Permit Application Status

PRFD201905597


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRFD201905597
Foundation
Closed
KNOX & AMERICAN I LLC
Other
Not Required
Site Clearing, site excavation, footing & foundation installation for a new 123 unit apartment facility named "The District."
05/30/2019
09/20/2019
11/20/2021

Locations

Property
0402724230085

Address
1801 W 80TH 1/2 ST, BLOOMINGTON, MN 55431

1801 West 80 1/2 Street, Bloomington, MN 55431

Permits

Permit Number: PRFD201905597

Foundation
Expired
09/20/2019
11/20/2021

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Building Final Inspection Pending
Footing Inspection Pending
Footing Inspection Pending 11/12/2019 (12:30 - 2:30)
Footing Inspection Pending 11/13/2019 (12:30 - 2:30)
Footing Inspection Pending 11/21/2019 (12:30 - 2:30)
Footing Inspection Pending 1/31/2020 (8:00 - 10:00)
Footing Inspection Partial Pass 10/17/2019 (12:30 - 2:30) 10/17/2019 (PM) 10/17/2019
East building - north east corner. A. Strip footing - per plan. #5 hook bars for std masonry wall, and #6 hook bars for masonry 1 wall. C. All hook bars spaced 16 inch on center.
Footing Inspection Not Ready 10/21/2019 (12:30 - 2:30) 10/21/2019 (PM) 10/21/2019
Footing Inspection Not Ready 10/22/2019 (12:30 - 2:30) 10/22/2019 (PM) 10/22/2019
Progress footing. South east corner of property. Rain.
Footing Inspection Partial Pass 10/23/2019 (12:30 - 2:30) 10/23/2019 (PM) 10/23/2019
Progress - footing.
Footing Inspection Partial Pass 10/24/2019 (12:30 - 2:30) 10/24/2019 (PM) 10/24/2019
Progress footings - A. CORRECT HORIZONTAL REINFORCEMENT ON ELEVATOR FOOTING WALL REINFORCEMENT PER PLAN.
Footing Inspection Partial Pass 10/25/2019 (12:30 - 2:30) 10/25/2019 (PM) 10/25/2019
Poured footing- East end along Knox Ave. Braun on site .
Footing Inspection Not Ready 10/28/2019 (12:30 - 2:30) 10/28/2019 (PM) 10/28/2019
Progress on CMU block foundation. A. Not ready to pour footing today.
Footing Inspection Partial Pass 10/29/2019 (12:30 - 2:30) 10/29/2019 (PM) 10/29/2019
Progress - block work going strong, excavation going strong. Footing pour not ready today.
Footing Inspection Partial Pass 10/30/2019 (12:30 - 2:30) 10/30/2019 (PM) 10/31/2019
Footing Inspection Passed 10/31/2019 (12:30 - 2:30) 10/31/2019 (PM) 10/31/2019
Progress - No pouring footings ar The District until November 10, 2019. Braun on site for cmu core fill today.
Footing Inspection Partial Pass 11/1/2019 (12:30 - 2:30) 11/1/2019 (PM) 11/01/2019
Progress - meet on site.
Footing Inspection Partial Pass 11/4/2019 (12:30 - 2:30) 11/4/2019 (PM) 11/04/2019
Progress - structural block work, ongoing. No footing today.
Footing Inspection Partial Pass 11/5/2019 (12:30 - 2:30) 11/5/2019 (PM) 11/05/2019
Progress - A. No footing pouring today. B. Block work ongoing from foundation footing. Block wall Types - CMU, CMU-1.
Footing Inspection Partial Pass 11/6/2019 (12:30 - 2:30) 11/6/2019 (PM) 11/06/2019
No concrete pouring until November 11, 2019. Progress on structural block-work.
Footing Inspection Partial Pass 11/7/2019 (12:30 - 2:30) 11/7/2019 (PM) 11/07/2019
Corrections:


Miscellaneous/Other
Comment Only
11/07/2019
Approximately 200 lineal feet of waterproofing and mat system with 2” R10 foam installed by glue applied. 4 ft. Lift of this system ... approved

Footing Inspection Not Ready 11/8/2019 (12:30 - 2:30) 11/12/2019 (PM) 11/12/2019
Corrections:


Miscellaneous/Other
Comment Only
11/12/2019
Not ready for inspections.

