PRFS201815286
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Fire Rough-in Inspection | Partial Pass | 5/21/2019 (8:00 - 10:00) | 5/21/2019 (AM) | 05/21/2019 |
Corrections:
Miscellaneous/Other
Comment Only
05/21/2019
Partial rough in. Rooms on floors 2 and 3 approved. Still need to inspect corridors and other common areas on these floors.
|
||||
Fire Rough-in Inspection | Failed | 7/12/2019 (10:00 - 12:00) | 7/12/2019 (AM) | 07/12/2019 |
Corrections:
Miscellaneous/Other
Carried Forward
07/12/2019
Not approved. 5th and 4th floors piping appears not be installed per revised plans dated 04/2019.
Contractor and designer must be on site to review further.
|
||||
Fire Rough-in Inspection | Partial Pass | 7/23/2019 (8:00 - 10:00) | 7/23/2019 (AM) | 07/23/2019 |
Corrections:
Miscellaneous/Other
Resolved
07/23/2019
Not approved. 5th and 4th floors piping appears not be installed per revised plans dated 04/2019.
Contractor and designer must be on site to review further.
|
||||
Miscellaneous/Other
Comment Only
07/23/2019
Partial rough in approved for guest rooms on floors 5 and 4
|
||||
Fire Rough-in Inspection | Partial Pass | 11/12/2019 (8:00 - 10:00) | 11/12/2019 (AM) | 11/12/2019 |
Corrections:
Miscellaneous/Other
Comment Only
11/12/2019
Rough in approved for hard lids on 1st floor of east wing.
|
||||
Fire Rough-in Inspection | Partial Pass | 12/2/2019 (8:00 - 10:00) | 12/2/2019 (AM) | 12/03/2019 |
Hydro Test Start | Partial Pass | 12/17/2019 (8:00 - 10:00) | 12/17/2019 (AM) | 12/17/2019 |
Corrections:
Miscellaneous/Other
Comment Only
12/17/2019
Hydro of floors 2-5.
|
||||
Hydro Test End | Partial Pass | 12/17/2019 (10:00 - 12:00) | 12/17/2019 (AM) | 12/17/2019 |
Corrections:
Miscellaneous/Other
Comment Only
12/17/2019
Hydro of floors 2-5 approved.
|
||||
Hydro Test Start | Passed | 1/23/2020 (7:00 - 8:00) | 1/23/2020 (AM) | 01/23/2020 |
Hydro Test End | Passed | 1/23/2020 (7:00 - 8:00) | 1/23/2020 (AM) | 01/23/2020 |
Acceptance Test Inspection | Passed | 01/23/2020 | ||
Fire Rough-in Inspection | Passed | 01/23/2020 | ||
Fire Inspection Final | Partial Pass | 01/23/2020 | ||
Corrections:
Inadequate sprinkler coverage.
Outstanding
01/23/2020
Inadequate sprinkler coverage. Need to add head in 1st floor electrical room as discussed on site.
|
||||
Fire Inspection Final | Passed w/ Conditions | 01/24/2020 | ||
Corrections:
Inadequate sprinkler coverage.
Comment Only
01/24/2020
Inadequate sprinkler coverage. Need to add head in 1st floor electrical room as discussed on site. Contractor will be adding asap. kkaiser 01/24/2020 2:05 PM
|