PRFD202307810
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Footing Inspection | Passed | 8/18/2023 (10:00 - 12:00) | 8/18/2023 (AM) | 08/18/2023 |
| Footing per plan, Passed. (Note: open electrical permit will call for there own final.) | ||||
| Footing Inspection | Passed | 9/1/2023 (10:00 - 12:00) | 9/1/2023 (AM) | 09/01/2023 |
| Location of sign has moved - new footing will need to be poured. See revised plans for new location. [Beyer\, Kelly @ 08/22/2023 9:36 AM] | ||||
|
Corrections:
Miscellaneous/Other
Comment Only
09/01/2023
New hole location and footing with rebar cage... approved
|
||||
| Building Final Inspection | Passed | 9/19/2023 (10:00 - 12:00) | 9/19/2023 (AM) | 09/19/2023 |