Summary

PRFD201912708
Foundation
Finaled
THE LUTHER COMPANY LLLP
Other
Not Required
DJ Kranz Co., Inc. will be building a Subaru car dealership near American Blvd and Lyndale Ave intersection. Requesting permit for footings and foundation for new build.
10/18/2019
01/02/2020
10/20/2020
04/23/2020

Locations

Permits

Permit Number: PRFD201912708

Foundation
Finaled
01/02/2020
10/20/2020

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Footing Inspection Partial Pass 1/7/2020 (12:30 - 2:30) 1/7/2020 (PM) 01/07/2020
Corrections:


Miscellaneous/Other
Comment Only
01/07/2020
Consultation with contractor , not ready for inspection today. Work is still being formed and rebar placed. Frost blankets on site.

Footing Inspection Partial Pass 1/8/2020 (12:30 - 2:30) 1/8/2020 (PM) 01/08/2020
Corrections:


Miscellaneous/Other
Comment Only
01/08/2020
Rebar as per plans for this concrete placement.... Grids J & G from lines 1.5 to 2.7. Elevator pads and column pad at line 2.7 grid F. Line E.6 grids 2 - 3 Approved for concrete placement. Special inspector to verify and take concrete cylinders.

Footing Inspection Not Ready 1/9/2020 (12:30 - 2:30) 1/9/2020 (PM) 01/09/2020
Corrections:


Miscellaneous/Other
Comment Only
01/09/2020
Not ready for inspection, still forming and setting rebar for the next footing placement.

Footing Inspection Partial Pass 1/10/2020 (12:30 - 2:30) 1/10/2020 (PM) 01/13/2020
Corrections:


Miscellaneous/Other
Comment Only
01/10/2020
Rebar , pad bar, and wall imbed bars, for strip footings at grid G linens 1 - 1.7. Line 1 grids D - G .... approved for concrete placement.

Miscellaneous/Other
Comment Only
01/13/2020
Rebar , pad bar, and wall imbed bars, for strip footings at grid G linens 1 - 1.7. Line 1 grids D - G .... approved for concrete placement.

Footing Inspection Partial Pass 1/13/2020 (12:30 - 2:30) 1/13/2020 (PM) 01/13/2020
Corrections:


Miscellaneous/Other
Comment Only
01/13/2020
Rebar for poured walls at line G around car lift to in between line 1&1.7. Line 2 from G to E.6.

Footing Inspection Partial Pass 1/15/2020 (12:30 - 2:30) 1/15/2020 (PM) 01/15/2020
Corrections:


Miscellaneous/Other
Comment Only
01/15/2020
Poured walls on grid G from line 1 to line 2 and encompassing the stoop and car lift. Line 2 to E.6 and onto E.6 from line to halfway to 3. Approved for concrete placement.

Footing Inspection Partial Pass 1/17/2020 (12:30 - 2:30) 1/17/2020 (PM) 01/17/2020
Corrections:


Miscellaneous/Other
Comment Only
01/17/2020
Poured walls on line E.6. Elevator walls already viewed at prior inspection...approved for concrete placement Grid H walls walls between lines 2-2.7...approved

Footing Inspection Not Ready 1/21/2020 (12:30 - 2:30) 1/21/2020 (PM) 01/21/2020
Corrections:


Miscellaneous/Other
Comment Only
01/21/2020
Not ready for inspection today. Stripping forms and set up for next footing pour is in process.

Footing Inspection Partial Pass 1/22/2020 (12:30 - 2:30) 1/22/2020 (PM) 01/22/2020
Corrections:


Miscellaneous/Other
Comment Only
01/22/2020
Wall footing at line 1 from grid D to north corner and turning East from lines 1 to just beyond grid 2. Wall footing at C.6 that includes the stair. Strip footing at parts lift. Approved for concrete placement

Footing Inspection Partial Pass 1/23/2020 (12:30 - 2:30) 1/23/2020 (PM) 01/23/2020
Corrections:


Miscellaneous/Other
Comment Only
01/23/2020
Rebar for walls at line 1 from D to C. 6 corner and from corner to line 2. Wall rebar at parts lift footing, and wall that includes stair. Approved.

Footing Inspection Not Ready 1/24/2020 (12:30 - 2:30) 1/24/2020 (PM) 01/24/2020
Corrections:


Miscellaneous/Other
Comment Only
01/24/2020
No footings or walls for inspection today, concrete is being placed to areas already inspected.

Footing Inspection Not Ready 1/27/2020 (12:30 - 2:30) 1/27/2020 (PM) 01/27/2020
Corrections:


Miscellaneous/Other
Comment Only
01/27/2020
Soil corrections being done and forming of connecting footings for today. Not ready for inspection of footings and rebar. Will view all footings with inspection on 1/28.

Footing Inspection Partial Pass 1/28/2020 (12:30 - 2:30) 1/28/2020 (PM) 01/28/2020
Corrections:


Miscellaneous/Other
Comment Only
01/28/2020
Footing on line 2. Footing on Grid Z lines 2-3 Approved for concrete placement

Footing Inspection Not Ready 1/29/2020 (12:30 - 2:30) 1/29/2020 (PM) 01/29/2020
Corrections:


Miscellaneous/Other
Comment Only
01/29/2020
Stripping forms and digging for footings, not ready for inspection today.

