PRFS201903796
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Fire Rough-in Inspection | Partial Pass | 5/6/2019 (12:30 - 2:30) | 5/6/2019 (PM) | 05/06/2019 |
Corrections:
Miscellaneous/Other
Comment Only
05/06/2019
Partial Rough in approved of second-floor changing areas and lounge area
|
||||
Fire Rough-in Inspection | Partial Pass | 5/16/2019 (7:00 - 8:00) | 5/16/2019 (AM) | 05/16/2019 |
Corrections:
Miscellaneous/Other
Comment Only
05/16/2019
Rough in approved for Phase II
|
||||
Fire Inspection Final | Partial Pass | 6/6/2019 (8:00 - 10:00) | 6/6/2019 (AM) | 06/06/2019 |
Corrections:
Miscellaneous/Other
Comment Only
06/06/2019
Partial final approved for Phase II
|
||||
Fire Rough-in Inspection | VOID | 6/6/2019 (8:00 - 10:00) | 6/6/2019 (AM) | 06/06/2019 |
Fire Inspection Final | Partial Pass | 7/30/2019 (12:30 - 2:30) | 7/30/2019 (PM) | 07/30/2019 |
Corrections:
Miscellaneous/Other
Comment Only
07/30/2019
Final approved for Phase III
|
||||
Rough In Inspection | Partial Pass | 10/09/2019 | ||
Corrections:
Miscellaneous/Other
Comment Only
10/09/2019
First floor handbag area approved to cover
|
||||
Fire Inspection Final | Partial Pass | 10/28/2019 (8:00 - 10:00) | 10/28/2019 (AM) | 10/31/2019 |
Corrections:
Miscellaneous/Other
Resolved
10/31/2019
Final approved for Phase III
|
||||
Miscellaneous/Other
Comment Only
10/31/2019
Partial Final approved. Need to final Channel 1st floor area.
|
||||
Rough In Inspection | Passed | 11/05/2019 | ||
Fire Inspection Final | Passed | 11/05/2019 |