Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Fire Rough-in Inspection | Partial Pass | 1/20/2021 (12:30 - 2:30) | 1/20/2021 (PM) | 01/20/2021 |
Fire Rough-in Inspection | Partial Pass | 1/28/2021 (12:30 - 2:30) | 1/28/2021 (PM) | 01/28/2021 |
Corrections:
Miscellaneous/Other
Comment Only
01/28/2021
2nd floor, south end rough in approved.
|
||||
Fire Rough-in Inspection | Partial Pass | 2/11/2021 (8:00 - 10:00) | 2/11/2021 (AM) | 02/11/2021 |
Corrections:
Miscellaneous/Other
Comment Only
02/11/2021
Partial rough in approved for rooms on 1st floor, south end .
|
||||
Fire Rough-in Inspection | Partial Pass | 2/22/2021 (10:00 - 12:00) | 2/22/2021 (AM) | 02/22/2021 |
Corrections:
Miscellaneous/Other
Comment Only
02/22/2021
Partial rough in. Approved for 4th and 3rd floor, north half.
Also advised to contractor to ensure sprinkler protection for trash/rec. chutes are sprinkler protected and have an isolation control valve and flow switch.
|
||||
Fire Rough-in Inspection | Partial Pass | 3/3/2021 (8:00 - 10:00) | 3/3/2021 (AM) | 03/04/2021 |
Fire Rough-in Inspection | Partial Pass | 3/23/2021 (8:00 - 10:00) | 3/23/2021 (AM) | 03/23/2021 |
Corrections:
Miscellaneous/Other
Comment Only
03/23/2021
Rough in approved for underground garage.
|
||||
Hydro Test Start | Passed | 4/21/2021 (10:00 - 12:00) | 4/21/2021 (AM) | 04/28/2021 |
Hydro Test End | Passed | 4/21/2021 (12:30 - 2:30) | 4/21/2021 (PM) | 04/28/2021 |
Acceptance Test Inspection | Passed | 08/03/2021 | ||
Fire Inspection Final | Passed | 08/03/2021 | ||
Fire Rough-in Inspection | Passed | 08/03/2021 |