Permit Application Status

PRFS201809174


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRFS201809174
Fire Suppression System
Finaled
WHIRLY SOUTH PROPERTIES LLC
Other
Install (one) wet fire sprinkler system for a four story hotel. System will have (2) standpipe risers and will be zoned by floor. 691 heads.
08/14/2018
11/20/2018
06/01/2020
12/04/2019

Locations

Permits

Permit Number: PRFS201809174

Fire Suppression System
Finaled
11/20/2018
06/01/2020

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Fire Rough-in Inspection Partial Pass 3/12/2019 (8:00 - 10:00) 3/12/2019 (AM) 03/12/2019
Corrections:


Miscellaneous/Other
Comment Only
03/12/2019
rough-in approved for 2nd and 3rd floor approved.

Fire Rough-in Inspection Partial Pass 06/25/2019
Corrections:


Miscellaneous/Other
Comment Only
06/25/2019
Rough in approved for 4th floor rooms and 3rd floors rooms re-pipe due to new separation curtains.

Fire Rough-in Inspection Partial Pass 9/6/2019 (12:30 - 2:30) 9/6/2019 (PM) 09/06/2019
Corrections:


Miscellaneous/Other
Comment Only
09/06/2019
Partial rough in only. Approved for 1st floor guest rooms only.

Fire Rough-in Inspection Partial Pass 9/26/2019 (10:00 - 12:00) 9/26/2019 (AM) 09/26/2019
Corrections:


Miscellaneous/Other
Comment Only
09/26/2019
Ok to cover hard lids only on true side. Mech room to be changed to metal pipe. Head added for garage door. Some heads to be adjusted in act. Jerry has plans that were marked up to reflect inspection.

Fire Rough-in Inspection Partial Pass 10/31/2019 (8:00 - 10:00) 10/31/2019 (AM) 10/31/2019
Corrections:


Miscellaneous/Other
Comment Only
10/31/2019
Rough in approved for 2,3,4 corridors.

Fire Rough-in Inspection Partial Pass 11/13/2019 (8:00 - 10:00) 11/13/2019 (AM) 11/13/2019
Corrections:


Inadequate coverage
Carried Forward
11/13/2019
Inadequate coverage. Need to add sprinkler protection in storage room adjacent to elevators on 1st floor.

Hydro Test Start Passed 11/15/2019 (12:30 - 2:30) 11/15/2019 (PM) 11/15/2019
Hydro Test End Passed 11/15/2019 (2:30 - 3:30) 11/15/2019 (PM) 11/15/2019
Fire Inspection Final Not Ready 11/25/2019 (12:30 - 2:30) 11/25/2019 (PM) 11/26/2019
Fire Inspection Final Passed 12/3/2019 (12:30 - 2:30) 12/3/2019 (PM) 12/04/2019
Acceptance Test Inspection Passed 12/04/2019