PRFS201707945
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Progress Inspection | Passed | 10/16/2017 | ||
Corrections:
Miscellaneous/Other
Comment Only
10/16/2017
Inspection of progress of work. 4th floor appears close to being ready for rough-in inspection.
Advised contractor to call for rough-in inspection as soon as work is ready and to install temp standpipe with FDC.
|
||||
Fire Rough-in Inspection | Partial Pass | 10/27/2017 | ||
Corrections:
Miscellaneous/Other
Comment Only
10/27/2017
Ok to cover 3rd floor rooms only. End caps needed in room 300 and 301.
|
||||
Fire Rough-in Inspection | Partial Pass | 10/27/2017 | ||
Corrections:
Comment Only
10/27/2017
4th floor rooms and corridor ok to cover. Temp Standpipe approved.
|
||||
Fire Rough-in Inspection | Failed | 11/8/2017 (10:00 - 12:00) | 11/8/2017 | 11/08/2017 |
Corrections:
Miscellaneous/Other
Outstanding
11/08/2017
City approved plans do not match installation. Advised contractor to resubmit plans and calcs.
|
||||
Fire Rough-in Inspection | Partial Pass | 11/9/2017 (8:00 - 10:00) | 11/9/2017 | 11/09/2017 |
Corrections:
Miscellaneous/Other
Resolved
11/09/2017
City approved plans do not match installation. Advised contractor to resubmit plans and calcs.
|
||||
Miscellaneous/Other
Comment Only
11/09/2017
Rough in approved for floors 2 and 1. Sprinkler Contractor added pipe as needed per plan and will submit final as built drawing upon completion of project.
|
||||
Fire Rough-in Inspection | Failed | 11/14/2017 (10:00 - 12:00) | 11/14/2017 | 11/14/2017 |
Corrections:
Heads obstructed
Carried Forward
11/14/2017
Heads obstructed. Soffits create obstructions to sidewall sprinkler heads and need to be protected as such.
|
||||
Fire Rough-in Inspection | Partial Pass | 11/16/2017 (10:00 - 12:00) | 11/16/2017 | 11/16/2017 |
Corrections:
Heads obstructed
Resolved
11/16/2017
Heads obstructed. Soffits create obstructions to sidewall sprinkler heads and need to be protected as such.
|
||||
Fire Rough-in Inspection | Passed | 11/29/2017 (8:00 - 10:00) | 11/29/2017 | 12/01/2017 |
Fire Rough-in Inspection | Partial Pass | 12/11/2017 (8:00 - 10:00) | 12/11/2017 | 12/12/2017 |
Fire Rough-in Inspection | Partial Pass | 2/16/2018 (8:00 - 10:00) | 2/16/2018 | 02/16/2018 |
Corrections:
Miscellaneous/Other
Comment Only
02/16/2018
Trash chutes only.
|
||||
Hydro Test Start | Passed | 2/20/2018 (10:00 - 12:00) | 2/20/2018 | 02/20/2018 |
Hydro Test End | Passed | 2/20/2018 (12:30 - 2:30) | 2/20/2018 | 02/20/2018 |
Fire Inspection Final | Partial Pass | 2/20/2018 (12:30 - 2:30) | 2/20/2018 | 02/20/2018 |
Corrections:
Miscellaneous/Other
Outstanding
02/20/2018
Partial final approved. Test of flows and tampers approved.
Need to raise sprinkler heads in Stair A and change out FDC to flush mount FDC style due to building obstructions.
|
||||
Fire Inspection Final | Passed | 3/14/2018 (12:30 - 2:30) | 3/14/2018 | 03/14/2018 |