Permit Application Status

PRFD201910928


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRFD201910928
Foundation
Finaled
SKYWATER TECH FOUNDRY INC
Other
Not Required
Footings & Foundation
09/17/2019
11/14/2019
12/06/2020
06/09/2020

Locations

Permits

Permit Number: PRFD201910928

Foundation
Finaled
11/14/2019
12/06/2020

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Footing Inspection Partial Pass 12/3/2019 (12:30 - 2:30) 12/3/2019 (PM) 12/03/2019
Corrections:


Miscellaneous/Other
Comment Only
12/03/2019
Grid 1 from T to F ... strip footings along existing building. Rebar tie-in’s and footing bar approved.

Footing Inspection Partial Pass 12/6/2019 (10:00 - 12:00) 12/6/2019 (AM) 12/06/2019
Corrections:


Miscellaneous/Other
Outstanding
12/06/2019
3 pier footings on line 2 on L.5, J.5, & G.5. Remaining strip footing from line F to the east corner of existing building. Approved for concrete placement.

Footing Inspection Partial Pass 12/9/2019 (10:00 - 12:00) 12/9/2019 (AM) 12/09/2019
Corrections:


Miscellaneous/Other
Comment Only
12/09/2019
Footing pads on line 2, grids Q.1, N.5, D.9, and Grid S. Piers on footing pads at grids L.5, J.5, & G.5. ... approved for concrete placement.

Footing Inspection Partial Pass 12/10/2019 (10:00 - 12:00) 12/10/2019 (AM) 12/10/2019
Corrections:


Miscellaneous/Other
Outstanding
12/10/2019
Piers on grids Q.1, N.5, & E on line 2.... approved for concrete placement.

Footing Inspection Not Ready 12/11/2019 (10:00 - 12:00) 12/11/2019 (AM) 12/11/2019
Corrections:


Miscellaneous/Other
Comment Only
12/11/2019
Not ready for inspection today.

Footing Inspection Not Ready 12/12/2019 (10:00 - 12:00) 12/12/2019 (AM) 12/12/2019
Corrections:


Miscellaneous/Other
Comment Only
12/12/2019
Rebar in the exterior footing on the west is still in process of install, will recheck at inspection on 12/13 all rebar for concrete placement that day.

Footing Inspection Partial Pass 12/13/2019 (10:00 - 12:00) 12/13/2019 (AM) 12/13/2019
Corrections:


Miscellaneous/Other
Comment Only
12/13/2019
Retaining wall footing/rebar, pads/ rebar, wall bars, and pier bars in the footing on grid line T, from lines 1 to bulkhead on line 9.... approved for concrete placement.

Footing Inspection Partial Pass 12/16/2019
Corrections:


Miscellaneous/Other
Comment Only
12/16/2019
Retaining wall Footing , pad footing and rebar at lines8.5 to line 11 at grid T....approved Piers on grid S lines 4 & 7.1 and grid Q.1 at line 4... approved

Footing Inspection Partial Pass 12/17/2019 (12:30 - 2:30) 12/17/2019 (PM) 12/17/2019
Corrections:


Miscellaneous/Other
Comment Only
12/17/2019
Pad footing at line 10 and grid Q.1 Pad footing at line 10 and grid S Line 12 pads/wall footings from corner to grid R.5 Approved for concrete placement

Footing Inspection Not Ready 12/18/2019 (10:00 - 12:00) 12/18/2019 (PM) 12/18/2019
Corrections:


Miscellaneous/Other
Comment Only
12/18/2019
Viewed the retaining wall rebar that is in process of being completed for concrete placement on 12/20.

Footing Inspection Partial Pass 12/19/2019 (10:00 - 12:00) 12/19/2019 (AM) 12/19/2019
Corrections:


Miscellaneous/Other
Comment Only
12/19/2019
Poured wall on grid T from line 1 to approximately line 7. Pads and wall footing on line 12 from grids T to approximately R.5. Pad footing with rebar at line 10 and grid Q.1. Pier at line 7.1 and grid Q.1. Approved for concrete placement.

Footing Inspection Partial Pass 12/23/2019 (10:00 - 12:00) 12/23/2019 (PM) 12/23/2019
Corrections:


Miscellaneous/Other
Comment Only
12/23/2019
Remaining of wall with rebar on line T... approved for concrete placement . Progress of wall rebar on line 12... being installed as per design.