Footing Inspection Partial Pass 1/30/2020 (12:30 - 2:30) 1/30/2020 (PM) 01/30/2020
Corrections:


Miscellaneous/Other
Comment Only
01/30/2020
Rebar for walls on line 2 and at line Z to line 3... Approved for concrete placement

Footing Inspection Partial Pass 1/31/2020 (12:30 - 2:30) 1/31/2020 (PM) 01/31/2020
Corrections:


Miscellaneous/Other
Comment Only
01/31/2020
Footings at Lin’s A.1 to just past B, grids 4-5. Stair footings adjoining and west of line 4

Footing Inspection Partial Pass 2/4/2020 (12:30 - 2:30) 2/4/2020 (PM) 02/04/2020
Corrections:


Miscellaneous/Other
Comment Only
02/04/2020
Pads on line 3 at grids B,C,D and E. Wall footings at Line 4 from grids A.1 to shy of D. Wall footings on line 6 from grids A.1to D.

Footing Inspection Not Ready 2/5/2020 (12:30 - 2:30) 2/5/2020 (PM) 02/05/2020
Corrections:


Miscellaneous/Other
Comment Only
02/05/2020
Not ready for inspection, still forming footings and placing rebar

Footing Inspection Partial Pass 2/6/2020 (12:30 - 2:30) 2/6/2020 (PM) 02/06/2020
Corrections:


Miscellaneous/Other
Comment Only
02/06/2020
Footings between grids D to E.6 on lines 4 & 6 including the stair footing that attaches to grid 4, approved for concrete placement. Missed pier at line 4 grid C to be epoxy’d into footing prior to wall forming and concrete placement.

Footing Inspection Not Ready 2/10/2020 (12:30 - 2:30) 2/10/2020 (PM) 02/10/2020
Corrections:


Miscellaneous/Other
Comment Only
02/10/2020
Forming up for wall pour, not ready for inspection. Column and pad at the line they are forming at this time need to be installed and the engineer to approve the design fix.

Footing Inspection Partial Pass 2/11/2020 (12:30 - 2:30) 2/11/2020 (PM) 02/11/2020
Corrections:


Miscellaneous/Other
Comment Only
02/11/2020
Continuation of poured walls on lines 4 &6 from grid B to E.6.

Footing Inspection Partial Pass 2/12/2020 (12:30 - 2:30) 2/12/2020 (PM) 02/12/2020
Corrections:


Miscellaneous/Other
Comment Only
02/12/2020
Remaining footing on line 4 to grid K . Footing fix at line 4 and grid C ...approved Approved for concrete placement

Footing Inspection Not Ready 2/13/2020 (12:30 - 2:30) 2/13/2020 (PM) 02/13/2020
Corrections:


Miscellaneous/Other
Comment Only
02/13/2020
No work being done today due to the minus temps. Not ready for inspection

Footing Inspection Not Ready 2/14/2020 (12:30 - 2:30) 2/14/2020 (PM) 02/14/2020
Corrections:


Miscellaneous/Other
Comment Only
02/14/2020
No work today, not ready for inspection.

Footing Inspection Not Ready 2/18/2020 (12:30 - 2:30) 2/18/2020 (PM) 02/18/2020
Corrections:


Miscellaneous/Other
Comment Only
02/18/2020
Ran into area in need of soil corrections, not ready for footing inspection.

Footing Inspection Partial Pass 2/19/2020 (12:30 - 2:30) 2/19/2020 (PM) 02/19/2020
Corrections:


Miscellaneous/Other
Comment Only
02/19/2020
Pads, footings at lines 2.5 to 4 at grids E.6 to K Approved for concrete placement

Footing Inspection Partial Pass 2/20/2020 (12:30 - 2:30) 2/20/2020 (PM) 02/20/2020
Corrections:


Miscellaneous/Other
Comment Only
02/20/2020
Footing at NE corner to tie in this corner. Lines 3 to 5 on grid Z to tie into footing at A.1 Approved for concrete placement

Footing Inspection Partial Pass 2/21/2020 (12:30 - 2:30) 2/21/2020 (PM) 02/21/2020
Corrections:


Miscellaneous/Other
Comment Only
02/21/2020
Poured walls connected at lines 3 & 4 and grid F.6 Approved for concrete placement

Footing Inspection Not Ready 2/24/2020 (12:30 - 2:30) 2/24/2020 (PM) 02/24/2020
Corrections:


Miscellaneous/Other
Comment Only
02/24/2020
Site cleanup and stripping forms, not ready for inspection today.

Footing Inspection Not Ready 2/25/2020 (12:30 - 2:30) 2/25/2020 (PM) 02/25/2020
Corrections:


Miscellaneous/Other
Comment Only
02/25/2020
No inspection today, contractor is not ready.

Footing Inspection Not Ready 2/26/2020 (12:30 - 2:30) 2/26/2020 (PM) 02/26/2020
Corrections:


Miscellaneous/Other
Comment Only
02/26/2020
Not ready for inspection

Footing Inspection Partial Pass 2/27/2020 (12:30 - 2:30) 2/27/2020 (PM) 02/27/2020
Corrections:


Miscellaneous/Other
Comment Only
02/27/2020
Poured walls at remainder of grid Z and line 5. This completes this NE corner. Poured was at line 2.5 to line 4 grids K and H. This completes the SE corner. All frost footings and stoops, and poured walls are completed.

Building Final Inspection Passed 04/23/2020
Corrections:


Miscellaneous/Other
Comment Only
04/23/2020
All footings and Foundations are in, the permit for this phase of the project is completed. See permit 201915119 for the remainder of work and inspections with this project. Final for this foundation and footing permit approved.