PRFS201803745
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Fire Inspection Final | Pending | |||
Fire Rough-in Inspection | Partial Pass | 5/9/2018 (8:00 - 10:00) | 5/9/2018 | 05/09/2018 |
5th floor hard lids only. | ||||
Fire Rough-in Inspection | Partial Pass | 5/22/2018 (12:30 - 2:30) | 5/22/2018 | 05/22/2018 |
4th floor hard lids only. 5/18/18 inspection cancelled by contractor. vcarlson 05/17/2018 9:41 AM | ||||
Fire Rough-in Inspection | Partial Pass | 6/5/2018 (8:00 - 10:00) | 6/5/2018 | 06/05/2018 |
Corrections:
Miscellaneous/Other
Comment Only
06/05/2018
Ok to cover inner offices on fourth floor. Ok to cover hard lids on 6th floor.
|
||||
Fire Rough-in Inspection | Partial Pass | 6/7/2018 (8:00 - 10:00) | 6/7/2018 | 06/07/2018 |
Corrections:
Miscellaneous/Other
Comment Only
06/07/2018
Ok to cover grid on 4th and 5th floor.
|
||||
Fire Rough-in Inspection | Partial Pass | 6/21/2018 (10:00 - 12:00) | 6/21/2018 | 06/21/2018 |
Corrections:
Miscellaneous/Other
Comment Only
06/21/2018
Ok to cover 6th floor with exception of small office and near mechanical room.
|
||||
Hydro Test Start | Passed | 6/21/2018 (10:00 - 12:00) | 6/21/2018 | 06/22/2018 |
Corrections:
Miscellaneous/Other
Comment Only
06/22/2018
5th and 6th floor ok. 4th floor has a bad isolation control valve. Valve is getting replaced.
|
||||
Hydro Test End | Passed | 6/21/2018 (12:30 - 2:30) | 6/21/2018 | 06/22/2018 |
Corrections:
Miscellaneous/Other
Comment Only
06/22/2018
4th floor to be tested once valve has been replaced.
|
||||
Fire Rough-in Inspection | Passed | 06/22/2018 | ||
Corrections:
Miscellaneous/Other
Comment Only
06/22/2018
Ok to cover all.
|
||||
Fire Inspection Final | Not Ready | 6/22/2018 (8:00 - 10:00) | 6/22/2018 | 06/22/2018 |
Corrections:
Miscellaneous/Other
Comment Only
06/22/2018
Rough in complete. Will close permit when ceiling in and plated out during fire marshal final.
|
||||
Hydro Test Start | Passed | 7/17/2018 (8:00 - 10:00) | 7/17/2018 | 07/17/2018 |
Hydro Test End | Passed | 7/17/2018 (10:00 - 12:00) | 7/17/2018 | 07/17/2018 |