Permit Application Status

PRFD202103306


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRFD202103306
Foundation
Expired
PARS PROPERTIES LLC
Other
Not Required
Demolition of an existing parking lot, installation of temporary shoring, excavation, underground utility work, footings, foundations, and precast concrete erection for a new 146 unit multi-family housing project.
03/29/2021
07/23/2021
12/10/2024

Locations

Permits

Permit Number: PRFD202103306

Foundation
Expired
07/23/2021
12/10/2024

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Footing Inspection Partial Pass 11/19/2021 (7:00 - 8:00) 11/19/2021 (AM) 11/19/2021
Corrections:


Miscellaneous/Other
Comment Only
11/19/2021
Perimeter footings with incorporated pads… Grid “H” to “M” Grid “M” Line 16 to and included line 4 Small section of grid “G” to pour stop Approved for concrete placement pending special inspection.

Footing Inspection Partial Pass 11/24/2021 (10:00 - 12:00) 11/24/2021 (AM) 11/24/2021
Corrections:


Miscellaneous/Other
Comment Only
11/24/2021
Poured walls at Grid 13 h -m Grid 16 h-m Approved for concrete placement

Footing Inspection Partial Pass 11/30/2021 (10:00 - 12:00) 11/30/2021 (AM) 11/30/2021
Corrections:


Miscellaneous/Other
Comment Only
11/30/2021
Grid line G 5 to grid line 12 CC Grid line A 4-8 Approved for concrete placement

Footing Inspection Partial Pass 12/7/2021 (10:00 - 12:00) 12/7/2021 (AM) 12/07/2021
Corrections:


Miscellaneous/Other
Comment Only
12/07/2021
Footings and rebar closing in the NE corner . Footing on the remainder of line 12. Footing on all of grid AA. Footing on line 9, tying into the footing at grid A. Wall section on line 2 was previously inspected at last inspection and now formed. Approved for concrete placement.

Footing Inspection Partial Pass 12/13/2021 (10:00 - 12:00) 12/13/2021 (AM) 12/13/2021
Corrections:


Miscellaneous/Other
Comment Only
12/13/2021
Poured wall on grid “AA” Poured wall on line 12, grid “AA - CC”. Approved for concrete placement

Footing Inspection Partial Pass 12/16/2021
Corrections:


Miscellaneous/Other
Comment Only
12/16/2021
3 footing pads on line 10, grids BB, CC, & CC.3 Piers on line 12 and the last formed section of wall… approved for concrete placement

Progress Inspection Partial Pass 12/21/2021 (8:00 - 10:00) 12/21/2021 (AM) 12/21/2021
Corrections:


Miscellaneous/Other
Comment Only
12/21/2021
First lift of waterproofing and 2” foam panel insulation on foundation at north perimeter … approved and ok to start backfill of first lift.

Footing Inspection Partial Pass 12/22/2021 (10:00 - 12:00) 12/22/2021 (AM) 12/22/2021
Corrections:


Miscellaneous/Other
Comment Only
12/22/2021
Drain tile at section of retaining wall that is water proofed… approved Progress of the remaining section of retaining wall footing on west and north west corner is still ongoing with rebar installation, special inspection can inspect the remaining rebar before concrete placement…. Approval to place concrete is per special inspection.

Footing Inspection Partial Pass 12/28/2021 (10:00 - 12:00) 12/28/2021 (AM) 12/28/2021
Corrections:


Miscellaneous/Other
Comment Only
12/28/2021
Foundation wall waterproofing on north end second lift, is installed a per mfg and design. Foundation retaining wall on west end, rebar as per plans … approved for concrete placement.

Footing Inspection Passed 12/30/2021 (10:00 - 12:00) 12/30/2021 (AM) 12/30/2021
Corrections:


Miscellaneous/Other
Comment Only
12/30/2021
First lift of waterproofing on line 12 foundation… approved Last section of poured wall at west side retaining wall footing… approved for concrete placement.

Footing Inspection Partial Pass 1/4/2022 (10:00 - 12:00) 1/4/2022 (AM) 01/04/2022
Corrections:


Miscellaneous/Other
Comment Only
01/04/2022
Pad footings…. Line 15 / grid J.4 Line 3, grids H.2, G.2, F & B Line 14, grid H Line 2 / grid G.2, E.9, D.9, C, & B Grid B, line 4

Footing Inspection Partial Pass 1/5/2022 (10:00 - 12:00) 1/5/2022 (AM) 01/05/2022
Corrections:


Miscellaneous/Other
Comment Only
01/05/2022
Pad footings at grid B, lines 3,4,5,6 & 7… approved for concrete placement and cover with blankets.

Footing Inspection Partial Pass 1/18/2022 (10:00 - 12:00) 1/18/2022 (AM) 01/19/2022
Corrections:


Miscellaneous/Other
Comment Only
01/19/2022
Rebar for footings being placed today is not yet completed at time of city inspection. Special inspection of these are being done by Braun, see the special inspection report submitted by Braun. Ok to proceed with concrete placement under special inspection approval. Note… all special inspection reports are to be submitted to the city of Bloomington as soon as available.

Footing Inspection Partial Pass 1/21/2022 (12:30 - 2:30) 1/21/2022 (PM) 01/21/2022
Corrections:


Miscellaneous/Other
Comment Only
01/21/2022
Poured wall by grid D, to line 7… approved

Footing Inspection Not Ready 1/25/2022 (12:30 - 2:30) 1/25/2022 (PM) 01/25/2022
Corrections:


Miscellaneous/Other
Comment Only
01/25/2022
Inspection canceled due to weather and not having footings ready. Call for inspection when ready.

Footing Inspection Partial Pass 1/28/2022 (8:00 - 10:00) 1/28/2022 (AM) 01/28/2022
Corrections:


Miscellaneous/Other
Comment Only
01/28/2022
Pads at lines 3&4 grids D.9 and C. Pads at grids C, lines 5,6, & 7. Pad and wall footing on line 3, between grids D&C. Remaining strip footing tie in off grid D. Elevator pit between grids C and D, lines 3&4. All rebar approved. Elevator drain piping, (4” diameter) installed and tied in.

Progress Inspection Partial Pass 01/31/2022
Corrections:


Miscellaneous/Other
Comment Only
01/31/2022
Section of wall rebar for poured wall and rebar for elevator pit wall and columns… approved

Footing Inspection Partial Pass 2/1/2022 (10:00 - 12:00) 2/1/2022 (AM) 02/01/2022
Corrections:


Miscellaneous/Other
Comment Only
02/01/2022
Remaining wall section between lines 7&8, off grid D. Elevator pit walls. 3 pads on line 11, grids DD,CC, and BB . Approved for concrete placement.

Progress Inspection Partial Pass 3/29/2022 (8:00 - 10:00) 3/29/2022 (AM) 03/29/2022
Corrections:


Miscellaneous/Other
Comment Only
03/29/2022
Next lift of waterproofing and R-10 insulation installation at foundation … approved and ok to backfill.

Building Final Inspection Passed 06/13/2024
Corrections:


Miscellaneous/Other
Comment Only
06/13/2024
See permit PRBD202113550 for remainder of this building construction inspections.