Footing Inspection Not Ready 11/12/2019 (12:30 - 2:30) 11/12/2019 (PM) 11/12/2019
Corrections:


Miscellaneous/Other
Comment Only
11/12/2019
Not ready for inspection

Footing Inspection Partial Pass 11/14/2019 (12:30 - 2:30) 11/14/2019 (PM) 11/14/2019
Progress - A. structural CMU block foundation ongoing. B. No footing ready today.
Footing Inspection Partial Pass 11/15/2019 (12:30 - 2:30) 11/15/2019 (PM) 11/15/2019
Progress - A Structural CMU block foundation - ongoing. B. No footing today, per contractor, deer hunting .
Footing Inspection Partial Pass 11/18/2019 (12:30 - 2:30) 11/18/2019 (PM) 11/18/2019
Progress - A. STRUCTURAL CMU block foundation walls, core filled. B. Starting to excavate and compact ongoing footing excavation.
Footing Inspection Partial Pass 11/19/2019 (12:30 - 2:30) 11/19/2019 (PM) 11/19/2019
Progress - A. ONGOING STRUCTURAL BLOCK FOUNDATION WALLS. B. EXCAVATING ON GOING FOOTING TRENCH AND SOIL COMPACTING. SAND SOIL.
Footing Inspection Partial Pass 11/20/2019 (12:30 - 2:30) 11/20/2019 (PM) 11/20/2019
Progress - Excavation progressing for next building footing pour NOVEMBER 21-22.
Footing Inspection Partial Pass 11/22/2019 (12:30 - 2:30) 11/22/2019 (PM) 11/22/2019
Corrections:


Miscellaneous/Other
Comment Only
11/22/2019
Footings and Padres inclusive of lines EA to EF, E1 to E4. As of inspection, not all bar is set... Contractor has uprights to set. Contractor will bulkhead off where he hasn’t finished setting upright bars and place concrete at next pour. Larger interior pads are not included in this inspection. Pending special inspection viewing...ok to place concrete.

Footing Inspection Partial Pass 11/25/2019 (12:30 - 2:30) 11/25/2019 (PM) 11/25/2019
Progress - A. Ongoing CMU structural block wall. No footing today. Exterior foundation waterproofing, and 2 inch R-10 exterior rigid polystyrene foam.
Footing Inspection Not Ready 11/26/2019 (12:30 - 2:30) 11/26/2019 (PM) 11/27/2019
Snow storm today. No one working.
Footing Inspection Partial Pass 12/13/2019 (12:30 - 2:30) 12/13/2019 (PM) 12/13/2019
Corrections:


Miscellaneous/Other
Comment Only
12/13/2019
16 footing pads with rebar at ... Line E9 grids EH,EG, EF, EE, ED. Line11, grids EH,EG,EF,EE EE.2. Line E11&12 grid EB. Lines E5-E10 at grid ED. Approved for concrete placement.

Footing Inspection Partial Pass 2/19/2020 (2:30 - 3:30) 01/10/2020
6 pad footings - Braun on site. Line E5 to E3, from line EH to EK.
Footing Inspection Partial Pass 11/27/2019 (12:30 - 2:30) 11/27/2019 (PM) 01/13/2020
Footing Inspection Partial Pass 2/20/2020 (10:00 - 12:00) 2/20/2020 (AM) 02/20/2020
Footing and elevator poured wall reinforcement. A. Location grid line W4 to W1 and W4 to WE. Ongoing work.
Progress Inspection Passed 05/24/2021
Progress Inspection Passed 5/6/2020 (10:00 - 12:00) 5/6/2020 (AM) 05/24/2021
Draft stop requirements. A. No flexible duct thru rated walls and rated floor systems. B. Draft stop requirements for un insulated cavity below flat roof system. C. Draft stop requirements for exit access stairways. D. Draft stop for concealed spaces. Site meeting with Denny Lundblad.