PRFD202111024
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Progress Inspection | Pending | |||
Footing Inspection | Passed | 10/20/2021 (8:00 - 10:00) | 10/20/2021 (AM) | 10/20/2021 |
Miscellaneous/Other
Comment Only
10/20/2021
Three pile cap Footings as per plan marked in field, approved.
|
||||
Footing Inspection | Passed | 10/27/2021 (8:00 - 10:00) | 10/27/2021 (AM) | 10/26/2021 |
Miscellaneous/Other
Comment Only
10/26/2021
Four pile Footings approved as per field marked plans.
|
||||
Footing Inspection | Passed | 10/29/2021 (8:00 - 10:00) | 10/29/2021 (AM) | 10/29/2021 |
Miscellaneous/Other
Comment Only
10/29/2021
Six pier footings as per plan marked in field, approved.
|
||||
Footing Inspection | Passed | 11/2/2021 (8:00 - 10:00) | 11/2/2021 (AM) | 11/02/2021 |
Miscellaneous/Other
Comment Only
11/02/2021
Two new pile Footings as per field marked plans approved.
|
||||
Footing Inspection | Passed | 11/5/2021 (8:00 - 10:00) | 11/5/2021 (AM) | 11/05/2021 |
Miscellaneous/Other
Comment Only
11/05/2021
Miscellaneous footings as per drawings marked infield approved. Includes three pile Footings and grade beam at south east corner.
|
||||
Progress Inspection | Passed | 11/10/2021 (10:00 - 12:00) | 11/10/2021 (AM) | 11/10/2021 |
Miscellaneous/Other
Comment Only
11/10/2021
Pylon footings and grade beams as per plans marked infield approved.
|
||||
Footing Inspection | Passed | 11/17/2021 (10:00 - 12:00) | 11/17/2021 (AM) | 11/17/2021 |
Miscellaneous/Other
Comment Only
11/17/2021
Pad footings on column lines B, C, D and G as marked infield approved.
|
||||
Footing Inspection | Passed | 11/23/2021 (10:00 - 12:00) | 11/23/2021 (AM) | 11/19/2021 |
Miscellaneous/Other
Comment Only
11/19/2021
Six pad footings as per field marked drawings approved.
|
||||
Miscellaneous/Other
Comment Only
11/23/2021
Seven pad footings on November 23 as per drawings marked in field, approved.
|
||||
Footing Inspection | Passed | 11/24/2021 (10:00 - 12:00) | 11/24/2021 (AM) | 11/24/2021 |
Miscellaneous/Other
Comment Only
11/24/2021
Pad footings on column lines 1 and seven as per marked plan approved.
|
||||
Footing Inspection | Passed | 11/29/2021 (12:30 - 2:30) | 11/29/2021 (PM) | 11/29/2021 |
Miscellaneous/Other
Comment Only
11/29/2021
Free pile cap Footings as per field marked drawings approved.
|
||||
Footing Inspection | Passed | 12/1/2021 (12:30 - 2:30) | 12/1/2021 (PM) | 12/01/2021 |
Miscellaneous/Other
Comment Only
12/01/2021
To pile footings at elevator that include field revisions.
|
||||
Footing Inspection | Passed | 12/6/2021 (12:30 - 2:30) | 12/6/2021 (PM) | 12/06/2021 |
Miscellaneous/Other
Comment Only
12/06/2021
Poured foundation walls at elevator pit approved.
|
||||
Footing Inspection | Passed | 12/7/2021 (12:30 - 2:30) | 12/7/2021 (PM) | 12/07/2021 |
Miscellaneous/Other
Comment Only
12/07/2021
Two pile caps as per marked drawing approved.
|
||||
Footing Inspection | Passed | 12/13/2021 (12:30 - 2:30) | 12/13/2021 (PM) | 12/13/2021 |
Miscellaneous/Other
Comment Only
12/13/2021
Two footings and column lines F7 and G6 approved.
|
||||
Progress Inspection | Passed | 12/15/2021 (10:00 - 12:00) | 12/15/2021 (AM) | 12/15/2021 |
Miscellaneous/Other
Comment Only
12/15/2021
Two footings on column line F and three footings on column line E approved.
|
||||
Progress Inspection | Passed | 12/17/2021 (10:00 - 12:00) | 12/17/2021 (AM) | 12/17/2021 |
Miscellaneous/Other
Comment Only
12/17/2021
|
||||
Miscellaneous/Other
Outstanding
12/17/2021
Last footing pad on pilling caps - F-6. A. Contractor to lift and shift rebar, using straps and lift. B. Ok to proceed. C. Temp =15 degree F.
|
||||
Building Final Inspection | Passed | 11/10/2022 (10:00 - 12:00) | 11/10/2022 (AM) | 11/10/2022 |