PRFS201700768
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Fire Rough-in Inspection | Failed | 3/6/2017 (8:00 - 10:00) | 3/6/2017 | 03/06/2017 |
Unable to pass security checkpoint without being escorted by contractor. called contractor advised all future inspections shall someone on sit. | ||||
Fire Rough-in Inspection | Passed w/ Conditions | 3/7/2017 (8:00 - 10:00) | 3/7/2017 | 03/07/2017 |
Rough in a proof or 12th floor bathrooms only | ||||
Fire Rough-in Inspection | Partial Pass | 3/27/2017 (10:00 - 12:00) | 3/27/2017 | 03/27/2017 |
Rough in approved for 11th floor | ||||
Fire Rough-in Inspection | Partial Pass | 5/1/2017 (7:00 - 8:00) | 5/1/2017 | 05/01/2017 |
Rough in approved for 10th floor restrooms. | ||||
Fire Rough-in Inspection | Partial Pass | 5/22/2017 (8:00 - 10:00) | 5/22/2017 | 05/22/2017 |
Corrections:
Miscellaneous/Other
Comment Only
05/22/2017
Ok to cover 9th floor bathrooms. Advised to submit plan and time line for main relocate at new loading dock.
|
||||
Fire Rough-in Inspection | Partial Pass | 6/20/2017 (12:30 - 2:30) | 6/20/2017 | 06/20/2017 |
Corrections:
Miscellaneous/Other
Comment Only
06/20/2017
Rough in approved for 8th floor bathrooms.
|
||||
Fire Rough-in Inspection | Partial Pass | 7/5/2017 (Afternoon) | 7/5/2017 | 07/05/2017 |
Corrections:
Miscellaneous/Other
Comment Only
07/05/2017
Rough in of 13th floor bathrooms approved.
|
||||
Fire Rough-in Inspection | Partial Pass | 7/12/2017 (8:00 - 10:00) | 7/12/2017 | 07/12/2017 |
Corrections:
Miscellaneous/Other
Comment Only
07/12/2017
Ok to cover 7th floor bathrooms
|
||||
Fire Rough-in Inspection | Partial Pass | 8/10/2017 (10:00 - 12:00) | 8/10/2017 | 08/10/2017 |
6th floor ok to cover. | ||||
Fire Rough-in Inspection | Partial Pass | 8/23/2017 (8:00 - 10:00) | 8/23/2017 | 08/23/2017 |
Corrections:
Ceiling in place - rough-In could not be completed
Comment Only
08/23/2017
Lower level elevator lobby approved.
However, lower level bathrooms hard lid ceiling in place and rough in inspection couldn't be performed.
Advised general contractor and drywall contractor to ensure rough in inspections are completed and approved prior to covering in the future.
|
||||
Fire Rough-in Inspection | Passed | 9/1/2017 (10:00 - 12:00) | 9/1/2017 | 09/01/2017 |
Fire Rough-in Inspection | Partial Pass | 9/29/2017 (10:00 - 12:00) | 9/29/2017 | 09/29/2017 |
14th floor bathroom ok | ||||
Fire Rough-in Inspection | Partial Pass | 10/6/2017 (10:00 - 12:00) | 10/6/2017 | 10/06/2017 |
Corrections:
Miscellaneous/Other
Comment Only
10/06/2017
Partial Rough-In:
Approved for 4th floor restrooms.
|
||||
Fire Rough-in Inspection | Partial Pass | 10/20/2017 (10:00 - 12:00) | 10/20/2017 | 10/20/2017 |
Besement level elevator lobby corridor approved. | ||||
Fire Rough-in Inspection | Partial Pass | 10/27/2017 (8:00 - 10:00) | 10/27/2017 | 10/27/2017 |
Fire Rough-in Inspection | Partial Pass | 11/3/2017 (10:00 - 12:00) | 11/3/2017 | 11/03/2017 |
Fire Rough-in Inspection | Passed | 11/22/2017 (10:00 - 12:00) | 11/22/2017 | 11/22/2017 |
Corrections:
Miscellaneous/Other
Comment Only
11/22/2017
1st restrooms approved for rough in.
|
||||
Fire Inspection Final | Passed | 12/21/2017 (8:00 - 10:00) | 12/21/2017 | 12/21/2017 |