PRFD202414990
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Building Final Inspection | Pending | |||
Footing Inspection | Pending | |||
Footing Inspection | Passed | 3/27/2025 (8:00 - 10:00) | 3/27/2025 (AM) | 03/27/2025 |
Corrections:
Miscellaneous/Other
Comment Only
03/27/2025
Perimeter footing and rebar with pads and column bars from grid F to Q, and Q to U.
Pads and columns at grid R and PQ, line 11.
|
||||
Footing Inspection | Passed | 3/31/2025 (10:00 - 12:00) | 3/31/2025 (AM) | 03/31/2025 |
Corrections:
Miscellaneous/Other
Comment Only
03/31/2025
Perimeter footings from grid U to V, and grid V to line 7.
Footings for carwash off grid V.
Stem wall from grid F to S.
|
||||
Footing Inspection | Not Ready | 4/2/2025 (10:00 - 12:00) | 4/2/2025 (AM) | 04/02/2025 |
CANCELED; rescheduling. vm 4/2 | ||||
Corrections:
Miscellaneous/Other
Comment Only
04/02/2025
Inspection canceled by contractor.
|
||||
Footing Inspection | Passed | 4/4/2025 (10:00 - 12:00) | 4/4/2025 (AM) | 04/04/2025 |
Corrections:
Miscellaneous/Other
Comment Only
04/04/2025
Footings of Area B, grids S to V.
Wall rebar grids 9A to 20, & A to F
|
||||
Footing Inspection | Passed | 4/9/2025 (10:00 - 12:00) | 4/9/2025 (AM) | 04/09/2025 |
Corrections:
Miscellaneous/Other
Comment Only
04/09/2025
Poured walls for todays concrete pour...
Foundation walls at carwash.
Area B grid S to V.
Insulation in process of installation at foundation... approved
|
||||
Footing Inspection | Passed | 4/11/2025 (10:00 - 12:00) | 4/11/2025 (AM) | 04/11/2025 |
Corrections:
Miscellaneous/Other
Comment Only
04/11/2025
Footings / Pads at grid R, lines 19 to 15
Pads on line 14, grids H to Q
Pads on line 20, grids H to R
Perimeter footing line 18, grids S to V
|
||||
Footing Inspection | Passed | 4/14/2025 (10:00 - 12:00) | 4/14/2025 (AM) | 04/14/2025 |
Cancelled inspection by contractor [jsmidt @ 04/14/2025 8:24 AM] | ||||
Corrections:
Miscellaneous/Other
Comment Only
04/14/2025
Inspection canceled by contractor
|
||||
Footing Inspection | Passed | 4/15/2025 (10:00 - 12:00) | 4/15/2025 (AM) | 04/15/2025 |
Corrections:
Miscellaneous/Other
Comment Only
04/15/2025
Interior footings at... grids U and V, lines 1-7
Wall at grid T, lines 7-18
Piers at grid 14, H -Q . Line 17 and grid Q. Line 9, and grids J-Q.
|
||||
Footing Inspection | Passed | 4/17/2025 (10:00 - 12:00) | 4/17/2025 (AM) | 04/17/2025 |
Corrections:
Miscellaneous/Other
Comment Only
04/17/2025
Footing on Grid "U".
Stem wall at Grid "B".
Pit at grid U, line 1.
SE planter wall.
Approved
|
||||
Footing Inspection | Passed | 4/21/2025 (10:00 - 12:00) | 4/21/2025 (AM) | 04/21/2025 |
Corrections:
Miscellaneous/Other
Comment Only
04/21/2025
Grid U stem wall
Line 21stemwall at SW corner
E/W Footing at grid B
|
||||
Footing Inspection | Passed | 4/22/2025 (10:00 - 12:00) | 4/22/2025 (AM) | 04/22/2025 |
Corrections:
Miscellaneous/Other
Comment Only
04/22/2025
Stem walls at E/W grid B approved for concrete.
|
||||
Footing Inspection | Not Ready | 4/25/2025 (10:00 - 12:00) | 4/25/2025 (AM) | 04/25/2025 |
Corrections:
Miscellaneous/Other
Comment Only
04/25/2025
Inspection canceled by contractor, not ready for the next section of footings at this time.
|