Permit Application Status

PRFS201702897


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRFS201702897
Fire Suppression System
Finaled
NORTH PAD DEVELOPMENT LLC
Other
Add on sprinklers based on new ceiling.
04/24/2017
04/27/2017
10/08/2020
10/12/2017

Locations

Permits

Permit Number: PRFS201702897

Fire Suppression System
Finaled
04/27/2017
10/08/2020

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Fire Rough-in Inspection Partial Pass 5/10/2017 (8:00 - 10:00) 5/10/2017 05/10/2017
4th and 5th floors
Corrections:


Miscellaneous/Other
Comment Only
05/10/2017
Ok to cover 4th and 5th floor common area hallway and kitchen area.

Fire Rough-in Inspection Partial Pass 5/18/2017 (10:00 - 12:00) 5/18/2017 05/18/2017
Corrections:


Miscellaneous/Other
Outstanding
05/18/2017

Miscellaneous/Other
Outstanding
05/18/2017

Miscellaneous/Other
Comment Only
05/18/2017
Ok cover 5th bathroom/s and leasing lounge area.

Fire Rough-in Inspection Partial Pass 6/7/2017 (10:00 - 12:00) 6/7/2017 06/08/2017
Corrections:


Miscellaneous/Other
Outstanding
06/08/2017
Ok to cover gridded ceiling in offices in the south side of the space on 4th floor. Ok to cover hard lid on north side 414 and hard lid in 400.

Fire Rough-in Inspection Passed 7/19/2017 (10:00 - 12:00) 7/19/2017 07/19/2017
Fire Inspection Final Passed 7/17/2017 (8:00 - 10:00) 7/17/2017 07/19/2017
Fire Inspection Final VOID 10/12/2017
Hydro Test End VOID 10/12/2017
Hydro Test Start VOID 10/12/2017