PRFD202502320
Foundation
Expired
CITY OF BLOOMINGTON
Not Required
Bloomington Bid Package #2 - Footings and Foundation for Rink 3.
03/07/2025
03/11/2025
11/24/2025

Locations

Permits

Permit Number: PRFD202502320

Foundation
Expired
03/11/2025
11/24/2025

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Building Final Inspection Pending
Footing Inspection Passed 3/25/2025 (10:00 - 12:00) 3/25/2025 (AM) 03/25/2025
Corrections:


Miscellaneous/Other
Comment Only
03/25/2025
Expanded footing improvements along north wall approved.

Footing Inspection Passed 4/1/2025 (8:00 - 10:00) 4/1/2025 (AM) 04/01/2025
Corrections:


Miscellaneous/Other
Comment Only
04/01/2025
Miscellaneous pad footings along east and west walls and pad footings along column line 3B approved.

Footing Inspection Passed 4/3/2025 (8:00 - 10:00) 4/3/2025 (AM) 04/03/2025
Corrections:


Miscellaneous/Other
Comment Only
04/03/2025
5 piers in area B... approved

Progress Inspection Passed 4/7/2025 (8:00 - 10:00) 4/7/2025 (AM) 04/07/2025
Vapor Barrier test
Corrections:


Miscellaneous/Other
Comment Only
04/07/2025
Viewed various sections where rebar , underslab poly and thickened footing of slab infills throughout areas... approved to place concrete . Veiwed the progress of the underpinning of double mat footing in the arena area where ramp will be located... progress of the infill is approved.

Progress Inspection Passed 4/9/2025 (10:00 - 12:00) 4/9/2025 (AM) 04/09/2025
Corrections:


Miscellaneous/Other
Comment Only
04/09/2025
First progress inspection of underpinning walls in rink number one approved.

Progress Inspection Passed 4/14/2025 (10:00 - 12:00) 4/14/2025 (AM) 04/14/2025
Corrections:


Miscellaneous/Other
Comment Only
04/14/2025
Reinforced slab inspection at West side, toilet rooms, trench in rink area number two between column lines C and D, south east toilet room at rink number two approved. Progress inspection of Reinforced structural walls in rink number one approved.

Progress Inspection Passed 4/23/2025 (8:00 - 10:00) 4/23/2025 (AM) 04/23/2025
Reinforced slab in section a concession area and section a toilet room areas approved. Inspection of reinforced walls in number one approved.
Corrections:


Miscellaneous/Other
Comment Only
04/15/2025
Reinforced slab inspections for concessions and remaining toilet rooms approved. Progress inspection of reinforced walls in number one approved.

Miscellaneous/Other
Comment Only
04/23/2025
Miscellaneous pads, trenches, and slab preparation for bleacher area in rink number three approved.

Progress Inspection Passed 5/28/2025 (8:00 - 10:00) 5/28/2025 (AM) 05/28/2025
Corrections:


Miscellaneous/Other
Comment Only
05/28/2025
Reinforced slab at North wall of arena number three approved. Stadia seating at south wall of arena number three approved. Rebar for rink slab in arena number one approved.