PRFS201903406
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Fire Rough-in Inspection | Partial Pass | 1/6/2020 (12:30 - 2:30) | 08/27/2019 | |
Corrections:
Miscellaneous/Other
Comment Only
08/27/2019
Partial rough in of standpipe, bulk pipe on 1st floor and rough in of heads in the southwest stairwell, floors 3-6 approved.
|
||||
Fire Rough-in Inspection | Partial Pass | 9/5/2019 (8:00 - 10:00) | 9/5/2019 (AM) | 09/05/2019 |
Corrections:
Miscellaneous/Other
Comment Only
09/05/2019
Partial Rough In:
Approved for South West floors 5 and 6 up to units 503 and 603.
|
||||
Fire Rough-in Inspection | Partial Pass | 9/12/2019 (8:00 - 10:00) | 9/12/2019 (AM) | 09/12/2019 |
Corrections:
Miscellaneous/Other
Comment Only
09/12/2019
partial rough in. SW building floors 3-4 approved up to the x03 units.
|
||||
Fire Rough-in Inspection | Partial Pass | 9/13/2019 (7:00 - 8:00) | 9/13/2019 (AM) | 09/13/2019 |
Corrections:
Miscellaneous/Other
Comment Only
09/13/2019
Partial rough. 2nd floor, SW building units up to 203.
Contractor shall provide updated drawings and calcs. for 2nd floor SW.
|
||||
Fire Rough-in Inspection | Partial Pass | 9/16/2019 (8:00 - 10:00) | 9/16/2019 (AM) | 09/16/2019 |
Corrections:
Miscellaneous/Other
Comment Only
09/16/2019
Partial rough in. Northwest 6 and 5 floors approved.
|
||||
Fire Rough-in Inspection | Partial Pass | 9/17/2019 (8:00 - 10:00) | 9/17/2019 (AM) | 09/18/2019 |
Corrections:
Miscellaneous/Other
Comment Only
09/18/2019
Partial rough in. Approved for 4th floor of NW building.
|
||||
Fire Rough-in Inspection | Partial Pass | 9/18/2019 (8:00 - 10:00) | 9/18/2019 (AM) | 09/18/2019 |
Corrections:
Miscellaneous/Other
Comment Only
09/18/2019
Partial rough in approved OK to cover third floor north west building.
|
||||
Fire Rough-in Inspection | Partial Pass | 9/19/2019 (8:00 - 10:00) | 9/19/2019 (AM) | 09/25/2019 |
Fire Rough-in Inspection | Partial Pass | 10/15/2019 (7:00 - 8:00) | 10/15/2019 (AM) | 10/15/2019 |
Corrections:
Miscellaneous/Other
Comment Only
10/15/2019
Partial rough in approved for 1st northwest units and 1st floor of townhouse units.
|
||||
Fire Rough-in Inspection | Partial Pass | 11/5/2019 (8:00 - 10:00) | 11/5/2019 (AM) | 11/05/2019 |
Corrections:
Miscellaneous/Other
Comment Only
11/05/2019
Partial rough in. Approved for 1st floor fitness room and related areas.
|
||||
Fire Rough-in Inspection | Partial Pass | 11/18/2019 (8:00 - 10:00) | 11/18/2019 (AM) | 11/19/2019 |
Corrections:
Miscellaneous/Other
Comment Only
11/19/2019
6th floor and 5th floor southwest building.
|
||||
Fire Rough-in Inspection | Partial Pass | 11/19/2019 (8:00 - 10:00) | 11/19/2019 (AM) | 11/19/2019 |
Fire Rough-in Inspection | Partial Pass | 11/20/2019 (8:00 - 10:00) | 11/20/2019 (AM) | 11/20/2019 |
Corrections:
Miscellaneous/Other
Comment Only
11/20/2019
Rough in approved for 3rd and 2nd floors of southwest building.
