PRFD202315508
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Footing Inspection | Partial Pass | 5/29/2024 (8:00 - 10:00) | 5/29/2024 (AM) | 05/29/2024 |
Site meeting, Braun special inspector on site. Footing not ready today. | ||||
Corrections:
Miscellaneous/Other
Comment Only
05/29/2024
Site meeting with Braun, and (Weis Builders - Kevin Johnson.)
|
||||
Footing Inspection | Not Ready | 6/3/2024 (12:30 - 2:30) | 6/3/2024 (PM) | 06/03/2024 |
Rained out today. | ||||
Footing Inspection | Passed | 6/4/2024 (12:30 - 2:30) | 6/4/2024 (PM) | 06/04/2024 |
Footing passed. Braun intertec on site. Strip footing for main bulding. West end. Passed | ||||
Corrections:
Miscellaneous/Other
Comment Only
06/04/2024
Strip footing, west end, for main building. Passed.
|
||||
Footing Inspection | Partial Pass | 6/5/2024 (12:30 - 2:30) | 6/5/2024 (PM) | 06/05/2024 |
North side strip footing and 2 pads. Steel reinforcement, per plan. Braun Intertec on site. Passed. Ongoing. | ||||
Corrections:
Miscellaneous/Other
Comment Only
06/05/2024
North side Strip footing, and two pads.passed Braun Intertec on site. Passed.
|
||||
Footing Inspection | Passed | 6/6/2024 (12:30 - 2:30) | 6/6/2024 (PM) | 06/06/2024 |
Corrections:
Miscellaneous/Other
Comment Only
06/06/2024
Three pad footings at West end and 50 feet of strip footing along south wall approved.
|
||||
Footing Inspection | Passed | 6/7/2024 (12:30 - 2:30) | 6/7/2024 (PM) | 06/07/2024 |
Corrections:
Miscellaneous/Other
Comment Only
06/07/2024
Three pad footings along north side, and 50 feet of strip footing along center of south wall, approved.
|
||||
Footing Inspection | Passed | 6/10/2024 (12:30 - 2:30) | 6/10/2024 (PM) | 06/10/2024 |
Corrections:
Miscellaneous/Other
Comment Only
06/10/2024
Footings for Northwest stairwell and 70 feet of strip footing along south wall approved.
|
||||
Footing Inspection | Passed | 6/11/2024 (12:30 - 2:30) | 6/11/2024 (PM) | 06/11/2024 |
Corrections:
Miscellaneous/Other
Comment Only
06/11/2024
Two pads along south wall and elevator pit approved.
|
||||
Footing Inspection | Not Ready | 6/13/2024 (12:30 - 2:30) | 6/13/2024 (PM) | 06/13/2024 |
Footing Inspection | Passed | 6/14/2024 (12:30 - 2:30) | 6/14/2024 (PM) | 06/14/2024 |
Corrections:
Miscellaneous/Other
Comment Only
06/14/2024
25 feet of strip footing along north side and one pad footing at south side. Approved.
|
||||
Footing Inspection | Not Ready | 6/17/2024 (12:30 - 2:30) | 6/17/2024 (PM) | 06/17/2024 |
Rain out, no footing concrete today. Very wet soil. Passed | ||||
Corrections:
Miscellaneous/Other
Comment Only
06/17/2024
Rain out, soil very wet. No concrete today. Not ready.
|
||||
Footing Inspection | Partial Pass | 6/18/2024 (12:30 - 2:30) | 6/18/2024 (PM) | 06/18/2024 |
On going reinforced footing and foundation pads, for south end of new building, working north. Passed. Special inspections by Braun intertec on site. Partial pass. | ||||
Footing Inspection | Partial Pass | 6/20/2024 (12:30 - 2:30) | 6/20/2024 (PM) | 06/20/2024 |
North side; Building strip footing and large footing pads. Passed. | ||||
Corrections:
Miscellaneous/Other
Comment Only
06/20/2024
North side, large pad footings, and strip footings with steel rebar. Braun Intertec on site. Passed.
|
||||
Footing Inspection | Not Ready | 6/21/2024 (12:30 - 2:30) | 6/21/2024 (PM) | 06/21/2024 |
Rain out. | ||||
Corrections:
Miscellaneous/Other
Comment Only
06/21/2024
Rain out.
|
||||
Footing Inspection | Partial Pass | 6/26/2024 (8:00 - 10:00) | 6/26/2024 (AM) | 06/26/2024 |
East end of new building, passed. Braun testing company on site today. (Starting exterior of CMU BLOCK foundation, WATERPROOFING..PARTIAL PASS, ONGOING INSPECTIONS.) | ||||
Corrections:
Miscellaneous/Other
Comment Only
06/26/2024
CMU Block foundation, and exterior SPRAY APPLIED WATERPROOFING .
