PRFS201814987
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Fire Inspection Final | Pending | 7/15/2020 (12:30 - 2:30) | ||
Contractor called and cancelled inspection bgillespie 07/14/2020 12:21 PM | ||||
Hydro Test Start | Not Ready | 7/22/2020 (8:00 - 10:00) | 7/22/2020 (AM) | 07/23/2020 |
Contractor called and cancelled inspection bgillespie 07/14/2020 12:21 PM | ||||
Hydro Test End | VOID | 7/22/2020 (10:00 - 12:00) | 7/22/2020 (AM) | 07/23/2020 |
Contractor called and cancelled inspection bgillespie 07/14/2020 12:21 PM | ||||
Hydro Test Start | Passed | 08/11/2020 | ||
Fire Rough-in Inspection | Passed | 8/11/2020 (12:30 - 2:30) | 8/11/2020 (PM) | 08/11/2020 |
Hydro Test End | Passed | 08/11/2020 |