Permit Application Status

PRFS201802252


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRFS201802252
Fire Suppression System
Finaled
FRIENDLY PALM HOSPITALITY LLC
New
New standpipe and sprinkler system for New Holiday Express building
03/20/2018
04/18/2018
02/03/2020
08/07/2019

Locations

Permits

Permit Number: PRFS201802252

Fire Suppression System
Finaled
04/18/2018
02/03/2020

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Fire Rough-in Inspection Partial Pass 8/16/2018 (8:00 - 10:00) 8/16/2018 08/16/2018
Corrections:


Miscellaneous/Other
Comment Only
08/16/2018
OK to cover guestrooms and core doors on floors 2, 3 & 4. Also noted no check valve installed for the fire department connection however that will be corrected prior to first floor rough in, per contractor.

Fire Rough-in Inspection Partial Pass 11/30/2018 (10:00 - 12:00) 11/30/2018 (AM) 11/30/2018
Corrections:


Miscellaneous/Other
Comment Only
11/30/2018
Ok to cover 5th floor rooms and corridors. Rough in still needed for 1st floor, stairwells, and linen chute,.

Fire Rough-in Inspection Partial Pass 4/8/2019 (10:00 - 12:00) 4/8/2019 (AM) 04/08/2019
Corrections:


Miscellaneous/Other
Comment Only
04/08/2019
Partial Rough In approved for 1st floor hard lid areas only. Still need to verify sprinkler protection and connections elsewhere on 1st floor. Hydro tests and final inspection needed on all other floors.

Hydro Test Start Passed 6/4/2019 (8:00 - 10:00) 6/4/2019 (AM) 06/04/2019
Hydro Test End Passed 6/4/2019 (12:30 - 2:30) 6/4/2019 (PM) 06/04/2019
Fire Rough-in Inspection Passed 06/27/2019
Acceptance Test Inspection Passed 06/27/2019
Corrections:


Miscellaneous/Other
Comment Only
06/27/2019
Test of water flow and tamper alarms. Contractor/Designer to provide verification report of system design prior to final inspection.

Fire Inspection Final Not Ready 6/27/2019 (8:00 - 10:00) 6/27/2019 (AM) 06/27/2019
Fire Inspection Final Passed 8/1/2019 (8:00 - 10:00) 8/1/2019 (AM) 08/07/2019