PRFD201905596
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Building Final Inspection | Pending | |||
Footing Inspection | Pending | |||
Footing Inspection | Partial Pass | 1/28/2020 (12:30 - 2:30) | 01/14/2020 | |
6 intersecting step footings at line WE and line W9. Passed. | ||||
Footing Inspection | Partial Pass | 01/15/2020 | ||
7 pad footings - line W5 to W10 and line WD4 to WD. Braun on site. | ||||
Footing Inspection | Partial Pass | 01/17/2020 | ||
A. Strip footing - line W5 to W9 along line WD. B. 6- pad footings line WD to WJ along line W4. C. Strip footing from line WE to WJ along line W5. | ||||
Footing Inspection | Partial Pass | 1/22/2020 (12:30 - 2:30) | 1/22/2020 (PM) | 01/22/2020 |
5- pad footings from line WJ to WE, and from line W3 to W2. ALL pad footings and strip footings from line W5 TO W2, and from line WK to WP. Braun special inspection on site. | ||||
Footing Inspection | Partial Pass | 1/23/2020 (12:30 - 2:30) | 1/23/2020 (PM) | 01/24/2020 |
Not pouring today. A. Site meeting with superintendent Denny Lundblad, framing and shaft details, and inspections. | ||||
Footing Inspection | Partial Pass | 1/24/2020 (12:30 - 2:30) | 1/24/2020 (PM) | 01/24/2020 |
Not ready today, excavator has not completed footing and pad excavation. Temp 30 degree F. | ||||
Footing Inspection | Partial Pass | 1/28/2020 (12:30 - 2:30) | 1/28/2020 (PM) | 01/28/2020 |
Footing and pads. A. Strip footing along line W12, from WA to WH. B. Strip footing along line WA, from W12 to W7. C. 3 Pad footings, at W12 and WB, W11 and WD, and W11 and WE.2. | ||||
Footing Inspection | Passed | 1/30/2020 (8:00 - 10:00) | 1/30/2020 (AM) | 01/30/2020 |
Strip footing - along line WA, from line W7 to W3 . Temp 18 degree F. | ||||
Footing Inspection | Partial Pass | 1/31/2020 (8:00 - 10:00) | 1/31/2020 (AM) | 01/31/2020 |
7 pad footings - along line WB from line W11 thru W5. | ||||
Footing Inspection | Partial Pass | 2/18/2020 | 2/18/2020 (PM) | 02/18/2020 |
Elevator footing only, with reinforcement per plan. Location - line W3 and line WC. |