Footing Inspection Partial Pass 12/26/2019 (10:00 - 12:00) 12/26/2019 (AM) 12/26/2019
Corrections:


Miscellaneous/Other
Comment Only
12/26/2019
Rebar and pad footings on grids N.5 & L.5 at line 7.1... approved Wall rebar on line 12 in progress and viewed as it is being installed in sections to be poured. Approved Waterproofing and insulation to wall of grid T... approved

Footing Inspection Partial Pass 12/27/2019 (10:00 - 12:00) 12/27/2019 (AM) 12/27/2019
Corrections:


Miscellaneous/Other
Comment Only
12/27/2019
3 piers on line 12 at grids S, R, and R.5. ... approved for concrete placement. Wall steel is being inspected as well for the next section of wall on line 12.

Footing Inspection Partial Pass 12/30/2019 (10:00 - 12:00) 12/30/2019 (AM) 12/30/2019
Corrections:


Miscellaneous/Other
Comment Only
12/30/2019
Rebar in wall on line 12 from grids Q.1 to N... approved for concrete placement. Waterproofing on line T of wall approved for the next lift of backfill.

Footing Inspection Partial Pass 12/31/2019 (10:00 - 12:00) 12/31/2019 (AM) 12/31/2019
Corrections:


Miscellaneous/Other
Comment Only
12/31/2019
Pad footings at lie7.1 at grids J.5 and G.5 Piers at line 7.1 at grids N.5 and L.5 Rebar for Wall footing and pads on line 12 from grids N.5 to J Approved for concrete placement.

Footing Inspection Partial Pass 1/2/2020 (10:00 - 12:00) 1/2/2020 (AM) 01/02/2020
Corrections:


Miscellaneous/Other
Comment Only
01/02/2020
Rebar, pad footings and rebar for piers, wall footing with wall dowels on line 12 from grids J to D.5.... approved for concrete placement.

Footing Inspection Partial Pass 1/3/2020 (10:00 - 12:00) 1/3/2020 (AM) 01/03/2020
Corrections:


Miscellaneous/Other
Comment Only
01/03/2020
Another Wall section on grid 12... approved for concrete placement

Footing Inspection Partial Pass 1/6/2020 (10:00 - 12:00) 1/6/2020 (AM) 01/06/2020
Corrections:


Miscellaneous/Other
Comment Only
01/06/2020
Pad footings w/ rebar and pier bars on grid D.9 at lines 4, 7,8, &9, and and at grid D line 10... approved per plans. Wall rebar on line 12 to grid E... approved per plans. Piers on line 12 at grids Q.1, N.5, L.5, J.5, G.5... Approved for concrete placement. Waterproofing at outside walls , all of wall on Grid T, and first 4ft. lift at line 12 of walls already placed.

Footing Inspection Partial Pass 1/7/2020 (10:00 - 12:00) 1/7/2020 (AM) 01/07/2020
Corrections:


Miscellaneous/Other
Comment Only
01/07/2020
Section of poured wall on line 12 up to grid E. Piers at the footing pads on grid E. Rebar for footing pad on line 7.1 at grid D. All approved for concrete placement.

Footing Inspection Not Ready 1/8/2020 (10:00 - 12:00) 1/8/2020 (AM) 01/08/2020
Corrections:


Miscellaneous/Other
Comment Only
01/08/2020
Stripping forms and starting the underpinning forming of footings at existing building. Not ready for inspection today.

Footing Inspection Not Ready 1/9/2020 (10:00 - 12:00) 1/9/2020 (AM) 01/09/2020
Corrections:


Miscellaneous/Other
Comment Only
01/09/2020
Not ready for inspection

Footing Inspection Partial Pass 1/10/2020 (10:00 - 12:00) 1/10/2020 (AM) 01/10/2020
Corrections:


Miscellaneous/Other
Comment Only
01/10/2020
Rebar, pad bars, pier bars and wall bars in remaining outer footing on line 12 from grids D.9 past grid C. At line C from grids 9-12. Approved for concrete placement.

Footing Inspection Partial Pass 1/13/2020 (10:00 - 12:00) 1/13/2020 (AM) 01/13/2020
Corrections:


Miscellaneous/Other
Comment Only
01/13/2020
Progress of rebar for poured walls at the South east corner of line 12, bar mats are on the ground and tied . Placement of mats has not yet begun. Special inspection to verify the wall bars when they are in place and all formed up.

Footing Inspection Partial Pass 1/15/2020 (10:00 - 12:00) 1/15/2020 (AM) 01/15/2020
Corrections:


Miscellaneous/Other
Comment Only
01/15/2020
Rebar for.... pad, wall hooks, and footing bars on grid C from lines 9-6.5 Section of poly for the floor slab is laid out, rebar inspection to follow when in place.

