Summary

PRFD202414990
Foundation
Permit(s) Issued
THE LUTHER COMPANY LLLP
Other
Not Required
Footing and foundation permit request for a new Kia Building to replace the existing. A separate building permit application will be submitted for the structure itself.
11/11/2024
02/26/2025
10/19/2025

Locations

Permits

Permit Number: PRFD202414990

Foundation
Issued
02/26/2025
10/19/2025

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Building Final Inspection Pending
Footing Inspection Pending
Footing Inspection Passed 3/27/2025 (8:00 - 10:00) 3/27/2025 (AM) 03/27/2025
Corrections:


Miscellaneous/Other
Comment Only
03/27/2025
Perimeter footing and rebar with pads and column bars from grid F to Q, and Q to U. Pads and columns at grid R and PQ, line 11.

Footing Inspection Passed 3/31/2025 (10:00 - 12:00) 3/31/2025 (AM) 03/31/2025
Corrections:


Miscellaneous/Other
Comment Only
03/31/2025
Perimeter footings from grid U to V, and grid V to line 7. Footings for carwash off grid V. Stem wall from grid F to S.

Footing Inspection Not Ready 4/2/2025 (10:00 - 12:00) 4/2/2025 (AM) 04/02/2025
CANCELED; rescheduling. vm 4/2
Corrections:


Miscellaneous/Other
Comment Only
04/02/2025
Inspection canceled by contractor.

Footing Inspection Passed 4/4/2025 (10:00 - 12:00) 4/4/2025 (AM) 04/04/2025
Corrections:


Miscellaneous/Other
Comment Only
04/04/2025
Footings of Area B, grids S to V. Wall rebar grids 9A to 20, & A to F

Footing Inspection Passed 4/9/2025 (10:00 - 12:00) 4/9/2025 (AM) 04/09/2025
Corrections:


Miscellaneous/Other
Comment Only
04/09/2025
Poured walls for todays concrete pour... Foundation walls at carwash. Area B grid S to V. Insulation in process of installation at foundation... approved

Footing Inspection Passed 4/11/2025 (10:00 - 12:00) 4/11/2025 (AM) 04/11/2025
Corrections:


Miscellaneous/Other
Comment Only
04/11/2025
Footings / Pads at grid R, lines 19 to 15 Pads on line 14, grids H to Q Pads on line 20, grids H to R Perimeter footing line 18, grids S to V

Footing Inspection Passed 4/14/2025 (10:00 - 12:00) 4/14/2025 (AM) 04/14/2025
Cancelled inspection by contractor [jsmidt @ 04/14/2025 8:24 AM]
Corrections:


Miscellaneous/Other
Comment Only
04/14/2025
Inspection canceled by contractor

Footing Inspection Passed 4/15/2025 (10:00 - 12:00) 4/15/2025 (AM) 04/15/2025
Corrections:


Miscellaneous/Other
Comment Only
04/15/2025
Interior footings at... grids U and V, lines 1-7 Wall at grid T, lines 7-18 Piers at grid 14, H -Q . Line 17 and grid Q. Line 9, and grids J-Q.

Footing Inspection Passed 4/17/2025 (10:00 - 12:00) 4/17/2025 (AM) 04/17/2025
Corrections:


Miscellaneous/Other
Comment Only
04/17/2025
Footing on Grid "U". Stem wall at Grid "B". Pit at grid U, line 1. SE planter wall. Approved

Footing Inspection Passed 4/21/2025 (10:00 - 12:00) 4/21/2025 (AM) 04/21/2025
Corrections:


Miscellaneous/Other
Comment Only
04/21/2025
Grid U stem wall Line 21stemwall at SW corner E/W Footing at grid B

Footing Inspection Passed 4/22/2025 (10:00 - 12:00) 4/22/2025 (AM) 04/22/2025
Corrections:


Miscellaneous/Other
Comment Only
04/22/2025
Stem walls at E/W grid B approved for concrete.

Footing Inspection Not Ready 4/25/2025 (10:00 - 12:00) 4/25/2025 (AM) 04/25/2025
Corrections:


Miscellaneous/Other
Comment Only
04/25/2025
Inspection canceled by contractor, not ready for the next section of footings at this time.