PRFS201810301
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Fire Rough-in Inspection | Pending | |||
Fire Rough-in Inspection | Partial Pass | 9/18/2018 (12:30 - 2:30) | 9/18/2018 | 09/18/2018 |
Corrections:
Miscellaneous/Other
Comment Only
09/18/2018
OK to cover lower level bathrooms
|
||||
Fire Rough-in Inspection | Partial Pass | 10/11/2018 (10:00 - 12:00) | 10/11/2018 | 10/11/2018 |
Fire Rough-in Inspection | Partial Pass | 10/12/2018 (12:30 - 2:30) | 10/12/2018 | 10/22/2018 |
Fire Inspection Final | Passed | 10/25/2018 (8:00 - 10:00) | 10/25/2018 | 10/25/2018 |
Fire Rough-in Inspection | Failed | 10/29/2018 (7:00 - 8:00) | 10/29/2018 (AM) | 10/29/2018 |