PRFS202003349
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
24-hr Air Test Start | Pending | |||
24-hr Air Test End | Pending | |||
Acceptance Test Inspection | Pending | |||
Fire Inspection Final | Pending | |||
Fire Rough-in Inspection | Pending | |||
Fire Rough-in Inspection | Partial Pass | 11/19/2020 (10:00 - 12:00) | 11/19/2020 (AM) | 11/19/2020 |
Fire Rough-in Inspection | Partial Pass | 1/4/2021 (8:00 - 10:00) | 1/4/2021 (AM) | 01/19/2021 |
Fire Rough-in Inspection | Partial Pass | 1/19/2021 (10:00 - 12:00) | 1/19/2021 (AM) | 01/19/2021 |
Fire Rough-in Inspection | Partial Pass | 1/21/2021 (10:00 - 12:00) | 1/21/2021 (AM) | 01/19/2021 |
Fire Rough-in Inspection | Partial Pass | 2/8/2021 (8:00 - 10:00) | 2/8/2021 (AM) | 02/08/2021 |
Approved 1st floor units. Hallway to be tied in. Still working on great room and connection from existing building. | ||||
Fire Rough-in Inspection | Partial Pass | 2/17/2021 (8:00 - 10:00) | 2/17/2021 (AM) | 02/17/2021 |
Fire Rough-in Inspection | Partial Pass | 3/24/2021 (8:00 - 10:00) | 3/24/2021 (AM) | 03/24/2021 |
Hydro Test Start | Passed | 7/7/2021 (8:00 - 10:00) | 7/7/2021 (AM) | 07/12/2021 |
Hydro Test End | Passed | 7/7/2021 (10:00 - 12:00) | 7/7/2021 (AM) | 07/12/2021 |
Fire Rough-in Inspection | Partial Pass | 7/13/2021 (7:00 - 8:00) | 7/13/2021 (AM) | 07/13/2021 |
Fire Rough-in Inspection | Not Ready | 11/23/2021 (8:00 - 10:00) | 11/23/2021 (AM) | 11/23/2021 |
Fire Rough-in Inspection | Partial Pass | 11/29/2021 (7:00 - 8:00) | 11/29/2021 (AM) | 12/03/2021 |
Fire Rough-in Inspection | Partial Pass | 12/16/2021 (8:00 - 10:00) | 12/16/2021 (AM) | 12/17/2021 |
Fire Rough-in Inspection | Partial Pass | 1/4/2022 (10:00 - 12:00) | 1/4/2022 (AM) | 01/05/2022 |
Fire Rough-in Inspection | Partial Pass | 1/25/2022 (8:00 - 10:00) | 1/25/2022 (AM) | 01/25/2022 |
2nd & 3rd floor center area and sitting room. | ||||
Fire Rough-in Inspection | Partial Pass | 2/17/2022 (10:00 - 12:00) | 2/17/2022 (AM) | 02/17/2022 |
Ok to cover all with the exception of 362, 352, 336, 337 | ||||
Fire Rough-in Inspection | Partial Pass | 3/3/2022 (8:00 - 10:00) | 3/3/2022 (AM) | 03/03/2022 |
Fire Rough-in Inspection | Partial Pass | 3/17/2022 (8:00 - 10:00) | 3/17/2022 (AM) | 03/21/2022 |
Hydro Test Start | Partial Pass | 4/4/2022 (10:00 - 12:00) | 4/4/2022 (AM) | 04/05/2022 |
Hydro Test End | Partial Pass | 4/4/2022 (10:00 - 12:00) | 4/4/2022 (AM) | 04/05/2022 |
Hydro Test Start | Passed | 5/9/2022 (8:00 - 10:00) | 5/9/2022 (AM) | 05/09/2022 |
Hydro Test End | Passed | 5/9/2022 (10:00 - 12:00) | 5/9/2022 (AM) | 05/09/2022 |