PRFS201803745


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRFS201803745
Fire Suppression System
Finaled
MINNESOTA CENTER JV LLC
Other
Remodeling the existing wet system on floors 4, 5, and partially the 6th
04/26/2018
05/02/2018
01/13/2019
06/22/2018

Locations

Permits

Permit Number: PRFS201803745

Fire Suppression System
Finaled
05/02/2018
01/13/2019

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Fire Inspection Final Pending
Fire Rough-in Inspection Partial Pass 5/9/2018 (8:00 - 10:00) 5/9/2018 05/09/2018
5th floor hard lids only.
Fire Rough-in Inspection Partial Pass 5/22/2018 (12:30 - 2:30) 5/22/2018 05/22/2018
4th floor hard lids only. 5/18/18 inspection cancelled by contractor. vcarlson 05/17/2018 9:41 AM
Fire Rough-in Inspection Partial Pass 6/5/2018 (8:00 - 10:00) 6/5/2018 06/05/2018
Corrections:


Miscellaneous/Other
Comment Only
06/05/2018
Ok to cover inner offices on fourth floor. Ok to cover hard lids on 6th floor.

Fire Rough-in Inspection Partial Pass 6/7/2018 (8:00 - 10:00) 6/7/2018 06/07/2018
Corrections:


Miscellaneous/Other
Comment Only
06/07/2018
Ok to cover grid on 4th and 5th floor.

Fire Rough-in Inspection Partial Pass 6/21/2018 (10:00 - 12:00) 6/21/2018 06/21/2018
Corrections:


Miscellaneous/Other
Comment Only
06/21/2018
Ok to cover 6th floor with exception of small office and near mechanical room.

Hydro Test Start Passed 6/21/2018 (10:00 - 12:00) 6/21/2018 06/22/2018
Corrections:


Miscellaneous/Other
Comment Only
06/22/2018
5th and 6th floor ok. 4th floor has a bad isolation control valve. Valve is getting replaced.

Hydro Test End Passed 6/21/2018 (12:30 - 2:30) 6/21/2018 06/22/2018
Corrections:


Miscellaneous/Other
Comment Only
06/22/2018
4th floor to be tested once valve has been replaced.

Fire Rough-in Inspection Passed 06/22/2018
Corrections:


Miscellaneous/Other
Comment Only
06/22/2018
Ok to cover all.

Fire Inspection Final Not Ready 6/22/2018 (8:00 - 10:00) 6/22/2018 06/22/2018
Corrections:


Miscellaneous/Other
Comment Only
06/22/2018
Rough in complete. Will close permit when ceiling in and plated out during fire marshal final.

Hydro Test Start Passed 7/17/2018 (8:00 - 10:00) 7/17/2018 07/17/2018
Hydro Test End Passed 7/17/2018 (10:00 - 12:00) 7/17/2018 07/17/2018