Permit Application Status

PRFS201815286


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRFS201815286
Fire Suppression System
Finaled
CERES DEVELOPMENT LLC
Alteration/Repair/Replace
Install new wet fire sprinkler system and standpipe for Cambria Suites.
12/17/2018
12/31/2018
07/22/2020
01/24/2020

Locations

Permits

Permit Number: PRFS201815286

Fire Suppression System
Finaled
12/31/2018
07/22/2020

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Fire Rough-in Inspection Partial Pass 5/21/2019 (8:00 - 10:00) 5/21/2019 (AM) 05/21/2019
Corrections:


Miscellaneous/Other
Comment Only
05/21/2019
Partial rough in. Rooms on floors 2 and 3 approved. Still need to inspect corridors and other common areas on these floors.

Fire Rough-in Inspection Failed 7/12/2019 (10:00 - 12:00) 7/12/2019 (AM) 07/12/2019
Corrections:


Miscellaneous/Other
Carried Forward
07/12/2019
Not approved. 5th and 4th floors piping appears not be installed per revised plans dated 04/2019. Contractor and designer must be on site to review further.

Fire Rough-in Inspection Partial Pass 7/23/2019 (8:00 - 10:00) 7/23/2019 (AM) 07/23/2019
Corrections:


Miscellaneous/Other
Resolved
07/23/2019
Not approved. 5th and 4th floors piping appears not be installed per revised plans dated 04/2019. Contractor and designer must be on site to review further.

Miscellaneous/Other
Comment Only
07/23/2019
Partial rough in approved for guest rooms on floors 5 and 4

Fire Rough-in Inspection Partial Pass 11/12/2019 (8:00 - 10:00) 11/12/2019 (AM) 11/12/2019
Corrections:


Miscellaneous/Other
Comment Only
11/12/2019
Rough in approved for hard lids on 1st floor of east wing.

Fire Rough-in Inspection Partial Pass 12/2/2019 (8:00 - 10:00) 12/2/2019 (AM) 12/03/2019
Hydro Test Start Partial Pass 12/17/2019 (8:00 - 10:00) 12/17/2019 (AM) 12/17/2019
Corrections:


Miscellaneous/Other
Comment Only
12/17/2019
Hydro of floors 2-5.

Hydro Test End Partial Pass 12/17/2019 (10:00 - 12:00) 12/17/2019 (AM) 12/17/2019
Corrections:


Miscellaneous/Other
Comment Only
12/17/2019
Hydro of floors 2-5 approved.

Hydro Test Start Passed 1/23/2020 (7:00 - 8:00) 1/23/2020 (AM) 01/23/2020
Hydro Test End Passed 1/23/2020 (7:00 - 8:00) 1/23/2020 (AM) 01/23/2020
Acceptance Test Inspection Passed 01/23/2020
Fire Rough-in Inspection Passed 01/23/2020
Fire Inspection Final Partial Pass 01/23/2020
Corrections:


Inadequate sprinkler coverage.
Outstanding
01/23/2020
Inadequate sprinkler coverage. Need to add head in 1st floor electrical room as discussed on site.

Fire Inspection Final Passed w/ Conditions 01/24/2020
Corrections:


Inadequate sprinkler coverage.
Comment Only
01/24/2020
Inadequate sprinkler coverage. Need to add head in 1st floor electrical room as discussed on site. Contractor will be adding asap. kkaiser 01/24/2020 2:05 PM