) 8/4/2021 (AM) 08/04/2021
Corrections:


Miscellaneous/Other
Carried Forward
08/16/2021
Went over what the city will require with the start up of this project after sitting dormant for most of a year. 1) underground plumbing to be addressed and fixed, inspections to follow as fixes occur. Air test will be performed prior to covering. 2) mold remediation to be done per contractor in areas affected. 3) structural steel to be individually protected, framing attached to will have to be removed to achieve full encasement protection and then reinstalled. 4) any damaged roof sheathing and floor sheathing to be replaced and or patched in. 5) housewrap to have manufacturers rep access installation and product due to prolonged exposure, opening wraps to also be corrected. 6) roof drains to be cut in and run. All hold downs and anchors to be installed per design, inspections of to follow. All inspections to be performed as per city and code requirements, no covering of areas will be allowed until approval has been given. Call in for inspections as they are ready and needed.

Progress Inspection Partial Pass 8/17/2021 (8:00 - 10:00) 8/17/2021 (AM) 08/17/2021
Corrections:


Miscellaneous/Other
Carried Forward
05/11/2023
Went over what the city will require with the start up of this project after sitting dormant for most of a year. 1) underground plumbing to be addressed and fixed, inspections to follow as fixes occur. Air test will be performed prior to covering. 2) mold remediation to be done per contractor in areas affected. 3) structural steel to be individually protected, framing attached to will have to be removed to achieve full encasement protection and then reinstalled. 4) any damaged roof sheathing and floor sheathing to be replaced and or patched in. 5) housewrap to have manufacturers rep access installation and product due to prolonged exposure, opening wraps to also be corrected. 6) roof drains to be cut in and run. All hold downs and anchors to be installed per design, inspections of to follow. All inspections to be performed as per city and code requirements, no covering of areas will be allowed until approval has been given. Call in for inspections as they are ready and needed.

Miscellaneous/Other
Comment Only
08/17/2021
Viewed the shear walls located on either side of the stairways and around elevators at floors 1-4. Ok to first layer with gypsum.

Building Final Inspection Passed 10/27/2023