Summary

PRFD202214935
Foundation
Finaled
BLOOMINGTON QOZ VENTURES LLC
Other
Not Required
Footing and foundation work for 235-unit market rate apartment building known as The Ardor. Includes two levels of underground parking and one level of precast concrete construction at grade.
12/02/2022
01/05/2023
06/03/2025
12/05/2024

Locations

Permits

Permit Number: PRFD202214935

Foundation
Finaled
01/05/2023
06/03/2025

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Footing Inspection Not Ready 2/7/2023 (12:30 - 2:30) 2/7/2023 (PM) 02/07/2023
Inspection canceled for today. Additional inspection on 2/14/23.
Corrections:


Miscellaneous/Other
Comment Only
02/07/2023
Inspection was canceled by contractor

Footing Inspection Partial Pass 2/8/2023 (12:30 - 2:30) 2/8/2023 (PM) 02/08/2023
Corrections:


Miscellaneous/Other
Comment Only
02/08/2023
Perimeter footings at Grid line H.5 , line 1-2.5 Line 1, Grid H.5-L Footings will be rechecked at inspection on 2/9 for remaining rebar that needs to be installed.

Footing Inspection Partial Pass 2/9/2023 (12:30 - 2:30) 2/9/2023 (PM) 02/09/2023
Corrections:


Miscellaneous/Other
Comment Only
02/09/2023
Approved for concrete placement at these line and grid locations. Line1, from just beyond grid J to L. Line 2.4 from grid K to L Grid L from Line 1 to 7

Footing Inspection Partial Pass 2/16/2023 (10:00 - 12:00) 2/16/2023 (AM) 02/16/2023
Corrections:


Miscellaneous/Other
Comment Only
02/16/2023
Strip footings on grid K, from lines 2.5-5. Strip footing and 3- F7 pads on Grid Z1, lines 7.6-9.5 F11 pad on line 4, grid J. F14 pad on line 5, grid J. Approved for concrete placement.

Footing Inspection Partial Pass 2/17/2023 (10:00 - 12:00) 2/17/2023 (AM) 02/17/2023
Corrections:


Miscellaneous/Other
Comment Only
02/17/2023
F12 pad at grid H , line 6 F10 pads at grid H, lines7&8 F10 pad at grid G, line 8 Approved for concrete placement

Footing Inspection Partial Pass 2/21/2023 (10:00 - 12:00) 2/21/2023 (AM) 02/21/2023
Corrections:


Miscellaneous/Other
Comment Only
02/21/2023
Section of Drain tile along grid L and grid Z1… installation approved.

Footing Inspection Not Ready 2/22/2023 (10:00 - 12:00) 2/22/2023 (AM) 02/22/2023
Corrections:


Miscellaneous/Other
Comment Only
02/22/2023
Inspection canceled by contractor due to weather.

Footing Inspection Not Ready 2/23/2023 (10:00 - 12:00) 2/23/2023 (AM) 02/23/2023
Corrections:


Miscellaneous/Other
Comment Only
02/23/2023
Inspection canceled by contractor due to weather

Footing Inspection Not Ready 2/24/2023 (10:00 - 12:00) 2/24/2023 (AM) 02/24/2023
Corrections:


Miscellaneous/Other
Comment Only
02/24/2023
Not ready for inspection

Footing Inspection Not Ready 2/27/2023 (10:00 - 12:00) 2/27/2023 (AM) 02/27/2023
Corrections:


Miscellaneous/Other
Comment Only
02/27/2023
Inspection canceled by contractor, not ready.

Footing Inspection Not Ready 2/28/2023 (10:00 - 12:00) 2/28/2023 (AM) 02/28/2023
Corrections:


Miscellaneous/Other
Comment Only
02/28/2023
Inspection canceled by contractor, not ready for inspection.

Footing Inspection Partial Pass 3/1/2023 (10:00 - 12:00) 3/1/2023 (AM) 03/01/2023
Corrections:


Miscellaneous/Other
Comment Only
03/01/2023
Strip footing on line 9.5 from grid G-F Footing on line Z1, from grid G-H Pad footing on grid G, line 9.5 Pad footings on grid G, lines 9&7 Pad footing on grid F, lines 9,8,& 7 Pad footing on grid E, lines 8 & 7 Approved for concrete placement.

Footing Inspection Partial Pass 3/2/2023 (10:00 - 12:00) 3/2/2023 (AM) 03/02/2023
Corrections:


Miscellaneous/Other
Comment Only
03/02/2023
Strip footing at line 9, grids E to G Pad footing at line 9.5, grid E. Approved for concrete placement. Pad footings on line 6, grids E,F,G are not ready at time of inspection. If they are to be poured today, they need to be viewed by special inspection, along with the stepped footing on line Z1.

Footing Inspection Partial Pass 3/3/2023 (10:00 - 12:00) 3/3/2023 (AM) 03/03/2023
Corrections:


Miscellaneous/Other
Comment Only
03/03/2023
Pads in area “A” grid A.2, lines 2.9, 4.2, 5.8, 7.2 Strip footing on line 9.5 of area B. Retaining wall step footing at line Z1, grids F to E. Pad footings at line 6, grids E, F, and G. Approved for concrete placement.

Footing Inspection Partial Pass 3/7/2023 (12:30 - 2:30) 3/7/2023 (PM) 03/07/2023
Corrections:


Miscellaneous/Other
Comment Only
03/07/2023
WF4-6 footing at grid “A” , lines 2-8. WF2-6 footing at line 2, grids A-B.7 ( wall dowels to be drilled and epoxy set at this footing due to the need to relocate the access ramp. This was approved by the designer and special inspection will be needed for the epoxy setting of dowels. WF4-0 footing at grid B.7, lines 2-3.7 Footing pad F12 at grid B, line 3.1 Footing pad F14 at grid B, line 5 Approved for concrete placement.