PASSED.
|
||||
Footing Inspection | Partial Pass | 6/27/2024 (12:30 - 2:30) | 6/27/2024 (PM) | 06/27/2024 |
Footing and CMU corefill. Passed as ongoing inspections. | ||||
Corrections:
Miscellaneous/Other
Comment Only
06/27/2024
Footing and CMU corefill. Passed.
|
||||
Footing Inspection | Partial Pass | 6/28/2024 (12:30 - 2:30) | 6/28/2024 (PM) | 06/28/2024 |
Ongoing work, east end of new building, passed. Braun on site. | ||||
Corrections:
Miscellaneous/Other
Comment Only
06/28/2024
East end of new building. Passed. Braun Intertec on site. Passed.
|
||||
Footing Inspection | Partial Pass | 7/1/2024 (12:30 - 2:30) | 7/1/2024 (PM) | 07/01/2024 |
Ongoing, poured wall with reinforcement, east end of building foundation. Passed. Ongoing, core fill CMU MASONRY EXTERIOR FOUNDATION WALL. Passed. (Braun Intertec on site. Ongoing. Partial pass.) | ||||
Corrections:
Miscellaneous/Other
Comment Only
07/01/2024
Core fill, new CMU REINFORCED EXTERIOR WALL ON NEW FOOTING,
PASSED. ONGOING.
|
||||
Footing Inspection | Partial Pass | 7/2/2024 (12:30 - 2:30) | 7/2/2024 (PM) | 07/02/2024 |
Ongoing poured concrete inspections, new foundation work. Braun Intertec on site. Ongoing inspections, partial pass. | ||||
Corrections:
Miscellaneous/Other
Comment Only
07/02/2024
Ongoing poured concrete foundation. Passed.
Braun Intertec on site for special inspections.
|
||||
Footing Inspection | Partial Pass | 7/3/2024 (12:30 - 2:30) | 7/3/2024 (PM) | 07/03/2024 |
East end poured reinforced wall. Braun Intertec on site. Passed. | ||||
Corrections:
Miscellaneous/Other
Comment Only
07/03/2024
East end of building, reinforced concrete foundation wall. Passed.
|
||||
Footing Inspection | Partial Pass | 7/8/2024 (12:30 - 2:30) | 7/8/2024 (PM) | 07/08/2024 |
Ongoing foundation and footing inspection. Partial Passed. | ||||
Corrections:
Miscellaneous/Other
Comment Only
07/08/2024
Foundation and site inspection, passed. Partial pass for ongoing inspections.
|
||||
Footing Inspection | Partial Pass | 7/9/2024 (12:30 - 2:30) | 7/9/2024 (PM) | 07/09/2024 |
Progress, inspection. A. Backfilling exterior side of foundation. Ongoing. Braun Intertec on site. Partial pass. Ongoing inspections. | ||||
Corrections:
Miscellaneous/Other
Comment Only
07/09/2024
Progress, back filling exterior side of new foundation. Partial pass ongoing.
|
||||
Footing Inspection | Partial Pass | 7/11/2024 (12:30 - 2:30) | 7/11/2024 (PM) | 07/11/2024 |
Footing inspection, soil testing gradation for exterior wall backfill soil. Concrete or masonry corefill, for reinforced CMU walls. Passed. (Partial pass for future inspections ). | ||||
Corrections:
Miscellaneous/Other
Comment Only
07/11/2024
Back fill, for exterior side of new foundation. Pass. Note; Partial pass for ongoing future inspections.
|
||||
Footing Inspection | Partial Pass | 7/12/2024 (12:30 - 2:30) | 7/12/2024 (PM) | 07/12/2024 |
Footing-foundation. Work completed. City requires all special inspection reports provided to (Kelly Byer@ city of Bloomingtonmn.gov . | ||||
Corrections:
Miscellaneous/Other
Comment Only
07/12/2024
Footing/foundation completed. Partial pass. (All Braun special inspection reports must be emailed to (Kelly Byer, @Bloomingtonmn.gov ) prior to Kelly issuing the final approved BUILDING permit .
|
||||
Building Final Inspection | Passed | 03/31/2025 | ||
Corrections:
Miscellaneous/Other
Comment Only
03/31/2025
All foundation work has been completed . See permit 202403846 for remaining inspections of the building.
|