PRFS201700507
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Fire Inspection Final | Failed | 7/27/2017 (10:00 - 12:00) | 7/27/2017 | 07/27/2017 |
Corrections:
Didn’t call for rough-in
Comment Only
10/10/2017
Didn’t call for rough-in. Work appears to be covered. unable to gain access into several areas and lack of sprinkler coverage for coffee bar under stairs.
Advised contractor to schedule an inspection with both the sprinkler contractor and job supervisor present.
|
||||
Fire Inspection Final | Partial Pass | 8/2/2017 (7:00 - 8:00) | 8/2/2017 | 08/02/2017 |
Corrections:
Didn’t call for rough-in
Outstanding
07/27/2017
Didn’t call for rough-in. Work appears to be covered. unable to gain access into several areas and lack of sprinkler coverage for coffee bar under stairs.
Advised contractor to schedule an inspection with both the sprinkler contractor and job supervisor present.
|
||||
Fire Inspection Final | Not Ready | 10/6/2017 (12:30 - 2:30) | 10/6/2017 | 10/06/2017 |
Fire Inspection Final | Passed w/ Conditions | 10/10/2017 (8:00 - 10:00) | 10/10/2017 | 10/10/2017 |
Corrections:
Replace covered heads.
Comment Only
10/10/2017
Head covered with painters tape near the bar. Remove tape prior to Fire Marshal Final of Building Permit
|
||||
Fire Rough-in Inspection | VOID | 10/13/2017 |