Footing Inspection Partial Pass 1/17/2020 (10:00 - 12:00) 1/17/2020 (AM) 01/17/2020
Corrections:


Miscellaneous/Other
Comment Only
01/17/2020
Poured wall just east of line C up to about line 6...approved Reinforced slab from line M to E , from line 3 to 7.5 ... approved pending vertical bars install and special inspection.

Footing Inspection Partial Pass 1/21/2020 (10:00 - 12:00) 1/21/2020 (AM) 01/21/2020
Corrections:


Miscellaneous/Other
Comment Only
01/21/2020
Mat slab 1.... installation of column bars into slab for concrete placement on 01/22/20. Bars approved and ok to place concrete for this mat slab.

Footing Inspection Partial Pass 1/22/2020 (10:00 - 12:00) 1/22/2020 (AM) 01/22/2020
Corrections:


Miscellaneous/Other
Comment Only
01/22/2020
Progress of mat slab pour #2 , grids a to E lines 8 to 11.... bottom mat is almost completed, still working on rebar placement of both mats. Slab on grad at grids R.8 to T.2 lines 1 to 3.5... underslab poly approved, rebar to be viewed in the morning of 1/23. This is a progress inspection only, not ready for concrete at this time.

Footing Inspection Not Ready 1/24/2020 (10:00 - 12:00) 1/24/2020 (AM) 01/24/2020
Corrections:


Miscellaneous/Other
Comment Only
01/24/2020
Not ready for inspection.

Footing Inspection Partial Pass 1/27/2020 (10:00 - 12:00) 1/27/2020 (AM) 01/27/2020
Corrections:


Miscellaneous/Other
Comment Only
01/27/2020
10 columns on lines 3&4 at grids M,L, K,J, and H. 3 pad footings on lines 2 at grids B, C, and D and one pad footing on line 4 grid D. Wall footing on line 1 from corner to corner of existing building approximately D.5 to A. Special inspector to view wall dowel rebar that isn’t in yet. Approved for concrete placement

Footing Inspection Partial Pass 1/28/2020 (10:00 - 12:00) 1/28/2020 (AM) 01/28/2020
Corrections:


Miscellaneous/Other
Outstanding
01/28/2020
Columns at line 3 , grids E,F,& G. Columns at line 5, grids E & G. Infill underpinnings at existing footing of building shown on plans at grid zP. Approved for concrete placement

Footing Inspection Partial Pass 1/29/2020 (10:00 - 12:00) 1/29/2020 (AM) 01/29/2020
Corrections:


Miscellaneous/Other
Comment Only
01/29/2020
Columns on lines 4,5,6,&7 as marked on plans.. approved

Footing Inspection Partial Pass 1/30/2020 (10:00 - 12:00) 1/30/2020 (AM) 01/30/2020
Corrections:


Miscellaneous/Other
Comment Only
01/30/2020
Line 2 all columns are completed. Line 4, 5 columns completed and inspected to grid H Line 5 all columns completed and inspected except for Line G line 6 all columns completed and inspected to grid F Line 7, 4 columns inspected to grid J Wall on line 1 still in process of rebar placement, all bars are in place but needing to be tied. Approved.

Footing Inspection Partial Pass 1/31/2020 (10:00 - 12:00) 1/31/2020 (AM) 01/31/2020
Corrections:


Miscellaneous/Other
Comment Only
01/31/2020
All columns inspected on Lines 3,4,5,6, and at line 7 the column set grids M to J an at E... Approved Wall at line 1 approved. Rebar being set at last section of wall footing, bottom bars of footing and pads F6 and F3 in place. Special inspection to verify the remaining bars at top mat and the 2 F1 pad bars.

Footing Inspection Partial Pass 02/05/2020
Corrections:


Miscellaneous/Other
Comment Only
02/05/2020
Rebar for columns approved. Columns on line 8 completed. Line 9 from grids K to E . line 10 from J to E. Line 11 grid E approved.

Progress Inspection Not Ready 2/10/2020 (12:30 - 2:30) 2/10/2020 (PM) 02/10/2020
Contractor called and cancelled the 2/6/2020 and 02/07/2020 inspections with Brian Post. Special inspections will take place. jsmidt 02/05/2020 1:03 PM
Corrections:


Miscellaneous/Other
Comment Only
02/10/2020
Concrete being placed for the already inspected wall. Not ready or any other inspections.

Footing Inspection Passed 2/7/2020 (10:00 - 12:00) 06/09/2020
Corrections:


Miscellaneous/Other
Comment Only
06/09/2020
All footings completed

Building Final Inspection Passed 06/09/2020
Corrections:


Miscellaneous/Other
Comment Only
06/09/2020
Final for this permit approved.