PRFS201709738
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Fire Rough-in Inspection | Failed | 10/31/2017 (8:00 - 10:00) | 10/31/2017 (AM) | 11/01/2017 |
Routed 2 revised plans to K.Kaiser. Moe\, Amanda 11/09/2017 2:18 PM | ||||
Corrections:
Miscellaneous/Other
Outstanding
11/01/2017
Provide plans that correctly show sprinkler pipe and recalculate remote area/s as needed.
NO further inspection will be performed until updated plans and calculations are received.
|
||||
Fire Rough-in Inspection | Partial Pass | 11/13/2017 (7:00 - 8:00) | 11/13/2017 | 11/13/2017 |
Corrections:
Miscellaneous/Other
Comment Only
11/13/2017
Partial pass of several areas as noted on job site inspection sheets per room/area
|
||||
Fire Rough-in Inspection | Partial Pass | 11/17/2017 (8:00 - 10:00) | 11/17/2017 | 11/17/2017 |
Corrections:
Miscellaneous/Other
Comment Only
11/17/2017
Partial rough in approved in areas as noted on job site inspection sheets.
|
||||
Fire Rough-in Inspection | Failed | 12/05/2017 | ||
Corrections:
Miscellaneous/Other
Outstanding
12/05/2017
Add heads in storage room by theater 12 exit.
|
||||
Fire Rough-in Inspection | Partial Pass | 12/22/2017 (10:00 - 12:00) | 12/22/2017 | 12/22/2017 |
Fire Inspection Final | Not Ready | 3/26/2018 (7:00 - 8:00) | 3/26/2018 | 03/26/2018 |
Fire Rough-in Inspection | Passed | 04/26/2018 | ||
Fire Inspection Final | Passed | 04/26/2018 |