PRFS201910311
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Fire Rough-in Inspection | Partial Pass | 1/16/2020 (8:00 - 10:00) | 1/16/2020 (AM) | 01/16/2020 |
Corrections:
Miscellaneous/Other
Comment Only
01/16/2020
Partial rough in approved for bulk pipe 1st floor office and training room areas. Still need to inspect flex drops once attached to ACT grid or other ceilings.
|
||||
Fire Rough-in Inspection | Partial Pass | 2/20/2020 (12:30 - 2:30) | 2/20/2020 (PM) | 02/21/2020 |
Corrections:
Miscellaneous/Other
Comment Only
02/21/2020
Rough in approved for hard lid kitchen and dayroom area.
|
||||
Hydro Test Start | Passed | 6/30/2020 (12:30 - 2:30) | 6/30/2020 (PM) | 06/30/2020 |
Contractor had to cancel inspections for 5/19/2020 as genral contractor poured concrete....near main drain. jsmidt 05/18/2020 9:27 AM | ||||
Hydro Test End | Passed | 6/30/2020 (2:30 - 3:30) | 6/30/2020 (PM) | 06/30/2020 |
Fire Inspection Final | Passed | 6/30/2020 (12:30 - 2:30) | 6/30/2020 (PM) | 06/30/2020 |
Contractor had to cancel inspections for 5/19/2020 as genral contractor poured concrete....near main drain. jsmidt 05/18/2020 9:27 AM |