PRFS201802252
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Fire Rough-in Inspection | Partial Pass | 8/16/2018 (8:00 - 10:00) | 8/16/2018 | 08/16/2018 |
Corrections:
Miscellaneous/Other
Comment Only
08/16/2018
OK to cover guestrooms and core doors on floors 2, 3 & 4.
Also noted no check valve installed for the fire department connection however that will be corrected prior to first floor rough in, per contractor.
|
||||
Fire Rough-in Inspection | Partial Pass | 11/30/2018 (10:00 - 12:00) | 11/30/2018 (AM) | 11/30/2018 |
Corrections:
Miscellaneous/Other
Comment Only
11/30/2018
Ok to cover 5th floor rooms and corridors.
Rough in still needed for 1st floor, stairwells, and linen chute,.
|
||||
Fire Rough-in Inspection | Partial Pass | 4/8/2019 (10:00 - 12:00) | 4/8/2019 (AM) | 04/08/2019 |
Corrections:
Miscellaneous/Other
Comment Only
04/08/2019
Partial Rough In approved for 1st floor hard lid areas only.
Still need to verify sprinkler protection and connections elsewhere on 1st floor.
Hydro tests and final inspection needed on all other floors.
|
||||
Hydro Test Start | Passed | 6/4/2019 (8:00 - 10:00) | 6/4/2019 (AM) | 06/04/2019 |
Hydro Test End | Passed | 6/4/2019 (12:30 - 2:30) | 6/4/2019 (PM) | 06/04/2019 |
Fire Rough-in Inspection | Passed | 06/27/2019 | ||
Acceptance Test Inspection | Passed | 06/27/2019 | ||
Corrections:
Miscellaneous/Other
Comment Only
06/27/2019
Test of water flow and tamper alarms. Contractor/Designer to provide verification report of system design prior to final inspection.
|
||||
Fire Inspection Final | Not Ready | 6/27/2019 (8:00 - 10:00) | 6/27/2019 (AM) | 06/27/2019 |
Fire Inspection Final | Passed | 8/1/2019 (8:00 - 10:00) | 8/1/2019 (AM) | 08/07/2019 |