Fire Rough-in Inspection | Failed | 9/24/2019 (8:00 - 10:00) | 9/24/2019 (AM) | 09/24/2019 |
Corrections:
Miscellaneous/Other
Carried Forward
09/24/2019
Pipe on 2nd floor not installed per plan.(3" called for 2" installed).
Sprinkler contractor shall be on site for future inspection and designer shall submit updated drawings and hydraulic calculations when changes are made to original plan.
If flex-head pipe to be installed provide manufacturer installation information and updated hydraulic calculation to account for the flexible pipe.
|
||||
Fire Rough-in Inspection | Partial Pass | 10/2/2019 (8:00 - 10:00) | 10/2/2019 (AM) | 10/02/2019 |
Corrections:
Miscellaneous/Other
Resolved
10/02/2019
Pipe on 2nd floor not installed per plan.(3" called for 2" installed).
Sprinkler contractor shall be on site for future inspection and designer shall submit updated drawings and hydraulic calculations when changes are made to original plan.
If flex-head pipe to be installed provide manufacturer installation information and updated hydraulic calculation to account for the flexible pipe.
|
||||
Miscellaneous/Other
Comment Only
10/02/2019
Partial rough in only. Approved for bulk pipe.
|
||||
Fire Rough-in Inspection | Partial Pass | 11/26/2019 (12:30 - 2:30) | 11/26/2019 (PM) | 11/26/2019 |
Hydro Test Start | Passed | 12/18/2019 (8:00 - 10:00) | 12/18/2019 (AM) | 12/18/2019 |
Hydro Test End | Passed | 12/18/2019 (10:00 - 12:00) | 12/18/2019 (AM) | 12/18/2019 |
Fire Inspection Final | Not Ready | 3/12/2020 (12:30 - 2:30) | 3/12/2020 (PM) | 03/16/2020 |