PRFS201707604
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Hydro Test Start | Pending | |||
| Hydro Test End | Pending | |||
| Fire Rough-in Inspection | Pending | |||
| Fire Inspection Final | Pending | |||
|
Corrections:
Miscellaneous/Other
Outstanding
11/15/2017
Add/relocate heads under tin roof that obstructs widow system in water park.
Relocate fire hose valve or towel shed. Towel shed in water park obstructs fire hose valve.
Remove tape off of heads as needed on 1st and 2nd floors.
|
||||
| Fire Rough-in Inspection | Partial Pass | 9/7/2017 (10:00 - 12:00) | 9/7/2017 | 09/07/2017 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/07/2017
Partial rough in approved for:
Lower level conference rooms soffit areas.
Hard lid soffits 2nd floor, by bathrooms.
Hard lid soffits on 1st floor by water park entrance area
Under new convenience stairs from 1st to 2nd floor.
Discussed and approved location of fire hose valves by lower level horizontal exit.
|
||||
| Fire Rough-in Inspection | VOID | 9/14/2017 (8:00 - 10:00) | 9/14/2017 | 09/14/2017 |
| Fire Rough-in Inspection | Partial Pass | 9/22/2017 (8:00 - 10:00) | 9/22/2017 | 09/22/2017 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/22/2017
Partial rough in approved for all hard lids and ACT lids in lower level. Several exposed ceilings in lower level still need protection.
Rough in approved for main level near/around arcade ticket area.
|
||||
| Fire Rough-in Inspection | Partial Pass | 10/2/2017 (8:00 - 10:00) | 10/2/2017 | 10/02/2017 |
|
Corrections:
Miscellaneous/Other
Comment Only
10/02/2017
Candy cove area approved for rough-in of hard lid area.
Discussed water curtain protection for new large windows separating water park from hotel areas on the east end.
Advised contractor to ensure sprinkler protection (heads) are at/near glass and to work with a fire protection engineer to develop fire protection plan and submit plan for review.
|
||||
| Fire Rough-in Inspection | Partial Pass | 10/6/2017 (8:00 - 10:00) | 10/6/2017 | 10/06/2017 |
|
Corrections:
Miscellaneous/Other
Comment Only
10/06/2017
Partial rough in:
Approved for water curtain of windows on east end
|
||||
| Fire Rough-in Inspection | Partial Pass | 10/18/2017 (8:00 - 10:00) | 10/18/2017 | 10/18/2017 |
| Ok to cover 1st floor tiled area. Add one to Ben and jerrys. Add one on second floor by roof peak. | ||||
| Progress Inspection | Partial Pass | 10/23/2017 (12:30 - 2:30) | 10/23/2017 | 10/23/2017 |
|
Corrections:
Miscellaneous/Other
Comment Only
10/23/2017
Rough-in approved of tree house play area.
|
||||
| Progress Inspection | Failed | 11/1/2017 (12:30 - 2:30) | 11/1/2017 (PM) | 11/01/2017 |
|
Corrections:
Outstanding
11/01/2017
Add sprinkler protection in lower level mechanical rooms as needed.
Add sprinkler protection under decorative roofs as needed on 1st and 2nd floors.
Found several heads covered with tape/foil on 1st and 2nd floor.
|
||||
| Fire Inspection Final | Partial Pass | 11/02/2017 | ||
| Progress Inspection | Failed | 11/2/2017 | 11/02/2017 | |
|
Corrections:
Miscellaneous/Other
Outstanding
11/02/2017
Advised sprinkler protection for 2nd floor assembly areas cannot be on water park sprinkler zone. Contractor to resubmit plan and clacs to repipe area to separate zone.
|
||||
| Fire Inspection Final | Partial Pass | 11/13/2017 (10:00 - 12:00) | 11/13/2017 | 11/14/2017 |
|
Corrections:
Miscellaneous/Other
Comment Only
11/02/2017
Partial final approved for lower level for temp occupancy of hotel staff. Still need sprinkler protection of mechanical closets in lower level.
|
||||
|
Miscellaneous/Other
Outstanding
11/14/2017
Partial final approved for hotel pending a follow up inspectiono of the items noted below, prior to Building Final:
-Missing and or painted sprinkler head discussion plates in the 01 rooms
-Several heads and or escutcheon plate covered with tape on first and second floor.
Still need to final inspect the water park.
|
||||
| Fire Inspection Final | Failed | 11/15/2017 | ||
|
Corrections:
Miscellaneous/Other
Carried Forward
11/15/2017
Add/relocate heads under tin roof that obstructs widow system in water park.
Relocate fire hose valve or towel shed. Towel shed in water park obstructs fire hose valve.
Remove tape off of heads as needed on 1st and 2nd floors.
|
||||