PRFS201807186
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Fire Rough-in Inspection | Failed | 7/18/2018 (8:00 - 10:00) | 7/18/2018 (AM) | 07/18/2018 |
Fire Rough-in Inspection | Partial Pass | 7/24/2018 (8:00 - 10:00) | 7/24/2018 | 07/24/2018 |
Corrections:
Miscellaneous/Other
Comment Only
07/24/2018
Ok to cover ride hard lid area
|
||||
Fire Rough-in Inspection | Partial Pass | 8/8/2018 (8:00 - 10:00) | 8/8/2018 | 08/08/2018 |
OK to cover the hallway to the theatre; OK to cover backside of theatre; OK to cover main entrance to space (*Josh will add a head to the far corner of the triangle if needed, all heads existing) | ||||
Fire Rough-in Inspection | Passed | 9/10/2018 (12:30 - 2:30) | 9/10/2018 | 09/10/2018 |
Fire Inspection Final | Passed | 11/01/2018 |