PRFS201702897
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Fire Rough-in Inspection | Partial Pass | 5/10/2017 (8:00 - 10:00) | 5/10/2017 | 05/10/2017 |
4th and 5th floors | ||||
Corrections:
Miscellaneous/Other
Comment Only
05/10/2017
Ok to cover 4th and 5th floor common area hallway and kitchen area.
|
||||
Fire Rough-in Inspection | Partial Pass | 5/18/2017 (10:00 - 12:00) | 5/18/2017 | 05/18/2017 |
Corrections:
Miscellaneous/Other
Outstanding
05/18/2017
|
||||
Miscellaneous/Other
Outstanding
05/18/2017
|
||||
Miscellaneous/Other
Comment Only
05/18/2017
Ok cover 5th bathroom/s and leasing lounge area.
|
||||
Fire Rough-in Inspection | Partial Pass | 6/7/2017 (10:00 - 12:00) | 6/7/2017 | 06/08/2017 |
Corrections:
Miscellaneous/Other
Outstanding
06/08/2017
Ok to cover gridded ceiling in offices in the south side of the space on 4th floor. Ok to cover hard lid on north side 414 and hard lid in 400.
|
||||
Fire Rough-in Inspection | Passed | 7/19/2017 (10:00 - 12:00) | 7/19/2017 | 07/19/2017 |
Fire Inspection Final | Passed | 7/17/2017 (8:00 - 10:00) | 7/17/2017 | 07/19/2017 |
Fire Inspection Final | VOID | 10/12/2017 | ||
Hydro Test End | VOID | 10/12/2017 | ||
Hydro Test Start | VOID | 10/12/2017 |