PRFS202101505
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Fire Rough-in Inspection | Partial Pass | 4/7/2021 (8:00 - 10:00) | 4/7/2021 (AM) | 04/09/2021 |
5 and 4 phase 1 ok. | ||||
Fire Rough-in Inspection | Partial Pass | 5/4/2021 (8:00 - 10:00) | 5/4/2021 (AM) | 05/13/2021 |
Fire Rough-in Inspection | Partial Pass | 5/11/2021 (8:00 - 10:00) | 5/11/2021 (AM) | 05/13/2021 |
Fire Rough-in Inspection | Partial Pass | 6/1/2021 (8:00 - 10:00) | 6/1/2021 (AM) | 06/01/2021 |
Fire Rough-in Inspection | Partial Pass | 6/21/2021 (2:30 - 3:30) | 6/21/2021 (PM) | 06/22/2021 |
Fire Rough-in Inspection | Partial Pass | 6/28/2021 (12:30 - 2:30) | 6/28/2021 (PM) | 06/28/2021 |
Fire Rough-in Inspection | Partial Pass | 7/6/2021 (12:30 - 2:30) | 7/6/2021 (PM) | 07/13/2021 |
Fire Rough-in Inspection | Partial Pass | 8/20/2021 (8:00 - 10:00) | 8/20/2021 (AM) | 08/27/2021 |
Hydro Test Start | Passed | 11/17/2021 (8:00 - 10:00) | 11/17/2021 (AM) | 11/19/2021 |
Hydro Test End | Passed | 11/17/2021 (10:00 - 12:00) | 11/17/2021 (AM) | 11/19/2021 |
Acceptance Test Inspection | Passed | 12/08/2021 | ||
Fire Inspection Final | Passed | 12/08/2021 | ||
Fire Inspection Final | Passed | 11/4/2021 (8:00 - 10:00) | 11/4/2021 (AM) | 12/08/2021 |
Rough In Inspection | Passed | 12/08/2021 |