|
||||
Fire Rough-in Inspection | Partial Pass | 11/21/2019 (8:00 - 10:00) | 11/21/2019 (AM) | 11/21/2019 |
Corrections:
Miscellaneous/Other
Comment Only
11/21/2019
Partial rough in. Approved for 1st floor of southwest building.
|
||||
Fire Rough-in Inspection | Partial Pass | 12/23/2019 (10:00 - 12:00) | 12/23/2019 (AM) | 12/24/2019 |
Corrections:
Miscellaneous/Other
Comment Only
12/24/2019
Rough in of east building, floors 4-6 approved.
|
||||
Fire Rough-in Inspection | Partial Pass | 1/6/2020 (12:30 - 2:30) | 1/6/2020 (PM) | 01/07/2020 |
Corrections:
Miscellaneous/Other
Comment Only
01/07/2020
NW Trash chute protection approved.
Need to add flow switch for the dedicated trash chutes’ fire protection.
|
||||
Fire Rough-in Inspection | Partial Pass | 1/23/2020 (10:00 - 12:00) | 1/23/2020 (AM) | 01/23/2020 |
Corrections:
Miscellaneous/Other
Comment Only
01/23/2020
Rough in approved for southeast building floors 2 and 3.
|
||||
Fire Rough-in Inspection | Partial Pass | 2/7/2020 (8:00 - 10:00) | 2/7/2020 (AM) | 02/07/2020 |
Corrections:
Miscellaneous/Other
Comment Only
02/07/2020
Residential areas approved. Parking ramp still needs rough-in and final inspections.
|
||||
Progress Inspection | Passed | 2/14/2020 (10:00 - 12:00) | 2/14/2020 (AM) | 02/14/2020 |
Hydro Test Start | Partial Pass | 2/18/2020 (8:00 - 10:00) | 2/18/2020 (AM) | 02/18/2020 |
Hydro Test End | Partial Pass | 2/18/2020 (10:00 - 12:00) | 2/18/2020 (AM) | 02/18/2020 |
Corrections:
Miscellaneous/Other
Comment Only
02/18/2020
Hydro of floor systems in northwest and southwest buildings approved.
|
||||
Fire Rough-in Inspection | Partial Pass | 3/3/2020 (10:00 - 12:00) | 3/3/2020 (AM) | 03/04/2020 |
Corrections:
Miscellaneous/Other
Comment Only
03/04/2020
Witness commissioning of fire pump. Passed per 3rd party engineer report.
|
||||
Fire Rough-in Inspection | Partial Pass | 3/17/2020 (8:00 - 10:00) | 3/24/2020 (AM) | 03/24/2020 |
Acceptance Test Inspection | Partial Pass | 03/24/2020 | ||
Corrections:
Miscellaneous/Other
Comment Only
03/24/2020
Testing of sprinkler water flow switches and tamper valves approved for Building A and B.
|
||||
Hydro Test Start | Passed | 3/25/2020 (8:00 - 10:00) | 3/25/2020 (AM) | 03/25/2020 |
Hydro Test End | Partial Pass | 3/25/2020 (10:00 - 12:00) | 3/25/2020 (AM) | 03/25/2020 |
Corrections:
Miscellaneous/Other
Comment Only
03/25/2020
Hydro test of 6 dry systems for parking ramp and all wet standpipes approved.
|
||||
24-hr Air Test Start | Passed | 04/06/2020 | ||
24-hr Air Test Start | Passed | 04/06/2020 | ||
Air test for dry parking ramp systems | ||||
24-hr Air Test End | Passed | 04/07/2020 | ||
Acceptance Test Inspection | Passed | 04/07/2020 | ||
Corrections:
Miscellaneous/Other
Comment Only
04/07/2020
Dry system tripped tests passed for all 6 systems in parking ramp.
|
||||
Fire Inspection Final | Passed | 6/24/2020 (8:00 - 10:00) | 6/24/2020 (AM) | 06/24/2020 |
Hydro Test End | Passed | 06/24/2020 | ||
Fire Rough-in Inspection | Passed | 08/27/2020 |