Summary

PRFD202111024
Foundation
Issued
WALSER REAL ESTATE LLC
Other
Not Required
Initial work would involve site removals and reclaiming of existing pavement. Reclaimed pavement would then be used in cut/fill operation to create level site for the deep foundation work which will utilize steel piling. As deep foundations are being installed concrete foundations will follow when safe working distances are achieved. Construction will typically flow from south to the north.
08/19/2021
09/03/2021
05/09/2023

Locations

Permits

Permit Number: PRFD202111024

Foundation
Expired

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Progress Inspection Pending
Footing Inspection Passed 10/20/2021 (8:00 - 10:00) 10/20/2021 (AM) 10/20/2021
Miscellaneous/Other
Comment Only
10/20/2021
Three pile cap Footings as per plan marked in field, approved.

Footing Inspection Passed 10/27/2021 (8:00 - 10:00) 10/27/2021 (AM) 10/26/2021
Miscellaneous/Other
Comment Only
10/26/2021
Four pile Footings approved as per field marked plans.

Footing Inspection Passed 10/29/2021 (8:00 - 10:00) 10/29/2021 (AM) 10/29/2021
Miscellaneous/Other
Comment Only
10/29/2021
Six pier footings as per plan marked in field, approved.

Footing Inspection Passed 11/2/2021 (8:00 - 10:00) 11/2/2021 (AM) 11/02/2021
Miscellaneous/Other
Comment Only
11/02/2021
Two new pile Footings as per field marked plans approved.

Footing Inspection Passed 11/5/2021 (8:00 - 10:00) 11/5/2021 (AM) 11/05/2021
Miscellaneous/Other
Comment Only
11/05/2021
Miscellaneous footings as per drawings marked infield approved. Includes three pile Footings and grade beam at south east corner.

Progress Inspection Passed 11/10/2021 (10:00 - 12:00) 11/10/2021 (AM) 11/10/2021
Miscellaneous/Other
Comment Only
11/10/2021
Pylon footings and grade beams as per plans marked infield approved.

Footing Inspection Passed 11/17/2021 (10:00 - 12:00) 11/17/2021 (AM) 11/17/2021
Miscellaneous/Other
Comment Only
11/17/2021
Pad footings on column lines B, C, D and G as marked infield approved.

Footing Inspection Passed 11/23/2021 (10:00 - 12:00) 11/23/2021 (AM) 11/19/2021
Miscellaneous/Other
Comment Only
11/19/2021
Six pad footings as per field marked drawings approved.

Miscellaneous/Other
Comment Only
11/23/2021
Seven pad footings on November 23 as per drawings marked in field, approved.

Footing Inspection Passed 11/24/2021 (10:00 - 12:00) 11/24/2021 (AM) 11/24/2021
Miscellaneous/Other
Comment Only
11/24/2021
Pad footings on column lines 1 and seven as per marked plan approved.

Footing Inspection Passed 11/29/2021 (12:30 - 2:30) 11/29/2021 (PM) 11/29/2021
Miscellaneous/Other
Comment Only
11/29/2021
Free pile cap Footings as per field marked drawings approved.

Footing Inspection Passed 12/1/2021 (12:30 - 2:30) 12/1/2021 (PM) 12/01/2021
Miscellaneous/Other
Comment Only
12/01/2021
To pile footings at elevator that include field revisions.

Footing Inspection Passed 12/6/2021 (12:30 - 2:30) 12/6/2021 (PM) 12/06/2021
Miscellaneous/Other
Comment Only
12/06/2021
Poured foundation walls at elevator pit approved.

Footing Inspection Passed 12/7/2021 (12:30 - 2:30) 12/7/2021 (PM) 12/07/2021
Miscellaneous/Other
Comment Only
12/07/2021
Two pile caps as per marked drawing approved.

Footing Inspection Passed 12/13/2021 (12:30 - 2:30) 12/13/2021 (PM) 12/13/2021
Miscellaneous/Other
Comment Only
12/13/2021
Two footings and column lines F7 and G6 approved.

Progress Inspection Passed 12/15/2021 (10:00 - 12:00) 12/15/2021 (AM) 12/15/2021
Miscellaneous/Other
Comment Only
12/15/2021
Two footings on column line F and three footings on column line E approved.

Progress Inspection Passed 12/17/2021 (10:00 - 12:00) 12/17/2021 (AM) 12/17/2021
Miscellaneous/Other
Comment Only
12/17/2021

Miscellaneous/Other
Outstanding
12/17/2021
Last footing pad on pilling caps - F-6. A. Contractor to lift and shift rebar, using straps and lift. B. Ok to proceed. C. Temp =15 degree F.

Building Final Inspection Passed 11/10/2022 (10:00 - 12:00) 11/10/2022 (AM) 11/10/2022