PRFS201814496
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Fire Inspection Final | Pending | |||
Hydro Test Start | Failed | 1/25/2019 (10:00 - 12:00) | 1/25/2019 (AM) | 01/28/2019 |
Corrections:
Miscellaneous/Other
Comment Only
01/28/2019
Bad pump. Unable to pump up system.
|
||||
Hydro Test End | Failed | 1/25/2019 (10:00 - 12:00) | 1/25/2019 (AM) | 01/28/2019 |
Fire Rough-in Inspection | Not Ready | 1/25/2019 (12:30 - 2:30) | 1/25/2019 (PM) | 01/28/2019 |
Hydro Test End | Passed | 2/5/2019 (10:00 - 12:00) | 2/5/2019 (AM) | 02/05/2019 |
Hydro Test Start | Passed | 2/5/2019 (8:00 - 10:00) | 2/5/2019 (AM) | 02/05/2019 |
Corrections:
Miscellaneous/Other
Comment Only
02/05/2019
Replace two heads noted that leaked.
|
||||
Fire Rough-in Inspection | Passed | 2/5/2019 | 08/15/2019 |