Footing Inspection Partial Pass 3/8/2023 (12:30 - 2:30) 3/8/2023 (PM) 03/08/2023
Corrections:


Miscellaneous/Other
Comment Only
03/08/2023
Drain tile around the poured perimeter footings of area “A” installed as per design.

Footing Inspection Partial Pass 3/9/2023 (10:00 - 12:00) 3/9/2023 (AM) 03/09/2023
Corrections:


Miscellaneous/Other
Comment Only
03/09/2023
Grid A, from lines 8-12 including the WF2-0 stoop footings outside grid A. Pad on line 12, with WF2-6 footing that runs back to Grid A. Pads, elevator pit, stair and step footings, from lines 10.4-11, from Grid A to A.s. Note…. Contractor is aware of the concrete coverage issue at the elevator pit drain piping and is going to adjust the mats to gain clearance for concrete coverage at the rebar.

Footing Inspection Passed 3/13/2023 (10:00 - 12:00) 3/13/2023 (AM) 03/13/2023
Corrections:


Miscellaneous/Other
Comment Only
03/13/2023
Pads on Grid B, lines 6&7 Pads on grid A.2, lines 8.4 & 9.4 Rebar for retaining wall … approved Elevator wall rebar… approved

Footing Inspection Partial Pass 3/14/2023 (12:30 - 2:30) 3/14/2023 (PM) 03/14/2023
Corrections:


Miscellaneous/Other
Comment Only
03/14/2023
Retaining wall rebar… approved Rebar for Elevator pit walls… approved Pier … approved

Footing Inspection Not Ready 3/15/2023 (10:00 - 12:00) 3/15/2023 (AM) 03/15/2023
Corrections:


Miscellaneous/Other
Comment Only
03/15/2023
No footings being placed today, Agg piers are being placed for stabilization of soil where missed at design.

Footing Inspection Not Ready 3/16/2023 (10:00 - 12:00) 3/16/2023 (AM) 03/16/2023
Corrections:


Miscellaneous/Other
Comment Only
03/16/2023
Inspection canceled by contractor

Footing Inspection Not Ready 3/17/2023 (8:00 - 10:00) 3/17/2023 (AM) 03/17/2023
Corrections:


Miscellaneous/Other
Comment Only
03/17/2023
Inspection canceled by contractor, not ready.

Footing Inspection Partial Pass 3/21/2023 (10:00 - 12:00) 3/21/2023 (AM) 03/21/2023
Corrections:


Miscellaneous/Other
Comment Only
03/21/2023
F11 pad on line 8, grid A.2 F12 pad on line 9, grid A.2 F11 pad on line 10, grid A.2 F9 pad on line 12, grid A.2 Footing on line 12, grids A.2-C Footing on grid C, lines 9.5-12 F5 pad and strip footing at line 9.5, grid C to matchline of grid E.

Footing Inspection Partial Pass 3/22/2023 (10:00 - 12:00) 3/22/2023 (AM) 03/22/2023
Corrections:


Miscellaneous/Other
Comment Only
03/22/2023
(2) columns - CP-16 at line 1, between grids L and K. F9 pad on line 9, grid D (4) F11 pads on grid C, lines 9,8,7,&6. Approved for concrete placement

Footing Inspection Not Ready 3/23/2023 (10:00 - 12:00) 3/23/2023 (AM) 03/23/2023
Corrections:


Miscellaneous/Other
Comment Only
03/23/2023
Not ready for inspection, removing soils for the last section of footings.

Footing Inspection Partial Pass 3/24/2023 (10:00 - 12:00) 3/24/2023 (AM) 03/24/2023
Corrections:


Miscellaneous/Other
Comment Only
03/24/2023
Footing at grid B.6, lines 2-3.7 Line 3.7, grid B.6- grid E Pad at grid C, line 5 Pads at grid D, lines 5,6,7&8 Added footing extensions to already poured pad where geo piers wer added for soil stabilization. Extensions are per design.

Footing Inspection Partial Pass 5/11/2023 (10:00 - 12:00) 5/11/2023 (AM) 05/11/2023
Corrections:


Miscellaneous/Other
Comment Only
05/11/2023
Base layer, and Geo grid for the egress well retaining wall... approved Waterproofing and draintile with west side of building viewed for first lift.

Footing Inspection Passed 5/12/2023 (8:00 - 10:00) 5/12/2023 (AM) 05/12/2023
Corrections:


Miscellaneous/Other
Comment Only
05/12/2023
Retaining wall... geogrid placed where required as per design.

Footing Inspection Not Ready 6/20/2023 (12:30 - 2:30) 6/20/2023 (PM) 06/20/2023
Corrections:


Miscellaneous/Other
Comment Only
06/20/2023
Inspection canceled by contractor... not ready.

Footing Inspection Passed 6/21/2023 (10:00 - 12:00) 6/21/2023 (AM) 06/21/2023
Corrections:


Miscellaneous/Other
Comment Only
06/21/2023
Remainder of footing on grid D.1 Approved

Footing Inspection Not Ready 6/22/2023 (10:00 - 12:00) 6/22/2023 (AM) 06/22/2023
Corrections:


Miscellaneous/Other
Comment Only
06/22/2023
Inspection canceled by contractor

Footing Inspection Passed 06/23/2023
Corrections:


Miscellaneous/Other
Comment Only
06/23/2023
Rebar in poured wall on remaining footing section at grid Z.1.... approved

Building Final Inspection Passed 12/05/2024
Corrections:


Miscellaneous/Other
Comment Only
12/05/2024
Final approved